Atch 2- FD2060-24-31655 Tunner OH Bridge QASP_COR Final.pdf
PDF 274 KB Posted
- Attached to
- Tunner Aircraft Cargo Loader (ACL) Bridge Federal contract opportunity
- Solicitation number
- FA8534-24-R-0011
About this file
This document is a Quality Assurance Surveillance Plan (QASP) for the overhaul of Tunner Aircraft Cargo Loaders (ACL) under a bridge contract. The QASP outlines the government's methodology for assessing the contractor's performance and quality management system, including monitoring of technical deliverables, schedule adherence, and quality control. It describes the roles and responsibilities of the Multi-Functional Team, Contracting Officer's Representative, and contractor, and specifies procedures for addressing unsatisfactory performance through the issuance of Performance Assessment Reports and Corrective Action Reports. The QASP also addresses requirements for contractor trafficking in persons monitoring and mishap reporting. The related federal contract opportunity is a sole source bridge contract for overhaul, Periodic Preventive Maintenance, and unscheduled depot-level maintenance of the Tunner ACL, to be awarded to Leonardo DRS for a one-year base period with four one-year options.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR: FD2060-24-31655 QASP REVISION: 0 1
Quality Assurance Surveillance Plan for
Tunner Aircraft Cargo Loaders (ACL) Overhaul Bridge
Purchase Request: FD2060-24-31655
05 March 2024
PR: FD2060-24-31655 QASP REVISION: 0 2
1.0 Purpose
The Quality Assurance Surveillance Plan (QASP) is a government-developed document used to determine if the contractor’s performance meets the performance standards contained in the contract. The QASP establishes procedures on how this assessment/inspection process will be conducted. It provides the details associated with a continuous oversight process, to include:
• What will be monitored
• How monitoring will take place
• Who will conduct the monitoring
• How monitoring efforts and results will be documented
1.1 The contractor is responsible for implementing and delivering performance that meets contract standards using its Quality Control Plan. The QASP provides the structure for the government’s surveillance of the contractor’s performance and their Quality Assurance/Quality
Control (QA/QC) actions to assure they meet contract standards. It is the government’s responsibility to be objective, fair and consistent in evaluating contractor performance.
1.2 The QASP is not part of the contract nor is it intended to duplicate the contractor’s Quality
Control Plan. This QASP is a living document. Flexibility in the QASP is required to allow for an increase or decrease in the level of surveillance necessary based on contractor performance.
Copies of the QASP and any revisions may be provided to the contractor to facilitate open communication. In addition, the QASP should recognize and accommodate unforeseen or uncontrollable circumstances which might occur that are outside the control of the contractor.
The QASP should ensure early identification and resolution of performance issues to minimize impact on mission performance.
1.3 Objective(s)
The QASP describes the services required for the Overhaul (OH) of the Tunner contract.
1.3.1 Overhaul (OH): OH functions include: vehicle receipt, incoming inspection, structural abnormalities identification, disassembly, repair, replacement, refurbishment, unique identification, finish coating, Time Compliance Technical Orders (TCTO’s), in-process testing, assembly, post-overhaul inspection, post-overhaul test, storage and security, packaging and shipping, and Overhaul Instructions Manual (OIM) maintenance. Overhaul of the Tunners will preserve the Operational Safety, Suitability, and Effectiveness (OSS&E) baselines (section 3 of the Prime Item Development Specification (MP- SP-006, rev 9) so that the Tunners will be available when needed, perform up to expectations, and perform safely.
1.4 Result(s)
The QASP is used for managing contractor performance assessment by ensuring that systematic quality assurance methods validate that contractor quality control efforts are timely, effective, and are delivering the results specified in the contract or task order. The QASP directly corresponds to the performance objectives and standards specified in the PWS. It provides specific details on how the Government will survey, observe, test, sample, evaluate, and document contractor performance results to determine if the contractor has met the required
PR: FD2060-24-31655 QASP REVISION: 0 3
performance standards for the objectives in the PWS. Successful completion of the objectives for the performance of the contract constitutes success of the program.
1.5 Authority
Authority for issuance of this QASP is provided under Part 46 of the Federal Acquisition
Regulation, Inspection of Services clauses, which provides for inspection, acceptance and documentation of the service called for in the contract or order. If commercial, quality assurance will be applied in accordance with commercial items clause.
2.0 Performance Assessment/Services Summary
The matrix below details the method of surveillance and frequency the COR will use to validate and inspect performance objectives. Inspection of each objective will be documented in the
COR file. Performance objectives define the desired outcomes and performance thresholds define the level of service required under the contract to successfully meet the performance objective. The inspection methodology defines how, when, and what will be assessed in measuring performance.
2.1 Method of Surveillance
Performance
Objective
PWS
Reference
Performance Threshold Method of Surveillance
Quality of
Contract Data
Requirements
List (CDRL) deliverable
4.2.1 There shall be no more
than one rejection of any deliverable. There shall be no more than 3 total rejection(s) of deliverables per contract year. The
Government will reject a deliverable if 3 or more technical errors or 10 or more minor errors are found within the deliverable. The rejected deliverable shall be corrected and resubmitted within 20 business days of notification of
Government rejection.
