This is a Questions and Answers document issued by the Air Force Life Cycle Management Center (AFLCMC), Operational Contracting Division, dated 29 April 2026, addressing contractor inquiries regarding Task 4 of an electrical installation project at Wright-Patterson Air Force Base, Ohio.
Question 1 addresses the scope and specifications for reinstallation and power connectivity work involving new wiring installation between Room 128A and Room 134. The answer clarifies that wiring will originate from a junction box in Room 134, be pulled into Room 128A, and terminate at PDU 8 with proper phasing. The required materials include 160 feet of 3/0 THHN copper stranded wire in three colors (brown, orange, and yellow), six BISR-250 250MCM in-line splice burners, and six BIT-250 Burndy uni-tap terminal connectors rated for 10-250MCM with two-entry capability. The document specifies that work on PDU 8 is limited to labeling only, with contractors required to ensure label information is correct and observe labels at both ends in the electrical room. Curtis V. Thomas III, Contracting Officer for AFLCMC/PZIBB, issued this clarification.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
HEADQUARTERS 88TH AIR BASE WING (AFLCMC)
WRIGHT-PATTERSON AIR FORCE BASE OHIO
29 April 2026
Strength Through Support
Questions and Answers Document
CONTRACTING ACTIVITY/AGENCY: Operational Contracting Division, Directorate of
Contracting, Air Force Life Cycle Management Center (AFLCMC), Air Force Material Command
(AFMC), Department of the Air Force.
AFLCMC/PZIBB
2275 D Street, Area B, Bldg. 16 Room 150
Wright-Patterson AFB, OH 45433
QUESTIONS
QUESTION 1: On task 4 you stated: "Task 4: Reinstallation and Power Connectivity: Install new wiring in the existing conduit between Room 128A and Room 134." Q: What will this new set of wires feed?
What is the length of the raceway and the size of the wires we need to source? The only thing we have to do with the PDU 8 is labeling, Right?
ANSWER: What will this new set of wires feed? The wiring will come from the junction box in RM 134, connect there and pull the wire into RM 128A, Terminate wire at PDU 8. Ensure wiring is phased correctly.
What is the length of the raceway and the size of the wires we need to source? 160 ft, 3/0
160ft
2428868 CUT 3/0 THHN CU STRD
BROWN WIRE .. Cuts: 1@ 160 ft
160ft
2428871 CUT 3/0 THHN CU STRD
ORANGE WIRE .. Cuts: 1@ 160 ft
160ft
2428872 CUT 3/0 THHN CU STRD
YELLOW WIRE .. Cuts: 1@ 160 ft
6ea
2023799 BISR-250 250MCM IN-LINE
SPLICE BUR
6ea
2017805 BIT-250 BURNDY UNI-TAP
TERM. CONN.
10-250MCM TWO-
ENTRY
Above is a BOM.
The only thing we have to do with the PDU 8 is labeling, Right? Label only. Ensure label information is correct. Visit electrical room and observe labels at both ends.
Curtis V. Thomas III
Contracting Officer
AFLCMC/PZIBB
| 2026-04-29T16:29:03-0400 | |
| THOMAS.CURTIS.VENSON.III.1613907110 |
File details come from the government source that posted it. Updated .