This is a Questions and Answers document issued by the Air Force Life Cycle Management Center (AFLCMC) at Wright-Patterson Air Force Base on 16 July 2026 in response to inquiries regarding Combined Synopsis/Solicitation FA8601-26-Q-0094 for temporary fencing rental and services.
The requirement involves the rental of approximately 19,000 linear feet of temporary fencing panels constructed of steel tubing with a 30-inch steel base (1-inch square tube and pipe approximately 5 inches), to be used along the Air Force Marathon event courses held annually on the third Saturday of September at Wright-Patterson AFB near Dayton, Ohio for safety and security purposes. Acceptable panel dimensions are 6-foot by 12-foot, provided they meet performance and security requirements. All panels must be powder-coated in white, red, blue, or black colors; powder coating is mandatory. The scope includes delivery, setup, installation, teardown, and removal services, with installation beginning Thursday prior to the marathon and removal commencing immediately following Saturday's completion of events. All costs for delivery, setup, operation, coordination, teardown, and removal must be included in the firm-fixed-price quotation and may be broken out as vendors determine. The base year and four option years should assume identical work requirements, quantities, and scope. Subcontracting is permitted but the awarded contractor remains fully responsible for all performance and quality. Personnel entering the installation must pass a background check, be U.S. Citizens, and have no felony charges. Travel costs may be included in the total price without additional fee or profit. Pricing evaluation will follow the Lowest Price Technically Acceptable criteria per FAR clause 52.212-2.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation QA 21 July 2026_Signed.pdf | ||
| Solicitation QA 20 July 2026_CO Signed.pdf | ||
| Solicitation Q_A 15 July 2026.pdf | ||
| Fencing QA.docx | DOCX document | |
| Fencing QA.docx | DOCX document | |
| CMMC_Quick Entry Guide for Contractors_Level 1.pdf | ||
| FA860126Q0094.pdf | ||
| WD 2015-4731 Rev29 dated 13MAY2026.pdf | ||
| Temporary Fencing Rental and Service PWS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
AIR FORCE LIFE CYCLE MANAGEMENT CENTER (AFLCMC) WRIGHT-
PATTERSON AIR FORCE BASE OHIO
16 July 2026
SUBJECT: Response to Inquiries regarding Combined Synopsis/Solicitation
FA8601-26-Q-0094, [AFM] Temporary Fencing Rental and Services
QUESTIONS AND ANSWERS
1. QUESTION: Please confirm that Solicitation FA8601-26-Q-0094 is a Department of the Air
Force (Air Force Materiel Command) procurement for temporary fencing rental and services at an Air Force Base. Requirements typically feature 6-foot or 8-foot chain-link fence panels, gates, and delivery/setup operations
ANSWER: Confirmed.
2. QUESTION: Please confirm that this requirement is for the rental of 19,000 linear feet of temporary fencing panels constructed of steel tubing, and associated services (setup, operation, and tear-down) to be placed along the annual Air Force Marathon event courses for safety and security purposes.
ANSWER: The information in the question is correct.
3. QUESTION: Please confirm that the feet of the panels shall be made of steel that is 30” long with a
1” square tube and pipe approximately 5” and welded to the top of each flat to create the base. Fence shall be placed in the square and round to create the interlocking panel.
ANSWER: The Government confirms.
4. QUESTION: Can you confirm that the Air Force Marathon is held annually on the third Saturday of September at Wright-Patterson Air Force Base near Dayton, Ohio. The race weekend typically takes place over two days, starting with shorter events on Friday and the main races on Saturday.
ANSWER: Confirmed.
5. QUESTION: The Performance Work Statement indicates that the temporary fencing panels should be powder coated and that white, red, blue, or black are acceptable colors. Is the powder-coated finish a mandatory requirement, or would non-powder-coated panels be considered acceptable if they otherwise meet the required specifications?
ANSWER: Yes, powder coating is a mandatory requirement
6. QUESTION: Would 6-foot by 12-foot temporary fence panels be considered acceptable, provided they meet the required performance and security needs?
ANSWER: Yes
7. QUESTION: We would also like to confirm the installation and removal schedule. Our understanding is that the initial fencing installation will begin on Thursday prior to the marathon, with any remaining installations completed as required for the event, and that fencing removal will begin immediately following the completion of the marathon events on Saturday. Could you please confirm that our understanding is correct
ANSWER: Yes, confirmed.
8. QUESTION: The solicitation references approximately 19,005 linear feet of barricades. Can the government confirm the required quantity and type of barricades required?
ANSWER: No, it is estimated. The requirement is temporary fencing panels for the barricades.
9. QUESTION: Are the required barricades specifically powder-coated crowd-control/event barricades?
ANSWER: Yes, that is correct.
10. QUESTION: Does the requirement include only rental of barricades, or are delivery, setup, installation, teardown, and removal services also required?
ANSWER: Delivery, setup, installation, teardown, and removal services are also required.
11. QUESTION: Are there any specific access requirements, security requirements, or base coordination procedures contractors should be aware of?
ANSWER: Yes, anyone entering the base must pass a background check. Additional access information can be found in the Performance Work Statement.
12. QUESTION: Are subcontractor arrangements acceptable for fulfilling portions of this requirement?
ANSWER: Yes, subcontracting is permitted. However, the awarded contractor will remain fully responsible and accountable for the successful performance, quality, and completion of all requirements under the contract, including any work performed by subcontractors.
13. QUESTION: Can you please confirm whether the 19,005 FT of crowd-control/event barricades quoted meet this specific temporary fencing panel requirement, or if the government specification would require the 6x12 temporary panel fencing instead?
ANSWER: Confirmed
14. QUESTION: If lodging/hotels are necessary, shall this be included as a separate line item on the estimate?
Does this fall under the Joint Travel Regulations?
ANSWER: If lodging/hotels are necessary, they do not have to be included as a separate line item on the estimate. Travel costs may be included in the total price, provided no fee or profit is earned on those travel expenses.
15. QUESTION: For the allowance of the 6’ fence, does this need to be included in the overall cost or a separate line item? Since this is an allowance, the solicitation reads as if the marathon may not require the 6’ fence.
ANSWER: Yes, this shall be included. It is a requirement, not an option.
16. QUESTION: Can the Government provide any additional pricing evaluation guidance beyond the stated Lowest Price Technically Acceptable criteria?
ANSWER: No additional pricing evaluation guidance beyond what is stated in clause 52.212-2 of the solicitation.
17. QUESTION: Can the Government confirm whether the base year and four option years should assume the same event requirements, quantities, and scope of work identified in the current Performance Work Statement?
ANSWER: The base year and four option years should assume the same work. Since we are an active military base and use public roadways, there is always a chance the requirements may change based on things out of our control and will be addressed accordingly should that occur.
18. QUESTION: Should vendors include all costs for delivery, setup, operation, coordination, teardown, and removal in the firm-fixed-price quotation?
ANSWER: Yes, costs for delivery, setup, operation, coordination, teardown, and removal shall all be included and can be broken out on your quote as you best see fit.
19. QUESTION: Are there any site access, security, background check, badging, or installation requirements vendors should consider when pricing?
ANSWER: A required background check will be run on anyone entering the installation. Anyone entering the installation must be a US Citizen and cannot have any felony charges against them at any time (past or current).
Amanda J. Hoyng
Contracting Officer
AFLCMC/PZIBB
| 2026-07-16T13:01:26-0400 | |
| HOYNG.AMANDA.J.1454180034 |