This is a Questions and Answers document issued by the Department of the Air Force, Headquarters 88th Air Base Wing (AFLCMC) on May 4, 2026, addressing contractor inquiries regarding a PDU (Power Distribution Unit) relocation requirement at Wright-Patterson Air Force Base, Ohio.
The document confirms that a pre-quote site visit is permitted on Wednesday, May 6, 2026, at 11:00 AM, with the meeting location at 2721 Sacramento Street, WPAFB, OH 45433. Contractors without base access must provide attendee names, driver's license numbers, and state information to POC Mike Bates (937-231-0584). Regarding the scope of work, the government will not supply any flooring parts, wiring, terminations, reconnections, materials, or equipment; the contractor must provide all parts and labor for installation. PDU 9 specifications indicate a weight rating of 2,500 pounds as documented in the attached Leibert user guide, page 4. Work is to be performed continuously throughout the period of performance rather than phased. The document is signed by Curtis V. Thomas III, Contracting Officer, AFLCMC/PZIBB.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
HEADQUARTERS 88TH AIR BASE WING (AFLCMC)
WRIGHT-PATTERSON AIR FORCE BASE OHIO
4 May 2026
Strength Through Support
Questions and Answers Document
CONTRACTING ACTIVITY/AGENCY: Operational Contracting Division, Directorate of Contracting, Air
Force Life Cycle Management Center (AFLCMC), Air Force Material Command (AFMC), Department of the
Air Force.
AFLCMC/PZIBB
2275 D Street, Area B, Bldg. 16 Room 150
Wright-Patterson AFB, OH 45433
QUESTIONS
Inquiry One (1): One of our electrical subcontractors has requested the opportunity to visit the site in order to better understand the project details before finalizing pricing. Could you please confirm whether a pre-quote site visit can be scheduled for this requirement? If a site visit is available, please provide the available date/time, meeting location, and any base access requirements. We can provide the attendee names, company information, phone numbers, and email addresses as needed for coordination.
ANSWER:
• A Site Visit will be permitted Wednesday, May 6, 2026, at 11am.
• POC Mike Bates 937-231-0584
• Meet: 2721 Sacramento St, WPAFB, OH, 45433
For contractors without base access, I will need name, driver’s license number and state.
Inquiry Two (2): I am currently preparing a quotation for the PDU relocation requirement at Wright-
Patterson AFB and wanted to clarify a few items to ensure full alignment with the scope of work:
1. Can you confirm whether subfloor modifications (including stands, anchors, and structural adjustments) are fully within the contractor's scope, or if any portion will be government-supported?
ANSWER: Government cannot supply flooring parts. Please provide all parts and the labor to install the parts.
2. Are there confirmed weight and dimensional specifications available for PDU 9 to support rigging and equipment planning? ANSWER: Please see attached user guide from Leibert, page 4. Document states it’s rated at 2500#
3. Is the expectation that the work be performed continuously, or will the project be phased over the period of performance? ANSWER: Yes. Work is to be performed continuously.
4. For the electrical portion, can you confirm whether all wiring, terminations, and reconnections are fully contractor-provided, or if any components/materials are government-furnished? ANSWER: Gov is not providing any additional material or equipment.
Curtis V. Thomas III
Contracting Officer
AFLCMC/PZIBB
| 2026-05-05T08:00:57-0400 | |
| THOMAS.CURTIS.VENSON.III.1613907110 |
File details come from the government source that posted it. Updated .