Response to RFI 8.

Text of this file

OFFERORS’ REQUEST FOR INFORMATION (RFI) contd… Solicitation: FA8601-12-R-0038

Project: 09-0006, Repair Fire Safety Deficiencies, F/30013 8.

Note 8 on drawing F002 indicate that the new underground fire protection loop around the building is a 12” loop. However, note 13 on the same page indicate that the loop is 10”. The cost difference between 10” and 12” is very substantial.

Please clarify if the new underground water line around the building is 10” or 12” diameter.

RESPONSE: As a clarification, the fire loop pipe size in Note #8 on Sheet F002 is in error.

The new water main from outside Pump House 30172 to the new building loop is 12"diameter pipe. Then the new fire loop around the building shall be 10" pipe diameter with risers of that size entering the facility as noted and drawn.

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .