7b_IPW_Cleaning_PWS_App_1_Equipment_List_30_Mar_2018_Revised.xlsx
XLSX spreadsheet 53 KB Posted
- Attached to
- Industrial Process Waste (IPW)
- Solicitation number
- FA8571-18-R-0014
About this file
Correct Equipment List Updated Equipment List, only change is rows 56-59 was inadvertently hid.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IPW Equip List as of 28 Nov 17
| Building # | Task ID # | Equipment # | Equipment Name | Category | Group | Shop | Frequency | Work Description | Estimated Dimensions | Known Hazards | Est Time to Complete | Unit | Extended | Equipment and Materials | Standards/References | Remarks | Still Required? | Frequency OK? | Any changes? | |
| 50 | 5001 | East Vent Plenum Drain Screens | Drain Screens | AMXG | Corrosion Control | 180 Days | Remove grates from trench drains, remove filter screens, wash thoroughly, remove all loose debris, paint stripper sludge and residue from floor, reinstall filter screens, and replace over trenches. | 12' x 12' x 16' | Confined Space. Cadmium, chromium, lead and chemical depaint (wet). Slip, trip and fall. | 8 hours | 179.00 | 358.00 | Pressure washer, hoses, nozles, tools and PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.146/29 CFR 1910.1027/ 29 CFR 1910.1026/29 CFR 1910.1025/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560/WR-ALC OI 91-25 | Y | Y | ||||
| 50 | 5002 | West Vent Plenum Drain Screens | Drain Screens | AMXG | Corrosion Control | 180 Days | Remove grates from trench drains, remove filter screens, wash thoroughly, remove all loose debris, and paint stripper sludge and residue from floor, reinstall filter screens, and replace over trenches. | 12' x 12' x 16' | Confined Space. Cadmium, chromium, lead and chemical depaint (wet). Slip, trip and fall. | 8 hours | 179.00 | 358.00 | Pressure washer, hoses, nozles, tools and PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.146/29 CFR 1910.1027/ 29 CFR 1910.1026/29 CFR 1910.1025/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560/WR-ALC OI 91-25 | Y | Y | ||||
| 50 | 5003 | Air Flow Tunnels (Long tunnel under hangar estimated 175 ft long x 6 ft wide x 8 ft tall) | Air Flow Tunnel | AMXG | Corrosion Control | 360 Days | Remove all loose debris, paint stripper sludge and residue from floor of tunnels, remove residue from walls, ceiling, and floor of tunnels down to bare concrete, clean overhead pipe drain and clean drain sump rooms, clean crossover duct(s) between both tunnels, remove all debris and residue in filter rooms including cleaning of reusable filters, clean each exhaust fan and discharge ducts, remove grates from trench drains, remove filter screens from trench, wash thoroughly, and reinstall grates over trenches. | 6 ft W x 8 ft H Approx 600 linear ft | Confined Space. Cadmium, chromium, lead and chemical depaint (wet). Slip, trip and fall. | 32 hours - Four (4) 8-hour days with 6 workers | 790.00 | 790.00 | Pressure washer, hoses, nozles, ladders, manlift, hepa vac, tools and PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.146/29 CFR 1910.1027/ 29 CFR 1910.1026/29 CFR 1910.1025/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560/WR-ALC OI 91-25 | Y | Y | ||||
| 54 | 5401 | Paint Chip Trench Drain | Trench Drain | AMXG | Corrosion Control | 360 Days | Remove grates from trench drains, remove paint stripper sludge, blast media, and all other residue, remove filter screens and/or drain baskets from trench, wash thoroughly, reinstall and replace grates over trenches. | 162 ft L x 2 ft W 130 ft L x 2 ft W 186 ft L x 2 ft W | Cadmium, chromium, lead and chemical depaint (wet). Slip, trip and fall. | 4 hours | 79.00 | 79.00 | Fork lift, pressure washer, tools and PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.1027/29 CFR 1910.1026/29 CFR 1910.1025/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||
| 54 | 5402 | Lift Station | Lift Station | AMXG | Corrosion Control | 90 Days | Remove debris from the water return area and place in appropriate containers. Remove debris and paint stripper sludge from main containment area so that it is not allowed to enter industrial waste drain. Replace and clean all pit covers. | 16 ft x 20 ft x 20 ft | Confined Space. Cadmium, chromium, lead and chemical depaint (wet). Slip, trip and fall. | 16 hours | 300.00 | 1,200.00 | Pressure washer, Vacuum, rakes, tools and PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.146/29 CFR 1910.1027/29 CFR 1910.1026/29 CFR 1910.1025/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560/WR-ALC OI 91-25 | Y | Y | ||||
| 59 Paint | 5901 | Floor Trenches and Drain Baskets | Trench Drain | AMXG | Corrosion Control | 360 Days | Remove grates from trench drains, remove screens, remove paint stripper sludge, and all other debris from trenches accumulated during paint/de-paint processes, remove drain baskets from trench, wash drain baskets and screens thoroughly, reinstal and replace grates over trenches. | 200 ft x 2 ft (2 each) | Cadmium, chromium, lead and chemical depaint. Slip, trip and fall. | 4 hours | 79.00 | 79.00 | Pressure washer, tools, PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.1027/29 CFR 1910.1026/29 CFR 1910.1025/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||
| 59P (Paint) | 5904 | Chem Strip Process in a facility designed for paint only | Paint Facility | AMXG | Corrosion Control | On Request | Remove paint stripper sludge, debris, sediment and residue from hangar floor so that it is not allowed to enter the industrial waste drains. | Cadmium, chromium, lead and chemical depaint (wet). Slip, trip, and fall | 5 days (crew of 5) | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.1027/ 29 CFR 1910.1026/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Changed 10/6/16 - Freq Increase | Y | Y | |||||||
