Attach_1_Specifications.pdf

PDF 4 MB Posted

Attached to
Alter Building 3 for Extreme Computing Facility Federal contract opportunity
Solicitation number
FA875119BA001
Issued by
Department of the Air Force Materiel Command Research Laboratory

About this file

Attachment 1 - Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Alter Building 3 for Extreme Computing Facility, newest first.
File Type Posted
Q&A_Extreme_Computing_Facility_Part_5.docx DOCX document
Solicitation_Amendment_FA875119BA0010001_SF_30.pdf PDF
Q&A_Extreme_Computing_Facility_Part_4.docx DOCX document
Q&A_Extreme_Computing_Facility_Part_3.docx DOCX document
Q&A_Extreme_Computing_Facility_Part_2.docx DOCX document
FINAL_SUBMISSION_SUBMITTAL_REGISTRY.pdf PDF
Colden_17641_Rome_AF_asbestos_lead_report.pdf PDF
Q&A_1_-__Extreme_Computing_Facility.docx DOCX document
Solicitation_-_FA875119BA001.pdf PDF
Attach_4_RRS_Form_31_Request_for_Visit_Authorization.pdf PDF
Attach_3_Wage_Decision_NY20190013.pdf PDF
Attach_2_Drawings.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT

COPYING, DISSEMINATION, OR DISTRIBUTION OF THIS DOCUMENT

TO UNAUTHORIZED RECIPIENTS IS PROHIBITED

Do not remove this notice Properly destroy or return documents when no longer needed.

PROJECT MANUAL

ALTER BUILDING 3 FOR

EXTREME COMPUTING FACILITY

PHASE 2 – ULDF 17-0302AE

OWNER: SUBMISSION:

FOR CONSTRUCTION

SPECIFICATIONS

DIVISION 00-31

ISSUE DATE:

December 12, 2018

ARCHITECT: PROJECT LOCATION:

AIR FORCE RESEARCH LABORATORY

ROME RESEARCH SITE

ROME, NY 13441

CONSULTANTS: PROJECT INFORMATION:

MEPFP ENGINEERING CONSULTANT:

ENVIRONMENTAL ENGINEERS:

COLDEN CORP.

A/E CONTRACT #.

OWNER PROJECT #:

NKB PROJECT #:

FA8751-16-D-0002

ULDF 17-0302AE

16340.06

PROJECT CERTIFICATION:

To the best of my knowledge, belief and professional judgment, the drawings and specifications which comprise the Construction Documents for the project are in compliance with applicable codes, including the latest editions of the International Building Code and NFPA 101.

NOT FOR

CONSTRUCTIN

AFRL – Rome NY PROJECT NR. ULDF 17-0302AE

ALTER BUILDING 3 FOR EXTREME COMPUTING FACILITY 12/12/2018

PHASE 2

TABLE OF CONTENTS 000100 - 1

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

DIVISION 0

000100 TABLE OF CONTENTS

000115 LIST OF DRAWING SHEETS

DIVISION 1 – GENERAL REQUIREMENTS

ROME AFRL PROJECT PROVISIONS:

010000 GENERAL REQUIREMENTS

011100 SUMMARY OF WORK

011101 ABBREVIATIONS AND SYMBOLS

013529 SAFETY, FIRE PROTECTION AND HEALTH

015001 ENVIRONMENTAL PROTECTION

015613 TEMPORARY BARRIERS AND ENCLOSURES

011000.1 SUMMARY OF WORK - SUPPLEMENTAL

013300 SUBMITTAL PROCEDURES

014000 QUALITY REQUIREMENTS

DIVISION 2 - EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION

028200 ASBESTOS ABATEMENT

DIVISION 3 – CONCRETE

033000 CAST-IN-PLACE CONCRETE

DIVISION 4 – MASONRY

042200 CONCRETE UNIT MASONRY

DIVISION 5 - METALS

051200 STRUCTURAL STEEL FRAMING

054000 COLD FORMED METAL FRAMING

055000 EQUIPMENT SUPPORT SYSTEM

055213 PIPE AND TUBE RAILINGS

055313 BAR GRATINGS

DIVISION 6 – WOOD, PLASTICS AND COMPOSITES

061053 MISCELLANEOUS ROUGH CARPENTRY

DIVISION 7 – THERMAL AND MOISTURE PROTECTION

079200 JOINT SEALANTS

079219 ACOUSTIC JOINT SEALANTS

DIVISION 8 – OPENINGS

081213 HOLLOW METAL DOORS AND FRAMES

084113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

087100 DOOR HARDWARE

088000 GLAZING

TABLE OF CONTENTS 000100 - 2

DIVISION 9 – FINISHES

092216 NON-STRUCTURAL METAL FRAMING

092900 GYPSUM BOARD

095100 ACOUSTICAL PANEL CEILING SYSTEM

095113 INDIRECT LIGHT COVE PERIMETER SYSTEM

096513 RESILIENT BASE AND ACCESSORIES

096700 ESD RESINOUS FLOORING

096800 ESD CARPET TILE

096933 LOW-PROFILE FIXED HEIGHT ACCESS FLOORING

099123 INTERIOR PAINTING

DIVISION 10 – SPECIALTIES

101423 PANEL SIGNAGE

102313 GLASS PARTITIONS SYSTEMS

104413 FIRE PROTECTION CABINETS

104416 FIRE EXTINGUISHERS

DIVISION 12 - FURNISHINGS

123530 RESIDENTIAL CASEWORK

123661 SIMULATED STONE COUNTERTOPS

DIVISION 21 – FIRE SUPPRESSION

211313 FIRE SUPPRESSION SPRINKLER SYSTEMS

DIVISION 22 – PLUMBING

220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

220553

220719

221429

IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

PLUMBING PIPING INSULATION

SUMP PUMPS

223000

223300

PLUMBING – GENERAL

ELECTRIC, DOMESTIC WATER HEATERS

224000

226113

226119

PLUMBING FIXTURES

COMPRESSED-AIR PIPING

COMPRESSED-AIR EQUIPMENT

DIVISION 23 – HEATING, VENTILATING AND AIR CONDITIONING

230513

230514

230516

230517

COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

ELECTRIC WIRING FOR HVAC EQUIPMENT

EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

SLEEVE AND SLEEVE SEALS FOR HVAC

230518 ESCUTCHEONS FOR HVAC PIPING

230519 METERS AND GAGES FOR HVAC PIPING

230523 GENERAL DUTY VALVES FOR HVAC PIPING

230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

230593

230713

TESTING, ADJUSTING, AND BALANCING FOR HVAC

DUCT INSULATION

TABLE OF CONTENTS 000100 - 3

230719

230900

HVAC PIPING INSULATION

INSTRUMENTATION AND CONTROL FOR HVAC

232113 HYDRONIC PIPING

232116

232123

232923

HYDRONIC PIPING SPECIALITIES

HYDRONIC PUMPS

VARIABLE-FREQUENCY MOTOR CONTROLLERS

233113 METAL DUCTS

233300 AIR DUCT ACCESSORIES

233413

233600

AXIAL HVAC FANS

AIR TERMINAL UNITS

233713

234100

235313

237313

238123

238214

238413

239119

DIFFUSERS, REGISTERS AND GRILLES

PARTICULATE AIR FILTRATION

FUME HOOD

INDOOR, SEMI-CUSTOM AIR-HANDLING UNIT

COOLANT DISTRIBUTION UNITS

CHILLED BEAMS

HUMIDIFIERS

FIXED LOUVERS

DIVISION 26 – ELECTRICAL

260519

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

260523 CONTROL-VOLTAGE ELECTRICAL POWER CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

260544 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

260923

262213

LIGHTING CONTROL DEVICES

LOW VOLTAGE DISTRIBUTION TRANSFORMERS

262416 PANELBOARDS

262500 ENCLOSED BUS ASSEMBLIES

262726 WIRING DEVICES

262816

263353

ENCLOSED SWITCHES

STATIC UNINTERRUPTIBLE POWER SUPPLY

265119 LED INTERIOR LIGHTING

265219 EMERGENCY AND EXIT LIGHTING

DIVISION 27 – COMMUNICATIONS

270526

270528

271100

271300

271500

271700

GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS

COMMUNICATIONS PATHWAYS SYSTEMS

COMMUNICATIONS EQUIPMENT ROOM FITTINGS

BACKBONE CABLING

HORIZONTAL CABLING

TESTING AND IDENTIFICATION

DIVISION 28 – FIRE ALARM

283111 DIGITAL, ADDRESSABLE, FIRE-ALARM SYSTEM

DIVISION 31 – EARTHWORK

312000 EARTH MOVING

TABLE OF CONTENTS 000100 - 4

THIS PAGE INTENTIONALLY LEFT BLANK

PHASE 2

LIST OF DRAWINGS 000115 - 1

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

DRAWING LIST

SHEET NUMBER SHEET NAME

GENERAL

G-001 COVER SHEET

STRUCTURAL

S-001 STRUCTURAL GENERAL NOTES

S-101 FOUNDATION PLAN

S-102 FRAMING PLAN

S-501 TYPICAL DETAILS

S-502 DETAILS

S-503 FOUNDATION SECTIONS, DETAILS, AND ELEVATIONS

S-504 FRAMING SECTIONS AND DETAILS

S-505 FRAMNG SECTIONS AND DETAILS

ARCHITECTURAL

A-001 GENERAL NOTES, SYMBOLS & ANNOTATIONS

A-002 PARTITION TYPES

A-003 CODE REVIEW

AD101 DEMOLITION FLOOR PLAN

AD102 CEILING & MEZZANINE DEMOLITION PLAN

AE101 FLOOR PLAN

AE102 MEZZANINE PLAN

AE103 FIRST FLOOR REFLECTED CEILING PLAN

AE104 MEZZANINE REFLECTED CEILING PLAN

AE105 BUILDING 2 MEZZANINE RELOCATION PLAN

AE301 BUILDING SECTIONS

AE302 WALL SECTIONS

AE401 ENLARGED PLANS & DETAILS

AE402 ENLARGED MEZZANINE STAIR PLAN & DETAILS

AE403 ENLARGED ACCESS STAIR PLAN & DETAILS

AE404 INTERIOR ELEVATIONS

AE405 INTERIOR ELEVATIONS

AE406 INTERIOR ELEVATIONS

AE407 STAIR SECTIONS

AE408 BUILDING 2 ENLARGED STAIR PLAN & SECTIONS

AE501 DETAILS

AE505 LABORATORY SECONDARY FRAMING SYSTEM PLAN

AE506 LABORATORY SECONDARY FRAMING SYSTEM AXONOMETRIC VIEWS

AE601 DOOR & HARDWARE SCHEDULES & DETAILS

AE602 ROOM FINISH SCHEDULE & FINISH LEGEND

AE603 WINDOW & GLAZING SCHEDULES & DETAILS

AE900 INTERIOR VIEWS

AI101 FURNITURE AND INTERIOR SIGNAGE PLAN

AI102 FLOOR FINISH PLAN

FIRE ALARM

FA001 SYMBOLS, NOTES AND ABBREVIATIONS

FAD001 FIRST FLOOR PLAN - DEMOLTITION

FA101 FIRST FLOOR PLAN

PHASE 2

LIST OF DRAWINGS 000115 - 2

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

FA102 MEZZANINE PLAN

FA103 MEZZANINE PLAN – BLDG 2

FIRE PROTECTION

FP001 SYMBOLS, NOTES AND ABBREVIATIONS

FPD101 FIRST FLOOR PLAN (LOWER LEVEL) - DEMOLITION

FP101 FIRST FLOOR PLAN

FP102 MEZZANINE PLAN (UPPER LEVEL)

