Amendment_Change_Log_(27_August_2014).pdf

PDF 76 KB Posted

Attached to
AN/FMQ-22 Automatic Meteorological Station (AMS) Contractor Logistics Support (CLS)
Solicitation number
FA8730-14-R-0017
Issued by

About this file

Amendment Change Log (27 August 2014)

View the file

Other files

File Type Posted
FMQ-22_CLS_RFP_QA_Responses_(7_Oct_14).pdf PDF
FMQ-22_CLS_RFP_Q A_Responses_(23_September_2014).pdf PDF
Attachment_5_-_Total_Evaluated_Price_Worksheet_(23_September_2014).xlsx XLSX spreadsheet
Attachment_7_-_Section_L_(17_September_2014).pdf PDF
FMQ-22_CLS_RFP_Q A_Responses_(17_September_2014).pdf PDF
FA8730-14-R-0017_Rev_1_September_2014.pdf PDF
FMQ-22_CLS_RFP_Q A_Responses_(11_September_2014).pdf PDF
Attachment_7_-_Section_L_(11_September_2014).pdf PDF
FMQ-22_CLS_RFP_Q A_Responses_(8_September_2014).pdf PDF
Exhibit_B_-_Separately_Priced_CDRL's_(Rev_2 _Sep_2014).pdf PDF
Exhibit_A_-_Not_Separately_Priced_CDRL's_(Rev_2_Sep_2014).pdf PDF
FMQ-22_CLS_RFP_QA_Responses_(21_August_2014).pdf PDF
FMQ-22_Spares_Warranty_Status.pdf PDF
FMQ-22_CLS_RFP_QA_Responses_(18_August_2014).pdf PDF
FMQ-22_CLS_RFP_QA_Responses_(26_August_2014).pdf PDF
Exhibit_B_-_Not_Separately_Priced_CDRL's_(19_August_2014).pdf PDF
Attachment_1_-_Past_Performance_Information_Sheet_(15_August_2014).docx DOCX document
Attachment_15_-_PSE_and_LRU_List_(22_August_2014).pdf PDF
Attachment_4_-_Roles_and_Responsibilities_Worksheet_(17_April_2014).xlsx XLSX spreadsheet
Attachment_14_-_Min_Max_purchase_quantities_(22_July_2014).pdf PDF
Attachment_5_-_Total_Evaluated_Price_Worksheet_(21_August_2014).xlsx XLSX spreadsheet
Attachment_7_-_Section_L_(21_August_2014).pdf PDF
FA8730-14-R-0017_Revision_1.pdf PDF
Attachment_11_-_Cross_Reference_Matrix_(22_August_2014).xlsx XLSX spreadsheet
Attachment_3_-_Client_Authorization_Letter_(17_April_2014).docx DOCX document
Attachment_6_-_Performance_Work_Statement_(19_August_2014).pdf PDF
Attachment_10_-_Government_Furnished_Property_List_(26_Aug_2014).pdf PDF
Attachment_2_-_Subcontractor_Teaming_Partner_Consent_Letter_(17_April_2014).docx DOCX document
Attachment_8_-_Section_M_(21_August_2014).pdf PDF
Exhibit_A_-_Not_Separately_Priced_CDRL's_(19_August_2014).pdf PDF
FMQ22_Spares_Usage__July_2013_-__June_2014_(15_August_2014).xlsx XLSX spreadsheet
FMQ-22_CLS_RFP_Q A_Responses_(15_August_2014).pdf PDF
Attachment_1_-_Past_Performance_Information_Sheet_(15_August_2014).pdf PDF
Attachment_6_-_Performance_Work_Statement_(12_August_2014).pdf PDF
FMQ-22_CLS_RFP_Q A_Responses_(12_August_2014).pdf PDF
Attachment_1_-_Past_Performance_Information_Sheet_(5_August_2014).pdf PDF
Exhibit_B_-_Separately_Priced_CDRL's_(30_July_2014).pdf PDF
Attachment_4_-_Roles_and_Responsibilities_Worksheet_(17_April_2014).xlsx XLSX spreadsheet
Attachment_10_-_Government_Furnished_Property_List_(20_June_2014).pdf PDF
Attachment_3_-_Client_Authorization_Letter_(17_April_2014).pdf PDF
Attachment_8_-_Section_M_(5_August_2014).pdf PDF
Attachment_5_-_Total_Evaluated_Price_Worksheet_(5_August_2014).xlsx XLSX spreadsheet
Attachment_14_-_Min_Max_purchase_quantities_(22_July_2014).pdf PDF
Attachment_2_-_Subcontractor_Teaming_Partner_Consent_Letter_(17_April_2014).pdf PDF
FA8730-14-R-0017_RFP_Without_Attachments_(7_August_2014).pdf PDF
Exhibit_A_-_Not_Separately_Priced_CDRL's_(30_July_2014).pdf PDF
Attachment_6_-_Performance_Work_Statement_(11_Apr_14).pdf PDF
Attachment_7_-_Section_L_(5_August_2014).pdf PDF
Attachment_11_-_Cross_Reference_Matrix_(17_April_2014).xlsx XLSX spreadsheet
FBO_Presolicitation_Posting_(1_August_2014).pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