| 59D (dry -depaint facility) | 5905 | Filter Walls | Plastic media facility not designed for sanding process. We have to clean sanding media once a year to prevent potential exposure to known hazards. | AMXG | Corrosion Control | Annually On Request | Remove covers, vacuum out the bottom of all the filter banks, and replace covers. Prevent purging of dust that risks employee exposure to hazardous waste. | Cadmium, chromium, lead and chemical depaint (dry). | 5 days (crew of 5) | 42 USC 6901/42 USC 7401/40 CFR 260/40 CFR 263/29 CFR 1910.1027/ 29 CFR 1910.1026/29 CFR 1910.1025/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | New 3/23/16 | Y | Y | |||||||
| 59D (dry -depaint facility) | 5906 | Sanding Hangar | Plastic media depaint facility not designed for sanding process. We have to clean once a year to prevent potential exposure to known hazards. | AMXG | Corrosion Control | Annually On Request | Remove dust and debris from all the hangar walls and any attachments (wipe down walls up to 8 feet above the floor). Remove all dust and debris from reachable surfaces of 2 metal staircases, filter access platform, and floor. | 265'W x 181"L=47,965 sq. ft + 112' x 104'=11,648 sq. ft. = 59,613 sq. ft. total | Cadmium, chromium, lead and chemical depaint (dry). | 6 days (crew of 7) | 42 USC 6901/42 USC 7401/40 CFR 260/40 CFR 263/29 CFR 1910.1027/ 29 CFR 1910.1026/29 CFR 1910.1025/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | New 10/6/16 | Y | Y | ||||||
| 89 | 08902 | Chemical Strip Process | Paint Facility | AMXG | Corrosion Control | On Request | Remove paint stripper sludge, debris, sediment and residue from hangar floor so that it is not allowed to enter the industrial waste drains. Clean drain baskets and sump to prevent flooding of hangar during chemical depaint process. | Cadmium, chromium, lead and chemical depaint (wet). Slip. Trip and fall. | 5 days (crew of 5) | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.1027/ 29 CFR 1910.1026/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | New 3/30/17 | |||||||||
| 125 | 12502-A | Hydrotron Sanding Booth | Sanding Booth | AMXG | C-5 Sheet Metal | 7 Days | Remove all dust, particles, and residue from walls, and floor of booth. | 12 ft x 12 ft x 10 ft | Dust with cadmium, chromium and lead above OSHA limits. | 2 hours | 450.00 | 900.00 | Hepa vac, ladders, tools and PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.1027/ 29 CFR 1910.1026/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||
| 125 | 12502-B | Hydrotron Sanding Booth | Sanding Booth | AMXG | C-5 Sheet Metal | 60 Days | Inspect the mist eliminators for buildup of solids. Remove solid buildup by soaking in soapy solution power wash to remove all traces of soap. Clean fitting where the tube from the differential switch connects to the body of the dust collector. Clean float switch. Drain water from tank. Use supplied rake to pull sludge to the front of the unit and remove using wet-dry vacuum. Dispose of sludge properly (consult NFPA code). Check seals on acrylic door/panel. | 16 ft x 16 ft x 8 ft | Dust with cadmium, chromium and lead above OSHA limits. | 1 hour | 825.00 | 4,950.00 | Wet-dry vac, soapy solution, brushes, tools, PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.1027/ 29 CFR 1910.1026/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||
| 137 | 13701 | Trench Drain - Bay 2 | Trench Drain | AMXG | Corrosion Control | 30 Days | Remove grates from trench drains, remove paint stripper sludge, blast media, and all other residue, remove filter screens and/or drain baskets from trench, wash thoroughly, and reinstall, wash grates and replace over trenches | 52 ft x 2 ft 16 ft x 2 ft | Paint waste and debris. Chromated primer overspray. | 5 hours | 700.00 | 8,400.00 | Pressure washer and accessories, tools, PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.124/ 29 CFR 1910.1027/ 29 CFR 1910.1026/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||
| 137 | 13702 | Trench Drain - Bay 1 | Trench Drain | AMXG | Corrosion Control | 30 Days | Remove grates from trench drains, remove paint stripper sludge, blast media, and all other residue, remove filter screens and/or drain baskets from trench, wash thoroughly, and reinstall, wash grates and replace over trenches | 52 ft x 2 ft 16 ft x 2 ft | Paint waste and debris. Chromated primer overspray. | 4 hours | 600.00 | 7,200.00 | Pressure washer and accessories, tools, PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.124/ 29 CFR 1910.1027/ 29 CFR 1910.1026/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||
| 137 | 13703 | Light Panels - Bay 2 | Paint Booth | AMXG | Corrosion Control | 180 Days | Remove all paint and residue from panels in booth through which light must pass, replace all covering over from panels in booth through which light must pass. | 18 sidelights 2' x 4' 20 toplights 2' x 2' | Paint waste and debris. Chromated primer overspray. | 4 hours | 699.00 | 1,398.00 | Scraper, ladder, light cover, PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.124/ 29 CFR 1910.1027/ 29 CFR 1910.1026/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||
| 137 | 13704 | Light Panels - Bay 3 | Paint Booth | AMXG | Corrosion Control | 180 Days | Remove all paint and residue from panels in booth through which light must pass, replace all covering over from panels in booth through which light must pass. | 16 sidelights globe 12 toplights 2' x 2' | Dust with cadmium, chromium and lead above OSHA limits. | 4 hours | 699.00 | 1,398.00 | Scraper, ladder, light cover, PPE | 42 USC 6901/42 USC 7401/40 CFR 260/40 CFR 263/29 CFR 1910.124/ 29 CFR 1910.1027/ 29 CFR 1910.1026/29 CFR 1910.1025/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||