FP103 MEZZANINE PLAN – BLDG 2

PLUMBING

P-001 SYMBOLS, NOTES AND ABBREVIATIONS

P-101 FIRST FLOOR PLAN

MECHANICAL

M-001 SYMBOLS, NOTES AND ABBREVIATIONS

MD101 FIRST FLOOR DEMOLITION PLAN

M-101 FIRST FLOOR DUCTWORK PLAN – BELOW MEZZANINE

M-102 FIRST FLOOR DUCTWORK PLAN – ABOVE MEZZANINE

M-103 FIRST FLOOR PIPING PLAN – BELOW MEZZANINE

M-104 FIRST FLOOR PIPING PLAN – ABOVE MEZZANINE

M-301 MECHANICAL SECTIONS

M-401 ENLARGED PARTIAL FIRST FLOOR PLAN

M-501 DETAILS

M-502 DETAILS

M-503 DETAILS

M-601 SCHEDULES

M-602 SCHEDULES

ELECTRICAL

E-001 SYMBOLS, NOTES AND ABBREVIATONS

ED101 FIRST FLOOR POWER PLAN- DEMOLITION

ED102 FIRST FLOOR LIGHTING PLAN- DEMOLITION

E-101 FIRST FLOOR POWER PLAN

ET101 FIRST FLOOR COMMUNICATIONS PLAN

E-102 FIRST FLOOR LIGHTING PLAN

E-103 MEZZANINE PLAN - BLDG 2

E-501 DETAILS

E-502 TELECOMUNICATIONS DETAILS

E-601 ONE-LINE DIAGRAM -DEMOLITION

E-602 ONE-LINE DIAGRAM

E-603 SCHEDULES

E-604 SCHEDULES

E-605 SCHEDULES

GENERAL REQUIREMENTS 010000 - 1

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

SECTION 010000 – GENERAL REQUIREMENTS

1.0 n/a – THIS SECTION IS SPECFIC TO EACH PROJECT

2.0 WORKING HOURS

A. The regular hours of work at the Information Directorate are 0700 to 1600 hours, Monday through Friday, excluding Federal holidays. The Government may restrict access to work sites to these hours and days. The Contractor shall consider all other hours as non- regular time and use the appropriate unit prices for tasks performed during those hours. In the technical/cost proposal submitted for each delivery order, the contractor shall clearly identify those items of work scheduled for accomplishment during non-standard time and include justification for the request. The contractor shall notify the Contracting Officer (CO) at least 48 hours in advance of any work performed during non-regular hours that requires inspection during accomplishment or that prevents inspection of previous work after accomplishment.

2.1. LEGAL HOLIDAYS

The Rome Research Site recognizes the following legal holidays:

New Year’s Day 1 January Martin Luther King’s Birthday Third Monday in January President’s Day Third Monday in February Memorial Day Last Monday in May Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veteran’s Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December

3.0 SECURITY REQUIREMENTS

A. The work to be done on this project is located in and around areas that are under the scrutiny of the Department of Defense Police assigned to the RRS Information Directorate. To gain access to the area(s) to examine the work to be done for job estimation purposes, arrangements must be made through the Contracting Office. Contractor personnel will be escorted into the area(s) for the purpose of project estimation.

B. When it has been determined which Contractor will accomplish the project, a Request for Visit Authorization Form (RRS Form 31) from the company, will be necessary prior to initial work commencement. The form needs to be signed by the Company President or Director of Human Resources. The form will also be used as the Entry Authority List. The Contractor will supply the form to Security (AFRL/RIOF) as instructed on the form. This information will be used to do a Local Files Check. This check will provide Drivers License Info, Wants & Warrants and Protection Orders and will also provide information on Illegal Immigration and suspected terrorist affiliations.

The Local Files Check will also be accomplished prior to work commencing. If the individual is not a US Citizen they will not be allowed within the complex or facilities. There will be no foreign national workers allowed on the Information Directore site. For work at DFAS (adjacent to RI), an additional Form SF 85 must be submitted for each contractor working in the facility.

Additional information regarding access to Air Force facilities and Government information tech-nology networks:

GENERAL REQUIREMENTS 010000 - 2

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

(a) Contractor employees requiring access to U.S. Air Force bases, AFRL facilities, and/or ac-cess to U.S. Government Information Technology (IT) networks in connection with the work on this contract/order must be U.S. citizens. For the purpose of base and network access, posses-sion of a permanent resident card (“Green Card”) does not equate to U.S. citizenship. This re-quirement does not apply to foreign nationals approved by the U.S. Department of Defense or U.S. State Department under international personnel exchange agreements with foreign govern-ments. Any waivers to this requirement must be granted in writing by the Contracting Officer prior to providing access. The above requirements are in addition to any other contract requirements related to obtaining a Common Access Card (CAC). .

(b) If an IT network/system does not require AFRL to endorse a Contractor’s application to said network/system in order to gain access, the organization operating the IT network/system is re-sponsible for controlling access to its system. If an IT network/system requires a U.S. Govern-ment sponsor to endorse the application in order to gain access to the IT network/system, AFRL will only endorse the following types of applications, consistent with the requirements above: (1) Contractor employees who are U.S. citizens performing work under this contract/order; or (2) Contractor employees who are non-U.S. citizens and who have been granted a waiver. Any addi-tional access restrictions established by the IT network/system owner apply.

C. Provide the Company’s phone number and a Project Leaders or Supervisor/Foremen cell-phone number is necessary for the Law Enforcement Desk Sergeant.

D. All facilities are entered using a magnetic media entry badge. Any personnel such as Supervisor/Foreman or Project Leader who may need building access for meetings etc. during the contract period can acquire a Local Contractor Entry Badge through the Division/Branch with oversight of the work. This will be accomplished with the RRS Form 110 (Unescorted Visitor Badge). The Security Visitation Office is located in the lobby of Bldg 3, West Wing. This badge will be worn at all times within the facility. These badges will be returned to the Contracting Officer’s Representative (COR) upon completion of the final inspection and Acceptance of Work.

Any badges lost during the period of work will be reported to Security as soon as possible.

E. Access to the Information Directorate complex is controlled by a Main Gate on Brooks Rd, located just west of the Otis & Brooks intersection. Identification for the contractor to enter with a vehicle will be an access list supported by the electronic badge issued. All commercial vehicles entering the gate will be searched. One-time deliveries can be escorted from the gate to delivery point by project personnel.

F. All commercial vehicles are searched prior to entry into the Information Directorate complex. Vehi-cle operators will be aware of the vehicle search pull-off area prior to approaching the Main Gate. A search of the vehicle will be conducted prior to its entry. All vehicles not needed for delivery of equipment or tools will be parked in the visitor parking area unless cleared through Security. There are no vehicles allowed within 25 meters (80 ft.) of the Information Directorate facilities.

G. All personnel should be aware that the Information Directorate site is property of the United States

Air Force. All personnel will follow all posted signage.

H. Contractor personnel will be notified by Information Directorate Police of any emergencies which would require an evacuation or work stoppage, such as an increase in the Force Protection Condi-tion.

I. Building/Room Keys: If the contractor needs access to area(s) that are locked (i.e. mechanical rooms, janitor’s closet, etc.), a request for entry of at least 2 working days prior to the need for ac-cess will be submitted to AFRL/RIOC construction representative. The area(s) will be provided on a daily basis. The area(s) will be locked down at the end of the day’s work.

GENERAL REQUIREMENTS 010000 - 3

J. Dumpsters: Per UFC 04-010-02, all construction dumpsters shall be located no less than 25 meters

(80 feet) from any facility, unless otherwise approved by Information Directorate Security. All dump-ster locations will be reviewed and evaluated on a case by case basis.

K. The 24 hour Desk Sgt can be reached at 315-330-2961.

4.0 SAFETY

A. The Contractor is responsible for compliance with all Federal, Air Force, and State safety and health regulations and is subject to Air Force safety, OSHA inspections, and conformance to Section 01 35 29 of this SOW, Safety, Fire Protection and Health while working at the Information Directorate Site

5.0 EXCAVATION PERMITS

A. The Contractor shall obtain excavation permits (Air Force form 103) prior to any excavation. The CO or COR shall assist the Contractor in obtaining the excavation permits. The Contractor shall provide drawings and details showing exact location and description of the type of excavation to be accomplished. Should any one of the coordination points indicate an additional underground utility or structure over and above those shown on the contract drawing either by sketch on the Contractor's drawing by field pointing or by flagging, the Contractor shall be responsible for protection of each of the items indicated. Should damage occur to any of the items indicated by the Contractor, contract drawings or coordinating agency to the permit, the Contractor shall be responsible for prompt repair of the damage to return the item to its original workable condition.

6.0 UTILITIES AND INTERRUPTION OF UTILITIES OR BUILDING SYSTEMS

A. Available water and electrical services may be used in this work at no cost to the Contractor.

The Contractor shall make arrangements for such services with the CO or COR. The Government will identify service tie-in points. Connections to these tie-in points shall be the responsibility of the Contractor.

B. The Government may not be held responsible for interruptions of utility service and will not be liable for Contractor delays, damages, or increased costs occasioned by any such interruption of service.

C. No utility services or building systems shall be interrupted to make connections, to relocate, or for any purpose without approval of the CO. Request for permission to shut down services or building systems shall be submitted in writing to the COR fourteen (14) days prior to date of proposed interruption. The request shall give the following information:

1. Location of shut-off.

2. Services affected.

3. Hour, date, and duration of shut-off.

D. Services shall not be interrupted until receipt of approval of the proposed hours and date from the CO. If utility services or building systems are damaged by the Contractor, the Contractor shall restore them within 24-hours.

7.0 EXISTING FACILITIES

GENERAL REQUIREMENTS 010000 - 4

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

A. The existing dimensions and locations shown on the applicable drawings are for approximation purposes only. Failure to verify the dimensions and locations will be at the Contractor’s risk and shall not relieve the Contractor from accomplishing the work required by the contract at the price awarded by the government. No additional costs will be allowed for contractor’s lack of coordination within the entire bid documents.

B. Any work which is required to be corrected or replaced due to lack of coordination with the entire contract documents will be done so at the Contractor's sole expense, not the Owner's.

8.0 SUBMITTALS

A. Submittals will be required on materials used under each proposal. Each submittal shall include information as described in the technical specifications or as shown on the drawings.

Submittals will accompany the contractor’s proposal on each project. All submittals shall include a Material Approval Submittal AF3000 cover sheet. Once an item of material or equipment has been approved, the Contractor will not be required to resubmit with the following exception: If, at any time during the duration of this contract, the Contractor desires to change materials from those originally approved, the new materials shall be resubmitted to and approved by the CO prior to incorporation into the project.

9.0 SCHEDULING WORK

A. Before any of the work is initiated the Contractor shall confer with the CO or COR and agree on a sequence of procedures; means of access to premises and buildings; space for storage of materials and equipment; delivery of materials and use of approaches; use of corridors, stairways, elevators, and similar means of communications; the location of partitions.

B. Delivery of materials and equipment shall be made with a minimal interference to Government op-erations and personnel.

C. The work shall, so far as practicable, be done in definite sections or divisions and confined to limited areas which shall be completed before work in other sections or divisions is begun.

a. Refer to section 0011100.1” Summary of Work Supplemental” for further work restrictions.

10.0 CONTRACTOR STORAGE

A. If agreed, a suitable outside storage area may be provided to the Contractor by the CO. Security shall be the responsibility of the Contractor. The Contractor shall keep the storage area neat, order-ly and clear of all debris. The Contractor shall not allow trash or other debris to be scattered from this area by wind or other means.

11.0 INSPECTION

A. Inspection of work by the Government will normally be accomplished along with the work as it pro-gresses. At the discretion of the CO, inspection may be directed at the completion of various phas-es of the work prior to initiation of any further work. The Contractor shall notify the COR that a phase will be complete at least 3 days in advance of the completion of each phase to be inspected.

END OF SECTION - GENERAL REQUIREMENTS

PHASE 2

SUMMARY OF WORK 011100 - 1

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

SECTION 011100 SUMMARY OF WORK

PART 1 - GENERAL

1.1 LOCATION

A. The work to be accomplished under this project is at the Rome Lab Research Site, Rome NY.

1.2 DESCRIPTION

A. The project consists of furnishing all labor, materials and equipment required for a broad range of demolition and construction work including but not limited to:

1. Renovation of existing building B3 to the extent as indicated on the Contract Drawings.

a. Building does not require abatement activities prior to demolition.

B. Refer also to Section “011100.1 Summary of Work – Supplemental” for more detailed descriptions regarding the project.

PART 2 - PRODUCTS

2.1 SUBMITTAL REQUIREMENTS

A. Submittal Requirements: Reproducible Shop drawings, manufacturer’s data, dated certifications and test reports, and samples constitute the project submittals. All submittals shall have an AF Form 3000 attached.

PART 3 - EXECUTION

A. Safety Requirements: It shall be the responsibility of the contractor to initiate and maintain such programs as to comply with the provisions of the Air Force Occupational Safety and Health Standards. These programs shall include the education and training of employees and subcontractors' personnel in the recognition, avoidance and prevention of unsafe conditions. See Section 01 35 29 for further instructions.

B. Disposal of Materials: Unless designated as salvageable, all waste materials generated by any work under this contract shall be handled, transported, stored and disposed of off Government property by the contractor at the end of each days work. Such materials shall be disposed of in accordance with applicable federal, state or local laws, ordinance or regulations. Spoils from excavation for marker bases may be spread evenly around the work area, but at no time will piles of soil be allowed in the work area. Coordination with the Environmental and Occupational Health office (EOH) is required before the generation and disposal of any Resource Conservation and Recovery Act (RCRA) ( http://www.access.gpo.gov/uscode/title42/chapter82_.html ) hazardous wastes.

a) Lead: The Contractor is responsible for ensuring surfaces coated with lead paint are properly remediated and disposed of IAW EPA protocols.

http://www.access.gpo.gov/uscode/title42/chapter82_.html

PHASE 2

SUMMARY OF WORK 011100 - 2

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

C. Fire Protection: The contractor shall be responsible for furnishing adequate and proper fire protection for all phases of the contract work.

D. Reference Standards and Publications: The standards and publications listed in each section of these specifications form part of these specifications to the extent referenced. The contractor shall conform to the provision of the dated issue of the listed standard or publication.

E. Clean-up: The contractor shall at all times, keep the construction area, including storage areas used by him, free from accumulation of waste materials or rubbish. Prior to completion of the work each day, remove from the construction site all waste materials or rubbish. Upon completion of the construction, the contractor shall leave the work premises in a clean, neat condition.

F. Pollution Control/Hazardous Substances: The contractor shall report any spill of oil or hazardous material to the EOH Office, and to take every reasonable precaution to prevent the spillage of oil or other hazardous substances. The Contractor will perform all work consistent with the requirements of all Federal, State and Local laws, rules and regulations pertaining to pollution control.

Additionally, Contractors using HAZMAT on this installation must comply with the procedures outlined in the RRS Hazardous Materials Management Plan (HMMP), section 2.4.4 (see below).

Any clarification of these procedures can be provided by the EOH Office.

{Excerpt from Rome Research Site Hazardous Materials Management Plan Section 2.4.4}

Pertaining to Contractor Usage

For the purposes of this contract, the “HMMP Team” and the “HAZMART” are the EOH Office.

2.4.4 HAZMAT Determination and Authorization Procedures for Contractors

2.4.4.1 Contractors using HAZMAT on Air Force installations must comply with the authorization procedures below.

2.4.4.1.1 If a contract is expected to require a contractor to bring or to use HAZMAT on an installation, the Contracting Office shall include both Federal Acquisition Regulation (FAR) Clause 52.223-3, Hazardous Material Identification and Material Safety Data, current edition, AFFARS Clause 5352.223-9003, and installation-specific contract requirements.

2.4.4.1.2 HMMP team representatives will provide the contracting office with installation-specific contract requirements (for inclusion in the contract) regarding how contractors must request AF Form 3952 authorization and report the required HAZMAT usage data to the HAZMART.

2.4.4.1.3 IAW FAR Clause 52.223-3, each offeror must provide the Contracting Office with a list of proposed HAZMAT that it plans to use on the installation during the performance of the contract.

Contractors must obtain Air Force authorization prior to using HAZMAT on an Air Force installation, and must report usage data to the HAZMART.

2.4.4.1.4 Contractors must submit to the Contracting Office the information and supporting documentation (including MSDS) necessary to obtain HAZMAT usage authorization. The Contracting Office will transmit the contractor submittal to the HAZMART for processing. No Class I ODS’s can be used.

2.4.4.1.5 For each contractor-identified HAZMAT that the HMMP team determines does not meet the Air Force definition of a HAZMAT, the RRS HMP requirements do not apply. The HMMP team will notify the Contracting Office that the contractor has authorization to bring and use that material on the installation without reporting usage.

PHASE 2

SUMMARY OF WORK 011100 - 3

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

2.4.4.1.6 For each contractor-identified HAZMAT that the HMMP team determines does meet the Air Force definition of a HAZMAT, the Air Force will require CE authorization and SE review of the AF Form 3952 information. The CE authorization is for environmental, fire protection concerns, and emergency response purposes. The SE review is “for information purposes only” (see AF Form 3952), and does not involve evaluation and approval of the contractor’s safety and health programs. The purpose of the SE review is to identify potential risks to government personnel and resources and advise CE and the Contracting Office on how to mitigate identified hazards from planned contractor HAZMAT usage.

2.4.4.1.7 The HAZMART ensures entry of the contractor supplied information into HMMS. This action includes the addition of the contractor to the AUL.

2.4.4.1.8 Report data on the HAZMAT used during the performance of the contract at intervals and in the format specified by the HMMP team. For the purposes of this contract, total gallons of each HAZMAT used must be reported.

2.4.4.1.9 If the contractor needs to bring a material on the installation that was not included in the original HAZMAT listing, the contractor must first notify the Contracting Office and then obtain prior authorization, if the HMMP team determines the material to be a HAZMAT.

END OF SECTION 011100

PHASE 2

SUMMARY OF WORK 011100 - 4

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

PHASE 2

ABBREVIATIONS AND SYMBOLS 011101 - 1

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

SECTION 011101 – ABBREVIATIONS AND SYMBOLS

MEASURE DESCRIPTION

1.0 DISTANCE

MM Millimeter IN Inch CM Centimeter FT Foot M Meter LF Linear Foot VLF Vertical Linear Feet YD Yard CLF 100 Linear Feet MLF 1000 Linear Feet MI Mile (Statute)

2.0 AREA

CM2 Square Centimeter SI Square Inch M2 Square Meter SF Square Foot HEC Hectare SY Square Yard KM2 Square Kilometer CSF 100 Square Feet CSY 100 Square Yards ACR Acre MI2 Square Mile

3.0 VOLUME

CC Cubic Centimeter CI Cubic Inch M3 Cubic Meters CF Cubic Feet CY Cubic Yard BF Board Feet MBF 1000 Board Feet

4.0 FLOW

CCS Cubic Centimeter/Sec CFM Cubic Ft/Minute CMM Cubic Meter/Minute MCF 1000 Cubic Ft/Minute

PHASE 2

ABBREVIATIONS AND SYMBOLS 011101 - 2

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

5.0 LIQUID

MEASURE DESCRIPTION

LIT Liter GAL Gallon (US)

6.0 WEIGHT

G Gram

OZ Ounce KG Kilogram LB Pound MT Metric Ton TON Ton (Short)

7.0 MISCELLANEOUS

BBL Barrel EA Each FLR Floor LAN Lane LS Lump Sum OPN Opening PCT Percent PR Pair RSR Riser SEA Seat SET Set SQ Square (Roofing) LD Load

END OF SECTION 011101

PHASE 2

SAFETY, FIRE PROTECTION AND HEALTH 013529 - 1

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

SECTION 013529 – SAFETY, FIRE PROTECTION AND HEALTH SPECIFICATION

PART 1 - GENERAL

1.1 SAFETY REQUIREMENTS

A. The contractor shall develop and implement a comprehensive written Safety and Occupational Health Program. The contractor will submit a safety plan within ten (10) calendar days after award of the contract that will implement a safety program that ensures protection of Government personnel and property. The contractor shall comply with U.S. Occupational Safety and Health Administration (OSHA) standards, program elements, explosive standards, and other safety and health requirements necessary for the protection of personnel, facilities, and equipment.

Acceptance of the contractor’s Safety and Occupational Health Plan only signifies that the plan generally conforms to the requirements of the contract. It does not relieve the contractor of the responsibility for providing employees with a safe and healthful work environment. The program will consist of, as a minimum:

1. Mishap reporting, as defined in paragraph B below.

2. A Safety Plan that addresses, as a minimum, the subjects listed in Section II -Safety Plan

Elements, and will be used during the performance of the work described in the contract.

The Safety Plan will be approved by the procuring safety office prior to commencement of any work described in this contract.

3. Routine and recurring surveillance of the procedures listed in the Safety Plan.

4. Competent personnel to provide surveillance of the Safety Plan.

5. Identification of segregated work site locations for operations that cannot be co-mingled with general industrial operations and the process for Contracting Officer approval of operations and changes at these specific sites.

6. Process for ensuring subcontractors comply with the safety provisions of this contract, as applicable.

1.2 MISHAP NOTIFICATION

A. The Contractor shall notify the contracting Safety Office and the CO within one (1) hour of all mishaps or incidents at or exceeding $2,000 (material + labor) in damage to DOD property entrusted by this contract. This notification requirement shall also include physiological mishaps/incidents. A written or email copy of this mishap/incident notification shall be sent within three calendar days to the CO, who will forward it to the Safety Office. For information not available at the time of initial notification, the Contractor shall provide the remaining information no later than 20 calendar days after the mishap, unless extended by the Contracting Officer.

Mishap notifications shall contain, as a minimum, the following information:

(a) Contract, Contract Number, Name and Title of Person(s) Reporting

(b) Date, Time and exact location of accident/incident

(c) Brief Narrative of accident/incident (events leading to accident/incident)

(d) Cause of accident/incident, if known

(e) Estimated cost of accident/incident (material and labor to repair/replace)

(f) Nomenclature of equipment and personnel involved in accident/incident

(g) Corrective actions (taken or proposed)

(h) Other pertinent information

PHASE 2

SAFETY, FIRE PROTECTION AND HEALTH 013529 - 2

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

B. If requested by Contracting Officer, the contractor shall immediately secure the mishap scene/damaged property and impound pertinent maintenance and training records, until released by the Procuring Safety Office.

1.3 CHANGES TO THE SAFETY PLAN

A. If the safety plan requires modification, the contractor shall submit the proposed modification, in writing, to the Contracting Officer.

1.4 SAFETY PLAN ELEMENTS

The contractor prepared Safety Plan shall clearly define procedures, personnel qualifications, facilities, required equipment, and other attributes necessary to fulfill the following elements. Each attribute shall meet or exceed the referenced benchmarks.