27 August 2014 Change Log:

Attachment 1: No change (posted in MS Word vs. PDF)

Attachment 2: No change (posted in MS Word vs. PDF)

Attachment 3: No change (posted in MS Word vs. PDF)

Attachment 4: No change (posted in MS Excel vs. PDF)

Attachment 5:

• Corrected CLINs 500X period of performance (6 months vice 12 months)

• Corrected typos in CLIN X005

• CLIN X006 is no longer separately priced. The Exhibit B CDRLs are now Not Separately

Priced (NSP) under CLIN X004 (Special Projects).

Attachment 6:

• Section 3.3.1: Added CDRL A007 requirement

• Section 3.5.3: Added Associate Contractor Agreement (ACA)

• Section 5.2.2: Removed, Number 7. “Artifacts (supporting documentation) as required”

• Section 5.2.2: Added “Quarterly scans will be submitted to the PMO NLT three calendar days after scan completion”

• Section 5.2.6: Updated reference within section to refer to (Section 5.2.2 vice Section

5.2)

• Section 5.3.5: Replaced words “electronic means” with “CD\DVD media”

• Section 6.3: Revised to include maintenance and recalibration requirement

• Section 6.3.1: Edited to remove PSE and LRU component lists. Both items have been moved to Attachment 15

• Section 6.3.2: Updated IUID website and marking requirements

• Section 6.4: Specified delivery requirements for CONUS and OCONUS locations

• Section 6.8: Revised to reflect Type I Training updates would be separately negotiated if/when required under CLIN X004 (Special Projects).

• Section 6.9: Revised “the minimum inventory” to “a representation of what inventory may be available”

• Section 7.3.1: Updated reference within section to refer to (Section 5.2.6 vice 5.2.2)

• Section 7.3.4: Added sentence: “The level of support shall be negotiated under each

ECP.”

• Section 8.1: Added Appendix A that was previously referenced but not provided

Attachment 7:

• Removed CLIN X006 reference from Section 5.1.1(b)

• ACA requirements to Section 4.3.2.1(b)

Attachment 8:

• Corrected typo in Section 5.2(e)

• Revised Section 5.2(f) to reflect the NSP nature of the Exhibit B CDRLs

Attachment 9: Revised document title; Updated Section 2.1 content (HMP45 and WS425) and page breaks

Attachment 10: Part Quantities, MTBF, Manufacturer, and Shelf Life values updated

Attachment 11:

• Sub-Factor B, (d): Added CDRL A007 to Quality Assurance Program Plan CDRL reference

• Factor 2 (f): Description of CLIN X006 to reflect NSP

Attachment 12: No change (still posted in PDF)

Attachment 13: No change (posted in MS Excel vs. PDF)

Attachment 14: No change (still posted in PDF)

Attachment 15: Added new attachment to address PSE and LRU components that were previously addressed in PWS Section 6.3.1

Exhibit A:

• CDRL POCs updated

• CDRLs A005 and A007 updated

• CDRL A015 has been deleted and noted as “THIS CDRL HAS INTENTIONAL BEEN LEFT BLANK”

Exhibit B:

• CDRL POCs updated

• Page 3: information added - "NOTE: Implementation of this CDRL will only be required in conjunction with a separately priced order placed under CLIN X004 (Special Projects)."

SF1449:

• Revise solicitation response date/time to 4:00PM EDT on 1 October 2014

• CLIN X006 structure and content revised

• Update Provision AFLCMC(H)-K001 MP 5315.209-90(B) USE OF NON-GOVERNMENT ADVISORS

(Jan 2014) to include both Jacobs and MITRE contractor personnel

• Section J Table of Contents updated to reflect revised Exhibits and Attachments