| 137 | 13705 | Light Panels - Bay 4 | Paint Booth | AMXG | Corrosion Control | 180 Days | Remove all paint and residue from panels in booth through which light must pass, replace all covering over from panels in booth through which light must pass. | 20 sidelights globe 16 toplights 2' x 2' | Paint waste and debris. Chromated primer overspray. | 4 hours | 699.00 | 1,398.00 | Scraper, ladder, light cover, PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.124/ 29 CFR 1910.1027/ 29 CFR 1910.1026/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||
| 137 | 13706 | Light Panels - Bay 5 | Paint Booth | AMXG | Corrosion Control | 180 Days | Remove all paint and residue from panels in booth through which light must pass, replace all covering over from panels in booth through which light must pass. | 10 sidelights 2' x 4' 42 toplights 2' x 2' | Paint waste and debris. Chromated primer overspray. | 4 hours | 699.00 | 1,398.00 | Scraper, ladder, light cover, PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.124/ 29 CFR 1910.1027/ 29 CFR 1910.1026/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||
| 137 | 13707 | Media Recovery - Bay 4 | Recovery Trench | AMXG | Corrosion Control | 360 Days | Remove grates and filter screens from floor recovery system, remove blast media and all other residue from floor recovery system, replace grating | 32 ft L x 60 ft W | Dust with cadmium, chromium and lead above OSHA limits. | 8 hours | 699.00 | 699.00 | Pressure washer, tools, PPE | 42 USC 6901/42 USC 7401/40 CFR 260/40 CFR 263/29 CFR 1910.124/ 29 CFR 1910.1027/ 29 CFR 1910.1026/29 CFR 1910.1025/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||
| 137 | 13708 | Trench Drain - Bay 5 | Trench Drain | AMXG | Corrosion Control | 180 Days | Remove grates from trench drains, remove paint stripper sludge, blast media, and all other residue, remove filter screens and/or drain baskets from trench, wash thoroughly, and reinstall, wash grates and replace over trenches | 104 ft L x 2 ft W (2 each) | Paint waste and debris. Chromated primer overspray. | 3 hours | 699.00 | 1,398.00 | Pressure washer, tools, PPE | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.124/ 29 CFR 1910.1027/ 29 CFR 1910.1026/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||
| 364 | 36401-A | Hydrotron Sanding Booth | Sanding Booth | AMXG | Consolidated Support Flight | 7 Days | Remove all dust, particles, and residue from walls, and floor of booth. | 10 ft Wide x 8 ft Tall x 10 ft Deep | Dust with cadmium, chromium and lead above OSHA limits. | 2 hours | 42 USC 6901/42 USC 7401/40 CFR 260/40 CFR 263/29 CFR 1910.1027/ 29 CFR 1910.1026/29 CFR 1910.1025/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | |||||||
| 364 | 36401-B | Hydrotron Sanding Booth | Sanding Booth | AMXG | Consolidated Support Flight | 60 Days | Inspect the mist eliminators for buildup of solids. Remove solid buildup by soaking in soapy solution power wash to remove all traces of soap. Clean fitting where the tube from the differential switch connects to the body of the dust collector. Clean float switch. Drain water from tank. Use supplied rake to pull sludge to the front of the unit and remove using wet-dry vacuum. Dispose of sludge properly (consult NFPA code). Check seals on acrylic door/panel. | 16 ft L x 16 ft W x | ||||||||||||
| 8 ft H | Dust with cadmium, chromium and lead above OSHA limits. | 1 hour | $ 825.00 | $ 4,950.00 | Hepa vacuum, amended water, pressure washer, Wet-dry vac, tools, supplies, PPE | 42 USC 6901/42 USC 7401/40 CFR 260/40 CFR 263/29 CFR 1910.1027/ 29 CFR 1910.1026/29 CFR 1910.1025/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | Y | Y | ||||||||||||
| 2036 | 203601 | Hangar Floor | Paint Facility | AMXG | Corrosion Control | On Request | Remove paint stripper sludge, debris, sediment and residue from hangar floor so that it is not allowed to enter the industrial waste drains. | Cadmium, chromium, lead and chemical depaint (wet). Slip, trip and fall. | 5 days (crew of 5) | 42 USC 6901/40 CFR 260/40 CFR 263/29 CFR 1910.1027/ 29 CFR 1910.1026/NFPA 30/AFI 32-7042/RAFB ISWMP/RAFB HWMP/RAFB 01560 | ||||||||||
| 140 | 14001 | RP8721 | Oil Tank | Tank | CMXG | Prop Shop | On Request | Remove liquids from tank into appropriate receptacle. Remove all residue from walls and bottom of tank. Remove residue from parts table assembly including table frame, grates, and rails. | Rectangular tank holds 110 gallons of light weight oil & lift table | 1.5 hours | 42 USC 6901 (solid waste disposal), 40 CFR 260 (hazardous waste mgmt), 40 CFR 263 (hazardous waste transport), 29 CFR 1910.124, (OSHA/beryllium), 29 CFR 1910.1027 (OSHA/cadmium), 29 CFR 1910.1026 (OSHA/chromium), NFPA 30 (flammable/combustible liquids), AFI 32-7042 (AF waste mgmt), RAFB ISWMP (local solid waste mgmt), RAFB HWMP (local hazardous waste mgmt), RAFB 01560 (environmental) | |||||||||
| 140 | 14002 | RP8723 | Finger Print Remover Tank | Tank | CMXG | Prop Shop | On Request | Remove liquids from tank into appropriate receptacle. Remove all residue from walls and bottom of tank. Remove residue from parts table assembly including table frame, grates, and rails. | Rectangular tank holds 110 gallons of MIL-C-15074C corrosion preventive liquid & lift table | 1.5 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.124, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||||||
| 140 | 14003 | WR000253 | Water Wash Grinding Booth # 1 | Dust Collector | CMXG | Prop Shop | 7 Days | Clean mist eliminators. Remove all dust, residue, and debris from unit. Drain tank. | 20 Ft Wide x 6 ft Tall | Aluminum dust | 0.50 hour (30 minutes) | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||||||
| 140 | 14004 | WR000254 | Water Wash Grinding Booth # 2 | Dust Collector | CMXG | Prop Shop | 7 Days | Clean mist eliminators. Remove all dust, residue, and debris from unit. Drain tank. | 20 Ft Wide x 6 ft Tall | Aluminum dust | 0.50 hour (30 minutes) | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||||||
