Alter Building 3 for Extreme Computing Facility

FA8751-19-B-A001

Q&A

Q1. Specification Section 05120 calls for the fabricator and the erector to be AISC certified. Can this be waived for qualified steel contractors?

A1. This requirement cannot be waived. Fabricator and erector must be AISC certified.