PWS HVAC-9 SEP.docx
DOCX document 45 KB Posted
- Attached to
- HVAC CLEANING
- Solicitation number
- FA860126Q0141
About this file
This is a Performance Work Statement (PWS) for HVAC supply and return vent cleaning, sanitization, and mold-inhibitor treatment at the Air Force Institute of Technology (AFIT) Complex located at Wright-Patterson Air Force Base in Ohio. The contractor must perform comprehensive dry cleaning, anti-bacterial sanitization, and mold-inhibitor treatment on approximately 2,992 overhead drop-ceiling diffusers and vents (1,940 supply vents and 1,052 return vents) across six designated buildings (20640, 20641, 20642, 20643, 20644, and 20646), excluding three auditoriums. All work must comply with National Air Duct Cleaners Association (NADCA) standards and OSHA safety guidelines. The contractor must provide all labor, equipment, tools, materials, and transportation necessary to complete the work.
The contractor shall complete all work within 120 calendar days from contract start and may perform services during normal business hours (0700–1600 Monday–Friday), after hours, or weekends as directed by the facility manager, with 72-hour advance written approval required for non-standard hours. Work is prohibited on federal holidays. Key deliverables include a base access roster (14 days pre-start), site safety and hazard communication plan (10 days pre-start), product data sheets and safety data sheets for all chemicals (10 days pre-start, requiring formal approval before bringing products on base), and quality photo inspection logs upon completion of each building or zone. Quality assurance standards require zero defects in vent cleaning with 100% compliance to NADCA standards, 100% adherence to approved EPA-registered chemical products, and complete HEPA-vacuumed cleanup with zero residual damage. The contractor must protect all government property beneath work areas using drop cloths, comply with OSHA and Operational Security (OPSEC) guidelines, display high-visibility safety barricades, and obtain base access passes through the 88th Security Forces Squadron. The Government furnishes no equipment, tools, or materials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AFIT HVAC Cleaning Questions 15 SEP.docx | DOCX document | |
| Questions_Answers.docx | DOCX document | |
| PWS HVAC-2 SEP.docx | DOCX document | |
| PWS HVAC-2 SEP.docx | DOCX document | |
| Solicitation - FA860126Q0141.pdf | ||
| Attachment 2_SCA Wage Determination.pdf | ||
| REQUIRED INFORMATION SHEET.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
HVAC SUPPLY AND RETURN VENT CLEANING, SANITIZATION, AND MOLD-INHIBITOR TREATMENT
Air Force Institute of Technology (AFIT) Complex Wright-Patterson Air Force Base (WPAFB), Ohio
1.0 GENERAL INFORMATION & SCOPE OF WORK
1.1 Scope of Work
The Contractor shall furnish all management, supervision, labor, personnel, equipment, tools, materials, supplies, transportation, and incidentals necessary to perform comprehensive dry cleaning, anti-bacterial sanitization, and mold-inhibitor treatment for all designated drop-ceiling HVAC supply and return vents across the Air Force Institute of Technology (AFIT) Complex at Wright-Patterson Air Force Base (WPAFB), Ohio.
1.2 Primary Objective
The primary objective of this requirement is to restore and maintain optimal indoor air quality (IAQ) and hygiene throughout the facility air distribution system, eliminating surface dust, particulate build-up, and biological contaminants in compliance with National Air Duct Cleaners Association (NADCA) standards and Occupational Safety and Health Administration (OSHA) safety guidelines.
2.0 PLACE OF PERFORMANCE & WORKLOAD INVENTORY
2.1 Place of Performance
All work under this contract shall be performed at the Air Force Institute of Technology (AFIT) Campus located at:
· Address: 2950 Hobson Way, Area-B, Wright-Patterson AFB, OH 45433
· Covered Facilities (6 Buildings): Buildings 20640, 20641, 20642, 20643, 20644, and 20646.
2.2 Estimated Quantities
The estimated quantities of overhead drop ceiling diffusers/vents subject to this PWS are summarized below:
| Vent Classification |
| Estimated Quantity |
| Performance Scope |
| Drop Ceiling Supply Vents |
| ~1,940 Units |
| Dry dusting, sanitization, mold inhibitor application |
| Drop Ceiling Return Vents |
| ~1,052 Units |
| Dry dusting, sanitization, mold inhibitor application |
| Total Estimated Vents |
| ~2,992 Units |
| Full treatment across 6 designated campus buildings |
2.3 Excluded Areas
Work under this contract shall NOT be performed in the following designated auditorium spaces:
1. Kenny Auditorium
2. Bain Auditorium
3. CE Auditorium
3.0 SPECIFIC TASKS AND TECHNICAL REQUIREMENTS
The Contractor shall execute all tasks sequentially, professionally, and in a workmanlike manner:
3.1 Protection of Government Property
Prior to beginning overhead work in any room or hallway, the Contractor shall protect all underlying government property (floors, carpeting, desks, chairs, computer workstations, research apparatus, and wall finishes) using clean, durable drop cloths and protective containment shields. Any damage resulting from Contractor operations shall be repaired or replaced at the Contractor's sole expense.
3.2 Mechanical Vent Cleaning & Dry Dusting
· The Contractor shall dry dust and mechanically remove all accumulated surface dirt, particulate matter, lint, and debris from all designated drop-ceiling supply and return grilles and diffusers.
· The Contractor shall provide appropriate access equipment to reach all required ceiling interfaces. All designated work areas are accessible utilizing a standard commercial ladder rated for heights of 12 feet or less, in accordance with applicable occupational safety standards.