| 140 | 14005-A | WR003106 | Three Stage Paint Booth | Paint Booth | CMXG | Prop Shop | 7 Days | Clean all lights and replace light diffuser covers. Remove all dust, residue, and debris from ceiling, walls, personnel doors, roll-up doors, and floor (including door thresholds). Inspect and re-cover fire sprinklers with new paper bags as required. Remove all floor covering and tape from floor except under workbench and cabinet area. Replace floor covering and tape to cover all accessible floor space. Workbench and cabinets may remain in place during this cleaning. | 20 ft Wide x 19 ft Tall | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium. | ||||||||||
| 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.124, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||||||||||||||||
| 140 | 14005-B | WR003106 | Three Stage Paint Booth | Paint Booth | CMXG | Prop Shop | 90 Days | Clean all lights and replace light diffuser covers. Remove all peel-coat from walls, ceiling and floor inside paint booth. Apply white water-based polymer emulsion peel-coat on walls and ceiling. Replace all floor covering and tape. Re-cover all fire sprinklers with new paper bags. Remove and limit build-up of paint to ensure visibility for reading gauges. Replace stage-1, stage-2, and stage-3 filters. | 20 ft Wide x 19 ft Tall | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium. | ||||||||||
| 7 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.124, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||||||||||||||||
| 140 | 14005-C | WR003106 | Three Stage Paint Booth | Paint Booth | CMXG | Prop Shop | On Request | Replace stage-1 filters. If requested while cleaning of that booth is underway, filters will be replaced at that time. If no cleaning is underway, filters will be replaced at the next cleaning time. | ||||||||||||
| 20 ft Wide x 19 ft Tall | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium. | |||||||||||||||||||
| 1 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.124, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||||||||||||||||
| 140 | 14005-D | WR003106 | Three Stage Paint Booth | Paint Booth | CMXG | Prop Shop | On Request | Replace stage-1 and stage-2 filters. If requested while cleaning of that booth is underway, filters will be replaced at that time. If no cleaning is underway, filters will be replaced at the next cleaning time. | 20 ft Wide x 19 ft Tall | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium. | ||||||||||
| 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.124, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||||||||||||||||
| 140 | 14005-E | WR003106 | Three Stage Paint Booth | Paint Booth | CMXG | Prop Shop | On Request | Replace stage-1, stage-2, and stage-3 filters. Replace ceiling filters. If requested while cleaning of that booth is underway, filters will be replaced at that time. If no cleaning is underway, filters will be replaced at the next cleaning time. | 20 ft Wide x 19 ft Tall | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium. | ||||||||||
| 4 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.124, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||||||||||||||||
| 140 | 14006-A | WR003566 | Robotic Blade Grinder Dust Collector | Dust Collector | CMXG | Prop Shop | 2 Times Weekly | Drain the system and clean water level control box and tank section in accordance with ProVent's Operation and Maintenance Manual. Wipe down exterior. | 4'W x 5' Tall | Aluminum dust | 1 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||||||
| 140 | 14006-B | WR003566 | Robotic Blade Grinder Dust Collector | Dust Collector | CMXG | Prop Shop | 30 Days | Remove and clean target plate, clean scrub cone, clean mist eliminator, and clean exhaust fan blades in accordance with ProVent's Operation and Maintenance Manual. | 4'W x 5' Tall | Aluminum dust | 3 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||||||
| 140 | 14007-A | RP10105 | Manual Blade Edge Grinding Booth | Grinding Booth | CMXG | Prop Shop | 2 Times weekly | Drain the system and clean water level control box and tank section in accordance with ProVent's Operation and Maintenance Manual. Wipe down exterior. | 7 ft wide Face | Aluminum dust | 1 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||||||
| 140 | 14007-B | RP10105 | Manual Blade Edge Grinding Booth | Grinding Booth | CMXG | Prop Shop | 90 Days | Clean target plates, clean scrub cones, clean mist eliminators, and clean exhaust fan blades in accordance with ProVent's Operation and Maintenance Manual. | 14'L x 10'W x 8' H | Aluminum dust | 4 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||||||
| 140 | 14008 | Penetrant Tank | Tank | CMXG | NDI Shop | 180 Days | Remove all liquids into appropriate receptacle and remove all residue from interior of tank including all installed features. | 75 gallons | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.124, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | New 2/25/16 | |||||||||
| 140 | 14009 | Emulsifier Tank | Tank | CMXG | NDI Shop | 180 Days | Remove all liquids into appropriate receptacle and remove all residue from interior of tank including all installed features. | 75 gallons | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.124, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | added back to requirement - bjb 11/9/2017 | |||||||||
| 140 | 14019 | WR003566 | Robotic Grinding Room and Equipment | Grinding Booth | CMXG | Prop Shop | 60 Days | Remove all metal dust, particles, and debris from all surfaces (equipment, cage, ceiling, walls, windows, floor, etc) within the room. | 114" L x 30" W x 82" D | Aluminum dust | 4 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Changed 3/31/16 | |||||||
