questions and answers.docx
DOCX document 11 KB Posted
- Attached to
- Substation B&D Maintenance
- Solicitation number
- FA8601-09-R-0023
About this file
There were some questions that were asked that we have received answers to. Please see attachment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Question_Maintain Substations B&D.doc | DOC document | |
| SOW-revised-19Mar09.docx | DOCX document | |
| Substation Site Visit Notes-19Mar09.pdf | ||
| Atch_4 Addendum to 52 212-2.doc | DOC document | |
| 52.212-3 Reps & Certs.doc | DOC document | |
| SOW.docx | DOCX document | |
| Atch_3 | — | |
| 5352.215-9001 Pre-bid Conference-19mar09.doc | DOC document | |
| http___www.wdol.gov_wdol_scafiles_std_05-2419.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Can we get copy of one-line for each substation?
--Not available for release.
2. When will the transformer outages be available - any during the week day?
-- Sub D transformers (one at a time) will be available during the week.
-- Sub B transformer B14 will require a power outage.
3. Who will do the transformer cable and/or bus disconnect/reconnect for the power factor tests? What are the transformer connections?
-- Contractor to perform disconnections. They can be made at flex fittings from the bus to the transformer bushings. Sub B transformer B14 has cable connections to the transformer secondary bushing.
4. Is it correct to assume all CB's will require a min of 2 hours after test before the next breaker can be taken out of service?
-- This is generally correct. Upon review, for the Sub D 15kV breakers, it may be assumed that average switching time is 1 hour, due to some efficiencies in switching.
5. Can transformers be taken out of service without a "power outage"?
-- Sub D transformers can be taken out of service without a "power outage." Sub B transformer B14 will require a power outage.
6. Will infrareds be done before or after the maintenance work?
-- Infrared inspections may be done either before or after maintenance work.
7. Assume work will start 90 days after award. Are there any restrictions in the time to complete the work?
-- Performance period is 90 days. Work must be completed within 90 days of award.