ELEMENT REQUIRED REFERENCED BENCHMARK

THE US AIR FORCE MISHAP PREVENTION

PROGRAM

AFI91-202 w/ AFMC Sup1

AIR FORCE OCCUPATIONAL AND

ENVIRONMENTAL SAFETY, FIRE

PROTECTION,AND HEALTH (AFOSH) PROGRAM

AFI91-301 w/AFMC Sup1

AIR FORCE CONSOLIDATED OCCUPATIONAL

SAFETY STANDARD

AFOSHSTD91-501 w/AFMC Sup1

CIVIL ENGINEERING AFOSHSTD91-10

WELDING, CUTTING, AND BRAZING AFOSHSTD91-5, NFPA 410, NFPA 51B

INTERIOR SPRAY FINISHING AFOSHSTD91-17

CONFINED SPACES AFOSHSTD91-25

HYDROCARBON FUELS-- GENERAL AFOSHSTD91-38

COMMUNICATIONS CABLE, ANTENNA AND

COMMUNICATIONS-ELECTRONIC(C-E) SYSTEMS

AFOSHSTD91-50

DATA PROCESSING FACILITIES AFOSHSTD91-64

GENERAL INDUSTRIAL OPERATIONS AFOSHSTD91-66

MATERIALS HANDLING AND STORAGE

EQUIPMENT

AFOSHSTD91-46

AGRICULTURAL TRACTORS AND IMPLEMENT

ATTACHMENTS

AFOSHSTD91-54

THE US AIR FORCE TRAFFIC SAFETY PROGRAM AFI91-207

CHEMICAL SAFETY AFOSHSTD91-68

http://www.e-publishing.af.mil/pubfiles/af/91/afi91-202/afi91-202.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afi91-301/afi91-301.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afoshstd91-501/afoshstd91-501.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afoshstd91-10/afoshstd91-10.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afoshstd91-5/afoshstd91-5.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afoshstd91-17/afoshstd91-17.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afoshstd91-25/afoshstd91-25.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afoshstd91-38/afoshstd91-38.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afoshstd91-50/afoshstd91-50.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afoshstd91-64/afoshstd91-64.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afoshstd91-66/afoshstd91-66.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afoshstd91-46/afoshstd91-46.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afoshstd91-54/afoshstd91-54.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afi91-207/afi91-207.pdf http://www.e-publishing.af.mil/pubfiles/af/91/afoshstd91-68/afoshstd91-68.pdf

PHASE 2

SAFETY, FIRE PROTECTION AND HEALTH 013529 - 3

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

Electronic/Electrostatic Discharge MIL HDBK 263, T.O. 00-25-234 Sensitive (ESD) Components

Facility Fire Protection NAS 3306, AFI 32-2001, NFPA 13, 70, 72, NFPA 409, 410

Grounding and Bonding T.O. 00-25-172

NOTE: Contractor employees should be familiar with Operational Risk Management (ORM) processes. Further information on ORM is contained in AFI 90-901, Operational Risk Management (ORM) Program, AFPAM 90-902, Operational Risk Management (ORM) Guidelines and Tools, AFMCPAM 63-101(Acquisition) Risk Management and AFMCI 90-902, Operational Risk Management (ORM) Program.

END OF SECTION 013529

PHASE 2

SAFETY, FIRE PROTECTION AND HEALTH 013529 - 4

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

PHASE 2

ENVIRONMENTAL PROTECTION 015001 - 1

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

SECTION 015001 – ENVIRONMENTAL PROTECTION

PART I - GENERAL

1.1 SCOPE

A. The work covered by this section consists of furnishing all labor, materials and equipment and performing all work required for the prevention of environmental pollution during, and as the result of, construction operations under this contract except for those measures set forth in other Technical Provisions of these specifications.

B. For the purpose of this specification, environmental pollution is defined as the presence of chemical, physical, or biological elements or agents which adversely affect human life; affect other species of importance to man or degrade the ability of the environment for aesthetic and recreational purposes. The control of environmental pollution requires consideration of air, water and land, and involves noise, solid waste-management and management of radiant energy and radioactive materials, as well as other pollutants.

1.2 APPLICABLE REGULATIONS

A. In order to prevent, and to provide for abatement and control of, any environmental pollution arising from the construction activities of the contractor in the performance of this contract, the contractor shall comply with all applicable Federal, State and local laws, and regulations concerning environmental pollution control and abatement.

1.3 NOTIFICATION

A. The Contracting Officer will notify the contractor in writing of any noncompliance with the foregoing provisions and the action to be taken. The contractor shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the contractor, shall be deemed sufficient for the purpose.

1.4 IMPLEMENTATION

A. Prior to commencement of the work, the contractor will meet with representatives of the Contracting Officer to develop mutual understandings relative to compliance with this provision and administration of the environmental pollution control program.

1.5 REPORTING OF HAZARDOUS MATERIALS BY CIVILIAN CONTRACTORS

A. In accordance with FAR Clause 52.223-3, each Contractor must provide the Contracting Office (CO) with a list of proposed Hazardous Materials (HAZMAT) that it plans to use on the installation during the performance of the contract. IAW AFI 32-7086, contractors must obtain Air Force authorization prior to using HAZMAT on an Air Force installation, and must report usage data to the Environmental and Occupational Health Office (RIOCV). This includes fuels used to run generators and other construction/maintenance equipment.

1. Contractors shall submit through the CO to RIOCV, Safety Data Sheets (formerly known as Material Safety Data Sheets or MSDS’s), for all potentially hazardous materials/products that will be brought on to the installation.

PHASE 2

ENVIRONMENTAL PROTECTION 015001 - 2

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

2. RIOCV will review all potentially hazardous materials and identify the materials deemed as HAZMAT that require tracking. RIOCV may remove any materials from consideration for use by the Contractor that contain ingredients prohibited buy the AF or other regulatory agency.

3. RIOCV will communicate to the COR the list of HAZMAT that will require AF-EESOH-MIS tracking. Those materials will require the completion of one Hazardous Materials Worksheet per HAZMAT by the Contractor (except for portions reserved by RIOCV). RIOCV will provide the Hazardous Material Worksheet to the Contractor and can assist the Contractor with this documentation if requested.