| 140 | 14020-A | WR002937 | Sanding Booth | Sanding Booth | CMXG | CNC Machine Shop | 2 Times Weekly | Remove all dust, particles, and residue from walls, and floor of booth. Empty and clean all trays. | 1556" L x 55"W x 165"H | Dust with cadmium, chromium and lead above OSHA limits. | 1 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.124, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | When will all the these be needed? | |||||||
| 140 | 14020-B | WR002937 | Sanding Booth | Sanding Booth | CMXG | CNC Machine Shop | 30 Days | Remove all dust, particles, and residue from ceiling (including all flat surface, conduit and light fixtures), and booth entrance facing. | 30"L x 3"W x 43"H | Dust with cadmium, chromium and lead above OSHA limits. | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.124, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | "" | |||||||
| 140 | 14020-C | WR002937 | Sanding Booth | Sanding Booth | CMXG | CNC Machine Shop | 180 Days | Remove all dust, particles, and residue from ceiling (including all flat surface, conduit and light fixtures), walls, and floor of booth. Empty and clean all trays. Remove all dust, particles, and residue from all exterior surfaces of the booth including walls, roof, filter housings, conduit, piping, catwalk, etc. | 96"L x 30"W x 66"H | Dust with cadmium, chromium and lead above OSHA limits. | 4 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.124, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | "" | |||||||
| 142 | 14201-A | Sealant Spray Booth | Paint Booth | CMXG | Plating Shop | On Request | Remove floor covering and tape. Replace all paper and tape to cover all floor space. Remove and replace door filters. | 101"L X 30"W x 48"H | Paint waste and debris. Chromated primer overspray. | 5 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | "" | ||||||||
| 142 | 14243 | Alkaline Tank # 601 | Tank | CMXG | Plating Shop | On request | Remove all liquids from tank into appropriate receptacle. Clean interior of tank including all installed or removed features. | 36"L x 30"W x 108"H | Contains 1840 L (490 gallons) of Sodium Hydroxide | 3 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Y | Y | |||||||
| 142 | 14244 | Rinse Tank # 602 | Tank | CMXG | Plating Shop | On Request | Remove all liquids from tank into appropriate receptacle. Clean interior of tank including all installed or removed features. | 40"L x 30"W x 108"H | 3 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Not on current contract | Y | N | Per Shane Groves, 10/28/16 - Not expected to be needed beyond the first couple of months on new contract. | ||||||
| 142 | 14245 | HN03 Tank # 603 | Tank | CMXG | Plating Shop | On Request | Remove all liquids from tank into appropriate receptacle. Clean interior of tank including all installed or removed features. | 40"L x 30"W x 108"H | Contains 1840 L (490 gallons) of Desmut (HNO3) | 3 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Y | N | Per Shane Groves, 10/28/16 - Not expected to be needed beyond the first couple of months on new contract. | ||||||
| 142 | 14246 | Rinse Tank # 604 | Tank | CMXG | Plating Shop | On Request | Remove all liquids from tank into appropriate receptacle. Clean interior of tank including all installed or removed features. | 40"L x 30"W x 108"H | 3 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Not on current contract | Y | N | Per Shane Groves, 10/28/16 - Not expected to be needed beyond the first couple of months on new contract. | ||||||
| 142 | 14247 | Chromate Acid Anodize Tank # 605 | Tank | CMXG | Plating Shop | On Request | Remove all liquids from tank into appropriate receptacle. Clean interior of tank including all installed or removed features. | 96"L x 30"W x 108"H | Contains 4920 L (1300 gallons) of Chromic Acid Anodize | 3 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Y | N | Per Shane Groves, 10/28/16 - Not expected to be needed beyond the first couple of months on new contract. | ||||||
| 142 | 14248 | Chromate Acid Anodize Tank # 606 | Tank | CMXG | Plating Shop | Every 3 yrs On Request | Remove all liquids from tank into appropriate receptacle. Clean interior of tank including all installed or removed features. | 96"L x 30"W x 108"H | Contains 4920 L (1300 gallons) of Chromic Acid Anodize | 3 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Y | N | Per Shane Groves, 10/28/16 - Not expected to be needed beyond the first couple of months on new contract. Cleaned recently @ 10/16. | ||||||
| 142 | 14249 | Rinse Tank # 607 | Tank | CMXG | Plating Shop | On Request | Remove all liquids from tank into appropriate receptacle. Clean interior of tank including all installed or removed features. | 40"L x 30"W x 108"H | 3 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Not on current contract | Y | N | Per Shane Groves, 10/28/16 - Not expected to be needed beyond the first couple of months on new contract. | ||||||
| 142 | 14250 | Rinse Tank # 608 | Tank | CMXG | Plating Shop | On Request | Remove all liquids from tank into appropriate receptacle. Clean interior of tank including all installed or removed features. | 36"L x 30"W x 108"H | 3 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Not on current contract | Y | N | Per Shane Groves, 10/28/16 - Not expected to be needed beyond the first couple of months on new contract. | ||||||
| 142 | 14295 | WR000464 |
RP8979
RP8981
| RP101099 | Hand Blast Systems (4 each) | Blast Equipment | CMXG | Plating Shop | 90 Days | Remove dust, particles, and residue from all exterior surfaces of the main unit of all four systems. | various sizes of small equipment | Dust with cadmium, chromium and lead above OSHA limits. | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 |
| 142 | 14296 | WR000464 |
RP8979
RP8981
