This document contains questions and responses related to federal contract solicitation number FA8650-19-S-1110, titled Resolute Sentry - Architecture Refinement, Demonstration and Integration Systems (ARDIS) Call 06, issued by the Department of the Air Force Materiel Command Research Laboratory. The solicitation seeks proposals for a software solution at Technology Readiness Level 5 or higher for integration into a controlled unclassified laboratory environment to support subsequent integration and test activities of the program. Offerors may propose either a cost-type or firm-fixed-price contract. While a facility security clearance is not required for proposal evaluation or award, an elevated clearance would allow for added communications and support during later program integration and test phases. Questions regarding submission of a white paper or requests for a DoD SAFE link through which to submit should be directed to the contracting points of contact listed in the solicitation. The government will consider restricted rights for software previously developed with private funds.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question Answer CUI?

Attachments 11, 12, and 13 have embedded excel references in Appendix C.

Attachment 8 (page 8) says these should open, but we can’t open them.

Perhaps they are unresolved links and not embedded documents?

Please let me know how we can get this resolved.

Attachments 10, 11, and 12 have embedded Excel references. If you are unable to successfully open these references, please send an email to the Technical Points of

Contact listed in the Call to request the documents. These will be sent via DoDSafe.

No

Is an existing FCL required or a factor in evaluating proposals?

Is there anything you can clarify or more context you could provide regarding a not-yet-cleared proposal?

A facility security clearance level (FCL) will not be either a requirement or a factor in the evaluation of proposals.

The factors for evaluation are posted in the Call.

During the execution of the base effort, the acquired software will be integrated into a controlled unclassified laboratory environment. For subsequent integration and test activities of the program, an elevated FCL will allow for added communications and support.

No

Can you confirm that the resulting contracts from this data call must be cost-type contracts or can a contractor propose and receive a Firm-Fixed-Price contract under this solicitation?

As stated in the Resolute Sentry Call "The Air Force

Reserves the right to award the instrument best suited to the nature of research proposed. Accordingly, the

Government may award any appropriate contract type under the FAR and/or Other Transaction(s) pursuant to 10

U.S.C. 4023,based on the instrument deemed most appropriate." The Government will consider a FFP contract if proposed. The Government and Offeror must determine a milestone/deliverable/payment schedule that is mutually acceptable.

No

Please confirm that ATT 3, ATT 5, ATT 6 and ATT 7 are the documents that are required to submit with this white paper. If there are additional requirements, please list.

None of the attachments are required for submission of a white paper. Note that these attachments WILL be required if a full proposal submission is requested. No

Please direct me with where to find the Basic ARA. The document located at this link, on SAM.gov, is for the

Sooperfly Industry Day. SAM.gov. This is the link for

Resolute Sentry call 06 on SAM.gov. SAM.gov I do not see it listed there.

The Basic ARA can be found at the below link.

https://sam.gov/opp/2b4bbe8bb8c24b88831646c1bc8c8 d2c/view

No

Please reply with a DOD SAFE upload invite so we may securely submit our white paper.

Contractors who wish to submit a White Paper will need to request a DoD SAFE link from the Contracting POCs listed in the Call. DoD SAFE links are only active for 14 days. Please provide requests for the link starting 7

August.

No

Given the Government is requesting a TRL5+ software solution, would the Government consider restricted rights for software previously developed on private funds?

Yes, the government will consider restricted rights on the software. Our strong preference is unlimited rights, however the government will consider purpose rights

(without license fees) for the rapid integration, transition, and maintenance of the software.