Solicitation FA8730-14-R-0017
Questions & Answers, 23 September 2014
Question Number
Document Reference
Title Questions Responses
1. Attachment 5 Total Evaluated Price (TEP) Worksheet
In the Excel file for the TEP Worksheet:
When I populate the Fixed Rates Table tab (with labor rates), the corresponding lines for CLIN X004 on the TEP Worksheet tab do not automatically populate the Unit Price or the EXT Total and both remain at $0.
a) Please confirm that we are to submit the TEP without populating those numbers and they will appear as $0 in our submitted proposal.
b) Confirm the Price Schedule of the RFP will have no price for this CLIN when submitted by the offeror.
c) Also confirm the Gov't will transfer the CLIN X004 amounts into the TEP and onto the Price Schedule of the RFP after our proposal is submitted.
There is no auto-populate for the extended total of CLIN X004.
Under the “TEP Worksheet” tab, the instructions for CLIN X004 indicate that the Government will calculate the total price for this CLIN IAW proposal evaluation instructions. Please see Attachment 8 (Section M), Paragraph 5.2(d) for additional information.
The TEP Worksheet and SF1449 values for CLIN X004 shall be written as $0 by each offeror. Attachment 7 (Section L) Paragraph 5.1.1(a) identifies that the rates proposed on the fixed rates table worksheet will be incorporated into the contract at the time of award. The TEP will be calculated by the Government for use in award determination purposes only.
2. Attachment 5 Total Evaluated Price (TEP) Worksheet
For the Not Separately Priced (NSP) CLIN's X005 and X006,
a) Please confirm that Unit Prices and EXT Total for these lines will be left blank in our submitted proposal. It is my understanding that the CLIN X001 prices will include the CLIN X005 and X006 deliverables.
b) Please confirm the Price Schedule of the RFP will have no prices for CLIN's X005 and X006 when submitted by the offeror.
CLINs X005 and X006 are both NSP and are not included in the TEP calculation.
However, CLIN X005 is NSP in support of CLIN X001, and CLIN X006 (CLS) is NSP in support of CLIN X004 (Special Projects).
Offerors will not provide individual pricing for CLINs X005 and X006. Please review Attachment 8 (Section M), Paragraph 5.0 for additional information
3. Attachment 5 Total Evaluated Price (TEP) Worksheet
In column B of the TEP Worksheet tab each CLIN is noted as FFP or
NSP.
CLIN X005 is NSP and X006 is FFP. Should X006 actually be noted as NSP?
Column B of the “TEP Worksheet” has been updated to reflect that CLIN X006 is NSP. Also, the “CLIN X004 BEQ” Worksheet has been updated to address missing labor categories. The revised Attachment 5 has been uploaded to the solicitation on