| RP101099 | Hand Blast Systems (4 each) | Blast Equipment | CMXG | Plating Shop | 90 Days | Remove dust, particles, and residue from all exterior surfaces of all components of all four systems. | various sizes of small equipment | Dust with cadmium, chromium and lead above OSHA limits. | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||||
| 146 | 14601 | Trench Drain | Trench Drain | CMXG | F-15 Water Pick | 7 Days | Remove trench grates. Remove all sludge and debris from trench into proper container. Remove and clean all filter screens and baskets and reinstall. Rinse trench clean. Wash and reinstall grates. | 2 Trenches - Each is XX Ft L x 12 In W x 18 In D | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Confirm Frequency for bridge contract | |||||
| 169 | 16901-B | Airless Degreaser (tank 2) | Vapor Degreaser | CMXG | Composite Repair | Annually On Request | Remove all liquids from main tank, two water separators, and associated plumbing into appropriate receptacle for turn-in. Remove safety screens for access. Clean and passivate all interior features with Soda Ash alkali solution including cooling coils, all plumbing lines, brackets, safety screens, drain troughs, water separator interiors and lids, tank lid, walls, bottom, heating elements and manual parts sprayer. Assure alkali solution reaches all crevices and underside surfaces and plumbing lines. Lightly abrade all tank walls, drain troughs and flat surfaces using steel brush or abrasive Scotch-Brite or equivalent pads and alkali solution IAW tank manufacturer’s procedures. Once more, remove all liquids from main tank, two water separators, and associated plumbing into appropriate receptacle for turn-in. Thoroughly rinse with water to remove alkali solution from all interior features. Dispose of water in industrial waste system. | 3 Ft W x 12 Ft L x 11 Ft D | Contains 220 gallons of 3M HFE7100 Vapor Degreaser | 16 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Bridge Contract? | ||||
| 169 | 16902 | Alkaline Tank (tank 3) | Tank | CMXG | Composite Repair | On Request | Remove all liquids into appropriate receptacle and clean interior of tank including all installed features. | 16'L x 3'W x 7'H | Contains 1850 gallons of Alkaline Cleaner | 4 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||
| 169 | 16905 | LNC Tank (tank 5) | Tank | CMXG | Composite Repair | On Request | Remove all liquids into appropriate receptacle and clean interior of tank including all installed features. | 16'L x 3'W x 7'H | 1850 gallons tank with heating elements & cooling coils contains Oakie Deoxidizer | 4 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||
| 169 | 16906 | Phosphoric Tank (tank 8) | Tank | CMXG | Composite Repair | On Request | Remove all liquids into appropriate receptacle and clean interior of tank including all installed features. | 16'L x 3'W x 7'H | 1850 gallons tan+J59+K59+K59:L59 | 4 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||
| 169 | 16907 | Spray Rinse Tank (tank 9) | Tank | CMXG | Composite Repair | Annually On Request | Remove all liquids into appropriate receptacle and clean interior of tank including all installed features. | 16'L x 3'W x 7'H | 4 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Not on current contract | |||||
| 169 | 16909-A | WR003749 | Dry Filter Paint Booth and Room | Paint Booth | CMXG | Composite Repair | 7 Days | Clean all paint from light diffusers. Replace light diffuser covers. Remove all dust, residue, and debris from ceiling, walls, doors, and floor (including door thresholds). Inspect and re-cover fire sprinklers with new paper bags as required. Remove all floor covering and tape from floor. Replace floor covering and tape to cover all floor space. | 20'L x 15'W x 8'H | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium. | ||||||
| 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||||||||||||
| 169 | 16909-B | WR003749 | Dry Filter Paint Booth and Room | Paint Booth | CMXG | Composite Repair | 90 Days | Remove all peel-coat from walls, ceiling and floor inside paint booth. Apply white water-based polymer emulsion peel-coat on walls and ceiling. Replace all floor covering and tape. Re-cover all fire sprinklers with new paper bags. Clean all lights and replace light diffuser covers. Remove and limit build-up of paint to ensure visibility for reading gauges. Replace filter stages 1, 2, and 3. | 20'L x 15'W x 8'H | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium. | ||||||
| 12 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||||||||||||
| 169 | 16909-C | WR003749 | Dry Filter Paint Booth and Room | Paint Booth | CMXG | Composite Repair | On Request | Replace Stage 1 filters. If requested while cleaning of that booth is underway, filters will be replaced at that time. If no cleaning is underway, filters will be replaced at the next cleaning time. | 20'L x 15'W x 8'H | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium. | 1 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16909-D | WR003749 | Dry Filter Paint Booth and Room | Paint Booth | CMXG | Composite Repair | On Request | Replace Stages 1 and 2 filters. If requested while cleaning of that booth is underway, filters will be replaced at that time. If no cleaning is underway, filters will be replaced at the next cleaning time. | 20'L x 15'W x 8'H | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium. | ||||||
| 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||||||||||||
| 169 | 16909-E | WR003749 | Dry Filter Paint Booth and Room | Paint Booth | CMXG | Composite Repair | On Request | Replace Stages 1, 2, and 3 filters. Replace intake filters. If requested while cleaning of that booth is underway, filters will be replaced at that time. If no cleaning is underway, filters will be replaced at the next cleaning time. | 20'L x 15'W x 8'H | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium | 3 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16910-A | WR002635 | Grit Blast Booth Doors | Grit Blast Booth | CMXG | Composite Repair | 2 Times Weekly | Clean all dust, particles, and residue from outside and edges of all doors. | 4'W x 8'H | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium. | ||||||
