questions and answers.docx

DOCX document 11 KB Posted

Attached to
Substation B&D Maintenance
Solicitation number
FA8601-09-R-0023
Issued by

About this file

There were some questions that were asked that we have received answers to. Please see attachment.

View the file

Other files

File Type Posted
Question_Maintain Substations B&D.doc DOC document
SOW-revised-19Mar09.docx DOCX document
Substation Site Visit Notes-19Mar09.pdf PDF
Atch_4 Addendum to 52 212-2.doc DOC document
52.212-3 Reps & Certs.doc DOC document
SOW.docx DOCX document
Atch_3 —
5352.215-9001 Pre-bid Conference-19mar09.doc DOC document
http___www.wdol.gov_wdol_scafiles_std_05-2419.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Can we get copy of one-line for each substation?

--Not available for release.

2. When will the transformer outages be available - any during the week day?

-- Sub D transformers (one at a time) will be available during the week.

-- Sub B transformer B14 will require a power outage.

3. Who will do the transformer cable and/or bus disconnect/reconnect for the power factor tests? What are the transformer connections?

-- Contractor to perform disconnections. They can be made at flex fittings from the bus to the transformer bushings. Sub B transformer B14 has cable connections to the transformer secondary bushing.

4. Is it correct to assume all CB's will require a min of 2 hours after test before the next breaker can be taken out of service?

-- This is generally correct. Upon review, for the Sub D 15kV breakers, it may be assumed that average switching time is 1 hour, due to some efficiencies in switching.

5. Can transformers be taken out of service without a "power outage"?

-- Sub D transformers can be taken out of service without a "power outage." Sub B transformer B14 will require a power outage.

6. Will infrareds be done before or after the maintenance work?

-- Infrared inspections may be done either before or after maintenance work.

7. Assume work will start 90 days after award. Are there any restrictions in the time to complete the work?

-- Performance period is 90 days. Work must be completed within 90 days of award.