4. RIOCV will complete their portion on the Hazardous Material Worksheet and load all information from the Worksheets into the AF-EESOH-MIS data system. The Contractor will also retain a copy of their Hazardous Material Worksheet for the duration of the specified project.

5. If the Contractor needs to bring a material on the installation that was not included in the original HAZMAT listing, the Contractor must first notify the CO and then obtain prior authorization, if RIOCV determines the material to be a HAZMAT.

6. The Contractor will submit a Contractor Material Usage Data Sheet provided by RIOCV to the CO once per month for contracts over 60 days. For contracts less than 60 days, a Material Usage Data Sheet will be submitted by the Contractor to the CO at the completion of the contract.

7. The CO will provide a copy of the Usage Data Sheet to RIOCV.

8. Any HAZMAT brought on site for the contract and not used in its entirety will be removed from the installation by the Contractor. If HAZMAT can be used in another contract at this installation, please contact RIOCV for assistance.

9. RIOCV is ready to assist the CO and Contractor in any way to simplify and expedite this reporting and tracking procedure. Please contact RIOCV (315-330-2098) with any questions.

1.06 UNIVERSAL WASTE

A. Special considerations must be made for any light bulbs and ballasts removed during the project.

B. RIOCV will provide boxes and protective material (i.e. bubble wrap), for the contractor to place the old light bulbs in. The contractor shall not dispose of these light bulbs; RIOCV must dispose of them in accordance with "Universal Waste" regulations.

C. In addition, the contractor shall not dispose of any light ballasts removed during this project. The contractor should stage the ballasts for processing and disposal by RIOCV.

D. RIOCV must be notified/consulted if the contractor encounters or generates any hazardous or potentially hazardous waste (i.e. broken light bulbs, mercury containing thermostats). The contractor shall never assume that generated wastes are hazardous. The contractor shall not dispose of any hazardous wastes, or sign hazardous waste manifests, on behalf of the government.

END OF SECTION 015001

PHASE 2

TEMPORARY BARRIERS AND ENCLOSURES 015613 - 1

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

SECTION 015613 - TEMPORARY BARRIERS AND ENCLOSURES (DUST PROTECTION)

PART 1 - DESCRIPTION OF WORK

1.1 This specification covers the protection of work areas by the furnishing and installation of a temporary framework covered by polyethylene sheeting around the area where work is being performed or around the area that requires protection.

PART 2 - PRODUCTS

2.1 FRAMEWORK

A. Shall be of non-combustible construction- sturdy fire-rated wood or metal composition.

2.2 POLYETHELENE

A. Film shall comply with ASTM D 2103, shall have a minimum density of 0.910, and an impact strength greater than 70.

2.3 Adhesive Tape [for sealing seams and edges]

A. Shall meet the polyethylene manufacturer's recommendations.

2.4 Sealing Compound

A. Shall comply with recommended practices for use of latex compounds as prescribed by ASTM C 790.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Dust protection enclosures shall be installed according to the manufacturer's recommendations.

B. Confirm assembly and location requirements with the Owner prior to installation. Coordinate all proposed and required locations in advance for acceptance and approval.

C. Comply with standards and code requirements for erecting structurally adequate barricades.

Paint with appropriate colors, graphics, and warning signs to inform personnel and occupants of the potential hazard involved.

PHASE 2

TEMPORARY BARRIERS AND ENCLOSURES 015613 - 2

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

3.2 REPAIRS

A. Any accidental penetrations of the enclosures shall be repaired swiftly and adequately to prevent dust intrusion.

B. Completely restore and/or replace permanent construction that may have been damaged or impacted because of interference or connections with the temporary enclosure.

END OF SECTION 015613

PHASE 2

SUMMARY OF WORK - SUPPLEMENTAL 011100.1 - 1

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

SECTION 011100.1 – SUMMARY OF WORK SUPPLEMENTAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including all other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Phased construction.

4. Work by Owner.

5. Work under separate contracts.

6. Future work.

7. Purchase contracts.

8. Owner-furnished products.

9. Contractor-furnished, Owner-installed products.

10. Access to site.

11. Coordination with occupants.

12. Work restrictions.

13. Specification and drawing conventions.

14. Miscellaneous provisions.

B. Related Requirements:

1. Section 010000 “General Requirements” for limitations and procedures, including but not limited to, governing temporary use of Owner's facilities.

1.3 PROJECT INFORMATION

A. Project Identification: ALTER BUILDING 3 FOR EXTREME COMPUTING FACILITY, ULDF 17-0302AE

B. Project Location: Rome AF Labs Research Site, Rome, NY.

C. Owner: Rome AF Research Lab.

1. Owner's Representative: TBD.

D. Architect: N.K Bhandari, Architecture & Engineering, P.C.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists, but not necessarily be limited to, the following:

1. Alterations to existing building B3 to the extent as indicated on the Contract Drawings.

2. Building requires removal of existing steel elements that may contain lead based paint.

PHASE 2

SUMMARY OF WORK - SUPPLEMENTAL 011100.1 - 2

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice properly destroy or return documents when no longer needed

B. Type of Contract:

1. Project will be constructed under a single prime contract.

1.5 PHASED CONSTRUCTION

A. The Work shall be conducted in one phase.

B. Before commencing Work, submit an updated copy of Contractor's construction schedule showing the sequence, commencement and completion dates, and move-out and -in dates of Owner's personnel for the Work.

1.6 WORK BY OWNER

A. General: Cooperate fully with Owner so work may be carried out smoothly, without interfering with or delaying work under this Contract or work by Owner. Coordinate the Work of this Contract with work performed by Owner.

1.7 OWNER-FURNISHED PRODUCTS

A. Owner will furnish products indicated. Unless otherwise noted, the Work includes receiving, unloading, handling, storing, protecting, and installing Owner-furnished products and making building services connections.

B. Owner-Furnished Products: Miscellaneous fixtures, furniture and equipment.

1.8 ACCESS TO SITE

A. General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.

B. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

C. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations to areas where work is permitted.

2. Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times.

Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.