| 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||||||||||||
| 169 | 16910-B | WR002635 | Grit Blast Booth | Grit Blast Booth | CMXG | Composite Repair | 90 Days | Remove all removable grates and screens from floor recovery system inside booth and behind booth. Remove all visible blast media and residue from floor recovery system. Replace grates. Clean all dust, particles, debris, and residue from the entire floor behind booth, especially around the hopper. | 34'L x 15'W x 12'H | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium. | ||||||
| 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | Changed 3/31/16 | |||||||||||||||
| 169 | 16912-A | WR003743 | Sanding Booth East | Sanding Booth | CMXG | Composite Repair | Daily | Remove all dust, particles, and residue from walls, and floor of booth. Empty and clean all trays. | 33'L x 15'W x 11'H | Dust with cadmium, chromium and lead above OSHA limits. | 1 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16912-B | WR003743 | Sanding Booth East | Sanding Booth | CMXG | Composite Repair | 7 Days | Remove all dust, particles, and residue from ceiling (including all flat surface, conduit and light fixtures), and booth entrance facing. | 33'L x 15'W x 11'H | Dust with cadmium, chromium and lead above OSHA limits. | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16912-C | WR003743 | Sanding Booth East | Sanding Booth | CMXG | Composite Repair | 90 Days | Remove all dust, particles, and residue from ceiling (including all flat surface, conduit and light fixtures), walls, and floor of booth. Empty and clean all trays. Remove all dust, particles, and residue from all exterior surfaces of the booth including walls, roof, filter housings, conduit, piping, catwalk, etc. | 33'L x 15'W x 11'H | Dust with cadmium, chromium and lead above OSHA limits. | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||
| 169 | 16912-D | WR | Central Vacuum System | Vacuum Cleaner | CMXG | Composite Repair | 7 Days | Remove, empty, and reinstall canisters. Clean all dust, particles and residue from vacuum systems' areas. | 4'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | .25 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16913-A | WR002935 | Sanding Booth South #1 | Sanding Booth | CMXG | Composite Repair | Daily | Remove all dust, particles, and residue from walls, and floor of booth. Empty and clean all trays. | 34'L x 19'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | 1 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16913-B | WR002935 | Sanding Booth South #1 | Sanding Booth | CMXG | Composite Repair | 7 Days | Remove all dust, particles, and residue from ceiling (including all flat surface, conduit and light fixtures), and booth entrance facing. | 34'L x 19'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16913-C | WR002935 | Sanding Booth South #1 | Sanding Booth | CMXG | Composite Repair | 90 days | Remove all dust, particles, and residue from ceiling (including all flat surface, conduit and light fixtures), walls, and floor of booth. Empty and clean all trays. Remove all dust, particles, and residue from all exterior surfaces of the booth including walls, roof, filter housings, conduit, piping, catwalk, etc. | 34'L x 19'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | 1.75 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16913-D | WR00369 | Central Vacuum System | Vacuum Cleaner | CMXG | Composite Repair | 7 Days | Remove, empty, and reinstall canisters. Clean all dust, particles and residue from vacuum systems' areas. | 4'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | .25 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16914-A | WR002936 | Sanding Booth South #2 | Sanding Booth | CMXG | Composite Repair | Daily | Remove all dust, particles, and residue from walls, and floor of booth. Empty and clean all trays. | 34'L x 19'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | 1 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16914-B | WR002936 | Sanding Booth South #2 | Sanding Booth | CMXG | Composite Repair | 7 Days | Remove all dust, particles, and residue from ceiling (including all flat surface, conduit and light fixtures), and booth entrance facing. | 34'L x 19'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16914-C | WR002936 | Sanding Booth South #2 | Sanding Booth | CMXG | Composite Repair | 90 Days | Remove all dust, particles, and residue from ceiling (including all flat surface, conduit and light fixtures), walls, and floor of booth. Empty and clean all trays. Remove all dust, particles, and residue from all exterior surfaces of the booth including walls, roof, filter housings, conduit, piping, catwalk, etc. | 34'L x 19'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | 1.75 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16914-D | WR003670 | Central Vacuum System | Vacuum Cleaner | CMXG | Composite Repair | 7 Days | Remove, empty, and reinstall canisters. Clean all dust, particles and residue from vacuum systems' areas. | 4'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | .25 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16915-A | WR003026 | Sanding Booth West | Sanding Booth | CMXG | Composite Repair | Daily | Remove all dust, particles, and residue from walls, and floor of booth. Empty and clean all trays. | 34'L x 19'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | 1 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16915-B | WR003026 | Sanding Booth West | Sanding Booth | CMXG | Composite Repair | 7 Days | Remove all dust, particles, and residue from ceiling (including all flat surface, conduit and light fixtures), and booth entrance facing. | 34'L x 19'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16915-C | WR003026 | Sanding Booth West | Sanding Booth | CMXG | Composite Repair | 90 Days | Remove all dust, particles, and residue from ceiling (including all flat surface, conduit and light fixtures), walls, and floor of booth. Empty and clean all trays. Remove all dust, particles, and residue from all exterior surfaces of the booth including walls, roof, filter housings, conduit, piping, catwalk, etc. | 34'L x 19'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | 1.75 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 169 | 16915-D | WR003668 | Central Vacuum System | Vacuum System | CMXG | Composite Repair | 7 Days | Remove, empty, and reinstall canisters. Clean all dust, particles and residue from vacuum systems' areas. | 4'W x 8'H | Dust with cadmium, chromium and lead above OSHA limits. | .25 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||
| 180 | 18005 | Trench Drain | Trench Drain | CMXG | Paint Shop | 2 Times Weekly | Remove grates,remove all paint stripper sludge and blast media into proper container, remove and clean filter screen or trench basket and reinstall,rinse trench clean,wash and reinstall grates. | 2 each trenches approx 60 ft long | Paint sludge from chemical depainting process | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||
| 180 | 18006 | Trench Drain | Trench Drain | CMXG | Paint Shop | 2 Times Weekly | Remove grates,remove all paint stripper sludge and blast media into proper container, remove and clean filter screen or trench basket and reinstall,rinse trench clean,wash and reinstall grates. | 2 each trenches approx 60 ft long | Paint sludge from chemical depainting process | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||
| 180 | 18007 | Trench Drain | Trench Drain | CMXG | Paint Shop | 2 Times Weekly | Remove grates,remove all paint stripper sludge and blast media into proper container, remove and clean filter screen or trench basket and reinstall,rinse trench clean,wash and reinstall grates. | 50 ft long L-shaped trench | Paint sludge from chemical depainting process | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||
| 180 | 18008 | Trench Drain | Trench Drain | CMXG | Paint Shop | 2 Times Weekly | Remove grates,remove all paint stripper sludge and blast media into proper container, remove and clean filter screen or trench basket and reinstall,rinse trench clean,wash and reinstall grates. | 125 ft long rectangular-shaped trench | Paint sludge from chemical depainting process | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||
| 180 | 18009 | Trench Drain | Trench Drain | CMXG | Paint Shop | 7 Days | Remove grates,remove all paint stripper sludge and blast media into proper container, remove and clean filter screen or trench basket and reinstall,rinse trench clean,wash and reinstall grates. | Approx 64 ft long L-shaped trench, connected w/IWC 18007 | Paint sludge from chemical depainting process | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | |||||
| 180 | 18010 | Paint Stripping Tank (Estimated 18 ft long x 3 ft wide x 4 ft deep) | Tank | CMXG | Paint Shop | On Request | Remove all liquids into appropriate receptacle and remove all residue from interior of tank including all installed features. | 21'L x 5'W x 4'H | Methylene Chloride, paint sludge | 3 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | went from 180 days to on request | ||||
| 180 | 18011 | Paint Stripping Tank (Small) | Tank | CMXG | Paint Shop | On Request | Remove all liquids into appropriate receptacle and remove all residue from interior of tank including all installed features. | Paint sludge from chemical depainting process | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | ||||||
| 180 | 18012-A | Sanding Booth | Sanding Booth | CMXG | Depaint Shop | Daily | Remove all dust, particles, and residue from walls, and floor of booth. Empty and clean all trays. | Dust with cadmium, chromium and lead above OSHA limits. | 1 hour | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | New 2/25/16 | |||||
| 180 | 18012-B | Sanding Booth | Sanding Booth | CMXG | Depaint Shop | 7 Days | Remove all dust, particles, and residue from ceiling, walls, 8 ft. high and lower. | Dust with cadmium, chromium and lead above OSHA limits. | 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | New 2/25/16 | |||||
| 180 | 18012-C | Sanding Booth | Sanding Booth | CMXG | Depaint Shop | 90 Days | Remove all dust, particles, and residue from ceiling (including all flat surface, conduit and light fixtures), walls, floor of booth, and booth entance facing. Empty and clean all trays. Remove all dust, particles, and residue from all exterior surfaces of the booth including walls, roof, filter housings, conduit, piping, catwalk, etc. | Dust with cadmium, chromium and lead above OSHA limits. | 1.75 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | New 2/25/16 | |||||
| 180 | 18013-A | Dry Filter Paint Booth | Paint Booth | CMXG | Paint Shop | 7 Days | Clean all paint from light diffusers. Replace light diffuser covers. Remove all dust, residue, and debris from walls and floor. Inspect and re-cover fire sprinklers with new paper bags as required. Remove all floor covering and tape from floor. Replace floor covering and tape to cover all floor space. | 20 Ft W x 50 Ft D x 16 Ft H = 1,000 Sq Ft | Paint waste and debris. Chromated primer overspray. Cadmium and Chromium. | |||||||
| 2 hours | 42 USC 6901, 40 CFR 260, 40 CFR 263, 29 CFR 1910.1027 , 29 CFR 1910.1026, NFPA 30, AFI 32-7042, RAFB ISWMP, RAFB HWMP, RAFB 01560 | New 10/6/16 - In use - Replaces 18001 |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.