Attachment_7_-_DIB_Development_5th_Edition_-Cost_Format_-Final.xlsx
XLSX spreadsheet 67 KB Posted
- Attached to
- DIB Development 5th Edition FINAL RFP FA873017R0024 Federal contract opportunity
- Solicitation number
- FA873017R0024
About this file
Correct version of Attachment 7 - DIB Development 5th Edition - Cost Format
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cover Page
Table of Contents
| Cost Format | Section L # |
| Summary | 5.3.4.1 |
| B-Table | 5.3.4.2 |
| Delivery Order 01- Initial TRN | 5.3.4.3 |
| Sample Epic | 5.3.4.4 |
| LH Rates at BEQ | 5.3.4.5 |
| Price Track | 5.3.4.6 |
&"Times New Roman,Bold"&18&UTable of Contents
Summary
| Table 1- Delivery Order 01- Initial TRN | |||
| Contract | |||
| CLIN | Type | Description | Total Price |
| 0001 | LH | DMO Labor | $ - 0 |
| 0002 | NSP | DMO Data | |
| 0003 | CR | DMO Other Direct Costs | $ 5,000 |
| 0004 | CR | DMO Travel | $ 5,000 |
| Total Table 1 | $ 10,000 |
| Table 2- CR CLINs | |||
| CLIN | Type | Description | Total Price |
| 0003 | CR | DMO Other Direct Costs | $ 100,000 |
| 0004 | CR | DMO Travel | $ 100,000 |
| 0006 | CR | DCGS AF Other Direct Costs | $ 100,000 |
| 0007 | CR | DCGS AF Travel | $ 100,000 |
| 0009 | CR | DCGS ARMY Other Direct Costs | $ 100,000 |
| 0010 | CR | DCGS ARMY Travel | $ 100,000 |
| 0012 | CR | DCGS NAVY Other Direct Costs | $ 100,000 |
| 0013 | CR | DCGS NAVY Travel | $ 100,000 |
| 0015 | CR | DCGS USMC Other Direct Costs | $ 100,000 |
| 0016 | CR | DCGS USMC Travel | $ 100,000 |
| 0018 | CR | DCGS SOCOM Other Direct Costs | $ 100,000 |
| 0019 | CR | DCGS SOCOM Travel | $ 100,000 |
| 0021 | CR | DCGS NGA Other Direct Costs | $ 100,000 |
| 0022 | CR | DCGS NGA Travel | $ 100,000 |
| 0024 | CR | DCGS INTEL COMMUNITY Other Direct Costs | $ 100,000 |
| 0025 | CR | DCGS INTEL COMMUNITY Travel | $ 100,000 |
| Total Table 2 | $ 1,620,000 |
| Table 3- Sample Epic* | |||
| Type | Description | Total Price | |
| LH | Sample Epic | $ - 0 | |
| Total Table 3 | $ - 0 | ||
| *Table 2 - Sample Epic will not be included as part of the Total Evaluated Price |
| Table 4 - LH Rates at BEQ | |||
| Type | Description | TEP | |
| LH | CY1 | ERROR:#DIV/0! | |
| LH | CY2 | ERROR:#DIV/0! | |
| LH | CY3 | ERROR:#DIV/0! | |
| LH | CY4 | ERROR:#DIV/0! | |
| LH | CY5 | ERROR:#DIV/0! | |
| Total Table 4 | ERROR:#DIV/0! |
B-Table
| Labor Hour | |||||||
| B-Table for CLINs 0001, 0005, 0008, 0011, 0014, 0017, 0020 and 0023 | |||||||
| Prime Contractor | |||||||
| DO 01 - Initial TRN | CY1 | CY2 | CY3 | CY4 | CY5 | ||
| 1 February 2018 - 16 March 2018 | 17 March 2018-16 March 2019 | 17 March 2019-16 March 2020 | 17 March 2020-16 March 2021 | 17 March 2021-16 March 2022 | 17 March 2022-31 January 2023 | ||
| Labor Category | |||||||
| Engineer Level 6 – E6 | |||||||
| Engineer Level 5 – E5 | |||||||
| Engineer Level 4 – E4 | |||||||
| Engineer Level 3 – E3 | |||||||
| Engineer Level 2 – E2 | |||||||
| Engineer Level 1 – E1 | |||||||
| Technician Level 5 – T5 | |||||||
| Technician Level 4 – T4 | |||||||
| Technician Level 3 – T3 | |||||||
| Technician Level 2 – T2 | |||||||
| Technician Level 1 – T1 | |||||||
| Program Manager | |||||||
| General Administration |
| Subcontractor A | |||||||
| DO 01 - Initial TRN | CY1 | CY2 | CY3 | CY4 | CY5 | ||
| 1 February 2018 - 16 March 2018 | 17 March 2018-16 March 2019 | 17 March 2019-16 March 2020 | 17 March 2020-16 March 2021 | 17 March 2021-16 March 2022 | 17 March 2022-31 January 2023 | ||
| Labor Category | |||||||
| Engineer Level 6 – E6 | |||||||
| Engineer Level 5 – E5 | |||||||
| Engineer Level 4 – E4 | |||||||
| Engineer Level 3 – E3 | |||||||
| Engineer Level 2 – E2 | |||||||
| Engineer Level 1 – E1 | |||||||
| Technician Level 5 – T5 | |||||||
| Technician Level 4 – T4 | |||||||
| Technician Level 3 – T3 | |||||||
| Technician Level 2 – T2 | |||||||
| Technician Level 1 – T1 | |||||||
| Program Manager | |||||||
| General Administration | |||||||
| IDT A | |||||||
| DO 01 - Initial TRN | CY1 | CY2 | CY3 | CY4 | CY5 | ||
| 1 February 2018 - 16 March 2018 | 17 March 2018-16 March 2019 | 17 March 2019-16 March 2020 | 17 March 2020-16 March 2021 | 17 March 2021-16 March 2022 | 17 March 2022-31 January 2023 | ||
| Labor Category | |||||||
| Engineer Level 6 – E6 | |||||||
| Engineer Level 5 – E5 | |||||||
| Engineer Level 4 – E4 | |||||||
| Engineer Level 3 – E3 | |||||||
| Engineer Level 2 – E2 | |||||||
| Engineer Level 1 – E1 | |||||||
| Technician Level 5 – T5 | |||||||
| Technician Level 4 – T4 | |||||||
| Technician Level 3 – T3 | |||||||
| Technician Level 2 – T2 | |||||||
| Technician Level 1 – T1 | |||||||
| Program Manager | |||||||
| General Administration | |||||||
| *The Prime Contractor, Subcontractor, and IDT B-Tables will be incorporated in to the contract at time of award. |
Delivery Order 01-Initial TRN Delivery Order 01 (Initial TRN)
| Delivery Order 01 -Initial TRN | ||||||||||
| CLIN 0001 | ||||||||||
| 1 February 2018- 16 March 2018 | ||||||||||
| Prime Contractor | Subcontractor A | IDT A | Total Price | |||||||
| Labor Category | Wrap Rate | Hours | Total Price | Wrap Rate | Hours | Total Price | Wrap Rate | Hours | Total Price | |
| Engineer Level 6 – E6 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Engineer Level 5 – E5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Engineer Level 4 – E4 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Engineer Level 3 – E3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Engineer Level 2 – E2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Engineer Level 1 – E1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Technician Level 5 – T5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Technician Level 4 – T4 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Technician Level 3 – T3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Technician Level 2 – T2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Technician Level 1 – T1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Program Manager | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| General Administration | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Total CLIN 0001 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Sample Epic Sample Epic
| Sample Epic | ||||||||||
| 17 March 2018 - 16 March 2019 | ||||||||||
| Prime Contractor | Subcontractor A | IDT A | Total Price | |||||||
| Labor Category | Wrap Rate | Hours | Total Price | Wrap Rate | Hours | Total Price | Wrap Rate | Hours | Total Price | |
| Engineering Level 6 – E6 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Engineering Level 5 – E5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Engineering Level 4 – E4 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Engineering Level 3 – E3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Engineering Level 2 – E2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Engineering Level 1 – E1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Technician Level 5 – T5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Technician Level 4 – T4 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Technician Level 3 – T3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Technician Level 2 – T2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Technician Level 1 – T1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Program Manager | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| General Administration | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Total Sample Epic | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
LH Rates at BEQ Labor Hour Rates at BEQ