· All cleaning operations shall strictly adhere to the current NADCA ACR Standard (Assessment, Cleaning, and Restoration of HVAC Systems).
3.3 Anti-Bacterial Sanitization
· The Contractor shall sanitize all cleaned supply and return vents utilizing an EPA-registered, hospital-grade anti-bacterial solution certified safe for indoor commercial HVAC applications.
· The Contractor shall ensure complete surface contact and dwell time in accordance with manufacturer specifications.
3.4 Mold Prevention & Inhibitor Application
· Following sanitization, the Contractor shall apply an EPA-registered, commercial-grade mold and mildew inhibitor to all treated supply and return vents to suppress biological and microbial regrowth.
· Chemical products shall be non-corrosive, non-staining, and low in Volatile Organic Compounds (VOCs).
3.5 Post-Work Cleanup and Carpet Restoration
· Immediately upon completing overhead work in each zone or room, the Contractor shall clean and vacuum all affected carpet and hard flooring beneath treated vents using HEPA-filtered vacuum equipment to eliminate all fallen dust, debris, and residue.
· All work areas must be returned to a clean, usable condition prior to the conclusion of each work shift.
4.0 CONTRACTOR SUBMITTALS AND DELIVERABLES
The Contractor shall submit the following deliverables to the Contracting Officer (CO) and Program/Facility Manager:
| Deliverable ID |
| Submittal Title |
| Delivery Schedule |
| Approval Authority |
| D-001 |
| Base Access Roster |
| 14 calendar days prior to contract start |
| 88 SFS / Base Pass & ID |
| D-002 |
| Site Safety & HazCom Plan |
| 10 calendar days prior to contract start |
| Facility Manager |
| D-003 |
| Product Data Sheets & SDS |
| 10 calendar days prior to contract start |
| Facility Manager |
| D-004 |
| Quality Photo Inspection Log |
| Upon completion of each building/zone |
| Facility Manager |
Note: All chemical submittals (D-003) for cleaning, sanitizing, and mold-inhibiting agents must be formally approved prior to bringing products onto Wright-Patterson AFB.
5.0 QUALITY ASSURANCE & SERVICES SUMMARY (SS)
The Program/Facility Manager will evaluate contractor performance according to the following Services Summary table. A final joint inspection between the Contractor and the Facility Manager is mandatory prior to contract acceptance.
| Performance Objective |
| PWS |
Ref
| Performance Standard |
| Acceptable Quality Level (AQL) |
| Method of Surveillance |
| Vent Cleaning & Debris Removal |
| 3.2 |
| Vents completely free of visible dust and debris per NADCA ACR standard. |
| Zero defects on inspected sample; 100% compliance. |
| Inspection and acceptance of services upon completion of service. |
| Sanitization & Mold Inhibitor Application |
| 3.3, 3.4 |
| Complete chemical coverage using approved EPA-registered solutions. |
| 100% adherence to approved technical product data. |
| Inspection and acceptance of services upon completion of service. |
| Site Cleanup & Carpet Restoration |
| 3.1, 3.5 |
| All work areas and floors HEPA-vacuumed; zero residual dirt or damage. |
| Zero customer complaints; 100% clean upon turnover. |
| Inspection and acceptance of services upon completion of service. |
| Safety & Overhead Containment |
| 6.2 |
| Strict OSHA compliance, proper PPE, and high-visibility work signage. |
| Zero safety violations or unbarricaded work areas. |
| Inspection and acceptance of services upon completion of service. |
6.0 GENERAL OPERATIONAL & SECURITY REQUIREMENTS
6.1 Period of Performance (PoP)
The Contractor shall complete all work described in this PWS within 120 calendar days from the contract start date.
6.2 Hours of Operation
· Standard Hours: Performance may be scheduled during normal business hours (0700 and 1600 hours, Monday through Friday), after normal business hours, and/or on weekends, as directed by the facility manager or designated government representative. The contractor shall maintain sufficient scheduling flexibility to perform services during the period necessary to avoid disruption to classroom activities and facility operations.
· Federal Holidays: Work shall not be scheduled on recognized Federal Holidays (New Year's Day, Martin Luther King Jr. Day, Washington's Birthday, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day).
· After-Hours / Weekend Requests: Any work outside standard hours must be requested in writing and approved by the Program/Facility Manager at least 72 hours in advance.
6.3 Security & Base Access
· All contractor personnel must undergo identity vetting and obtain base access passes through the 88th Security Forces Squadron (88 SFS) Pass and Registration Office.
· Personnel shall display valid credentials at all times while on base.
· Contractor personnel shall adhere strictly to Operational Security (OPSEC) guidelines and remain within authorized work zones at the AFIT campus.
6.4 Safety & Hazard Communication
· All operations must comply with OSHA standards, AFOSH guidelines, and local environmental requirements.
· The Contractor shall place high-visibility safety barricades and overhead warning signs beneath active work areas to alert building occupants.
6.5 Government Furnished Property (GFP)
None. The Government will not provide tools, equipment, lifts, cleaning chemicals, or consumable materials for this contract.
7.0 SOLICITATION PROVISIONS & ATTACHMENTS
7.1 Pre-Proposal Site Visit
A formal pre-proposal site visit will be conducted at the AFIT Complex to allow prospective offerors to assess ceiling heights, diffuser types, and physical layouts. While attendance is optional, offerors are strongly urged to attend.
Failure to attend will not constitute grounds for subsequent claims or equitable adjustments.
File details come from the government source that posted it. Updated .