| CY1 | CY2 | CY3 | CY4 | CY5 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 17 March 2018-16 March 2019 | 17 March 2019 -16 March 2020 | 17 March 2020 - 16 March 2021 | 17 March 2021 - 16 March 2022 | 17 March 2022 - 31 January 2023 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Prime Contractor | Subcontractor A | IDT A | Total Price | # Rates Proposed | TEP | Prime Contractor | Subcontractor A | IDT A | Total Price | # Rates Proposed | TEP | Prime Contractor | Subcontractor A | IDT A | Total Price | # Rates Proposed | TEP | Prime Contractor | Subcontractor A | IDT A | Total Price | # Rates Proposed | TEP | Prime Contractor | Subcontractor A | IDT A | Total Price | # Rates Proposed | TEP | |||||||||||||||||||||||||||||||
| Labor Category | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | Wrap Rate | BEQ | BEQ Extension | |||||||||||||||
| Engineering Level 6 – E6 | $ - 0 | 1,008 | $ - 0 | $ - 0 | 1,008 | $ - 0 | $ - 0 | 1,008 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,008 | $ - 0 | $ - 0 | 1,008 | $ - 0 | $ - 0 | 1,008 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,008 | $ - 0 | $ - 0 | 1,008 | $ - 0 | $ - 0 | 1,008 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,008 | $ - 0 | $ - 0 | 1,008 | $ - 0 | $ - 0 | 1,008 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,008 | $ - 0 | $ - 0 | 1,008 | $ - 0 | $ - 0 | 1,008 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| Engineering Level 5 – E5 | $ - 0 | 2,081 | $ - 0 | $ - 0 | 2,081 | $ - 0 | $ - 0 | 2,081 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 2,081 | $ - 0 | $ - 0 | 2,081 | $ - 0 | $ - 0 | 2,081 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 2,081 | $ - 0 | $ - 0 | 2,081 | $ - 0 | $ - 0 | 2,081 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 2,081 | $ - 0 | $ - 0 | 2,081 | $ - 0 | $ - 0 | 2,081 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 2,081 | $ - 0 | $ - 0 | 2,081 | $ - 0 | $ - 0 | 2,081 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| Engineering Level 4 – E4 | $ - 0 | 1,163 | $ - 0 | $ - 0 | 1,163 | $ - 0 | $ - 0 | 1,163 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,163 | $ - 0 | $ - 0 | 1,163 | $ - 0 | $ - 0 | 1,163 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,163 | $ - 0 | $ - 0 | 1,163 | $ - 0 | $ - 0 | 1,163 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,163 | $ - 0 | $ - 0 | 1,163 | $ - 0 | $ - 0 | 1,163 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,163 | $ - 0 | $ - 0 | 1,163 | $ - 0 | $ - 0 | 1,163 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| Engineering Level 3 – E3 | $ - 0 | 1,160 | $ - 0 | $ - 0 | 1,160 | $ - 0 | $ - 0 | 1,160 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,160 | $ - 0 | $ - 0 | 1,160 | $ - 0 | $ - 0 | 1,160 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,160 | $ - 0 | $ - 0 | 1,160 | $ - 0 | $ - 0 | 1,160 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,160 | $ - 0 | $ - 0 | 1,160 | $ - 0 | $ - 0 | 1,160 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,160 | $ - 0 | $ - 0 | 1,160 | $ - 0 | $ - 0 | 1,160 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| Engineering Level 2 – E2 | $ - 0 | 3,076 | $ - 0 | $ - 0 | 3,076 | $ - 0 | $ - 0 | 3,076 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 3,076 | $ - 0 | $ - 0 | 3,076 | $ - 0 | $ - 0 | 3,076 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 3,076 | $ - 0 | $ - 0 | 3,076 | $ - 0 | $ - 0 | 3,076 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 3,076 | $ - 0 | $ - 0 | 3,076 | $ - 0 | $ - 0 | 3,076 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 3,076 | $ - 0 | $ - 0 | 3,076 | $ - 0 | $ - 0 | 3,076 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| Engineering Level 1 – E1 | $ - 0 | 1,730 | $ - 0 | $ - 0 | 1,730 | $ - 0 | $ - 0 | 1,730 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,730 | $ - 0 | $ - 0 | 1,730 | $ - 0 | $ - 0 | 1,730 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,730 | $ - 0 | $ - 0 | 1,730 | $ - 0 | $ - 0 | 1,730 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,730 | $ - 0 | $ - 0 | 1,730 | $ - 0 | $ - 0 | 1,730 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 1,730 | $ - 0 | $ - 0 | 1,730 | $ - 0 | $ - 0 | 1,730 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| Technician Level 5 – T5 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| Technician Level 4 – T4 | $ - 0 | 194 | $ - 0 | $ - 0 | 194 | $ - 0 | $ - 0 | 194 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 194 | $ - 0 | $ - 0 | 194 | $ - 0 | $ - 0 | 194 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 194 | $ - 0 | $ - 0 | 194 | $ - 0 | $ - 0 | 194 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 194 | $ - 0 | $ - 0 | 194 | $ - 0 | $ - 0 | 194 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 194 | $ - 0 | $ - 0 | 194 | $ - 0 | $ - 0 | 194 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| Technician Level 3 – T3 | $ - 0 | 405 | $ - 0 | $ - 0 | 405 | $ - 0 | $ - 0 | 405 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 405 | $ - 0 | $ - 0 | 405 | $ - 0 | $ - 0 | 405 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 405 | $ - 0 | $ - 0 | 405 | $ - 0 | $ - 0 | 405 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 405 | $ - 0 | $ - 0 | 405 | $ - 0 | $ - 0 | 405 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 405 | $ - 0 | $ - 0 | 405 | $ - 0 | $ - 0 | 405 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| Technician Level 2 – T2 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| Technician Level 1 – T1 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | 20 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| Program Manager | $ - 0 | 702 | $ - 0 | $ - 0 | 702 | $ - 0 | $ - 0 | 702 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 702 | $ - 0 | $ - 0 | 702 | $ - 0 | $ - 0 | 702 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 702 | $ - 0 | $ - 0 | 702 | $ - 0 | $ - 0 | 702 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 702 | $ - 0 | $ - 0 | 702 | $ - 0 | $ - 0 | 702 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 702 | $ - 0 | $ - 0 | 702 | $ - 0 | $ - 0 | 702 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| General Administration | $ - 0 | 70 | $ - 0 | $ - 0 | 70 | $ - 0 | $ - 0 | 70 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 70 | $ - 0 | $ - 0 | 70 | $ - 0 | $ - 0 | 70 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 70 | $ - 0 | $ - 0 | 70 | $ - 0 | $ - 0 | 70 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 70 | $ - 0 | $ - 0 | 70 | $ - 0 | $ - 0 | 70 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! | $ - 0 | 70 | $ - 0 | $ - 0 | 70 | $ - 0 | $ - 0 | 70 | $ - 0 | $ - 0 | - 0 | ERROR:#DIV/0! |
| Total Price @ BEQ | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ERROR:#DIV/0! | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ERROR:#DIV/0! | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ERROR:#DIV/0! | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ERROR:#DIV/0! | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ERROR:#DIV/0! |
Price Track
PRICE TRACK ($)
| Description | INITIAL PROPOSAL PRICE | Schedule Shift | Change in Labor Hours | Change in Wrap Rates | Change in Material | Change in Indirects | Total Changes | FPR PRICE |
| Delivery Order 01 - Intitial TRN (CLIN 0001) |
Sample Epic
LH Rates at BEQ
TOTAL PROPOSAL
Microsoft_Word_Document1.docx For Official Use Only (FOUO)
D-ILS Statement of Objectives 1st DRAFT V ((0) 13-May-2009
ATTACHMENT 7
COST FORMATS
COST/PRICE VOLUME III
DISTRIBUTED COMMON GROUND/SURFACE SYSTEM (DCGS) INTEGRATION BACKBONE (DIB) DEVELOPMENT 5th Edition
19 September 2017
Version: Original i
For Official Use Only (FOUO) image1.emf
File details come from the government source that posted it. Updated .