100% inspection of monthly CDRL submittals for quality. Inspection performed by PM and engineer.
Surveillance will be documented, at a minimum, quarterly by the COR in the
PAR or SPM COR Status Reports.
Receipt of
CDRL
deliverable
4.2.2 There shall be no more than
2 late submission(s) of deliverables per contract year. The Contractor shall notify the Government at least 5 working days prior to due date if the delivery of any data/document will not
100% inspection of monthly CDRL submittals for timeliness. Inspection performed by PM and engineer
Surveillance will be documented, at a minimum, quarterly by the COR in the PAR or SPM COR Status
Reports.
PR: FD2060-24-31655 QASP REVISION: 0 4
meet the scheduled delivery date and negotiate a revised delivery date. The data/document shall be delivered by the revised delivery date acceptable to the Government.
Delivery of
Overhauled
Loaders
4.5.1 Overhauled assets shall be
delivered in accordance with the schedule defined by the contract/order.
There shall be zero (0) late deliveries per contract year.
The Contractor shall notify the Government if the delivery of any asset will not meet the scheduled delivery date and negotiate a revised delivery date. The late asset shall be delivered by the revised delivery date acceptable to the
Government. The time between the delivery dates of the first loader inducted into the overhaul line and the last loader for each contract year shall not exceed 12 months.
Program Manager will review OH delivery report 100% weekly
Surveillance will be documented, at a minimum, quarterly by the COR in the
PAR or SPM COR Status Reports
Provide thorough and meaningful
Earned Value
Management
System
(EVMS) cost and schedule variance analyses in the
Integrated
Program
Management
Data and
Analysis
Reports
(IPMDARs)
4.5.1.1.2 No more than 3
unacceptable variance analyses per month shall be submitted; all unacceptable variance analyses shall be satisfactorily re-written and re-submitted within
20 calendar days of initial written notification.
Program Manager will review monthly, 100% of all IPMRs for open task orders.
Surveillance will be documented, at a minimum, quarterly by the COR in the
PAR or SPM COR Status Reports
Adherence to
Contractor
Quality
5.10 100% compliance with the
QMS is required.
Engineer will review the QMS system monthly, to ensure contractor is compliant. Surveillance will be
PR: FD2060-24-31655 QASP REVISION: 0 5
Management
System (QMS) documented, at a minimum, quarterly by the COR in the PAR or SPM COR Status
Reports
2.2 COR Surveillance File Documentation
The Contracting Officer Representative (COR) will establish and maintain an online file containing training and surveillance documentation in the Procurement Integrated Enterprise
Environment (PIEE) via the Joint Appointment Module (JAM) and Surveillance and
Performance Module (SPM). At a minimum, the following documentation will be maintained in
JAM/SPM by the COR or Contracting Officer, as applicable.
a. Joint Appointment Module (JAM)
• Training and Appointment
❖ DAU CLC 222, Contracting Officers Representative (COR) Online Training
❖ DAU ACQ 0030, Overview of Acquisition Ethics, or agency equivalent
❖ DAU DOD 0020, Combatting Trafficking in Persons for Acquisition & Contracting
Personnel
❖ SYS 600, Wide Area Workflow (WAWF) Introduction
❖ QAPC-Led Training Certificate
❖ Contract Specific Training
❖ DAU CLC 206, CORs in a Contingency Environment (if applicable)
❖ Confirmation of reviewing JAM/SPM Training (Memo)
❖ Refresher training (16 CLPs every three years)
❖ Confirmation of filing the annual OGE 450
• Complete COR Experience (Agency & Technical Experience)
• Designation of Contracting Officer’s Representative (Smart Form)
• Termination of Contracting Officer’s Representative (Smart Form)
b. Surveillance & Performance Monitoring Module (SPM)
• QA Surveillance Plan
❖ QASP, QASP revision(s)
• SPM Smart Forms
❖ COR Status Report (Surveillance, equivalent to PAR)
❖ Contract Discrepancy Report (equivalent to CAR)
❖ Trip Report (if applicable)
❖ Contractor Progress Report Review
❖ Correspondence Report
❖ Surveillance Schedule
❖ Surveillance Checklist
❖ Memorandum for the Record
• Manually Uploaded Documents (examples):
❖ Other Surveillance Document
PR: FD2060-24-31655 QASP REVISION: 0 6
- Performance Assessment Reports (PARs)
- Corrective Action Reports (CARs) ❖ Deliverables (CDRLs, including Contractor Status Reports)
❖ Safety Plan (Contractor)
❖ Integrated Master Schedule
- Master/Delivery Schedules ❖ Other
- Contract, including modifications (if not in EDA)
- PWS, including revisions (if not in EDA)
- DD Form 254 (if not in EDA)
- CDRLs (Form 1423 - if not in EDA)
- Customer Complaint Records
- Documentation of Contractor payment (if not processed in WAWF)
- Trip Reports
- CAV-AF Repair Item Actions Report(s)
- Surveillance Schedule/Checklist
- Annual COR File Inspection Checklist(s)
2.3 Plan for Corrective Action
2.3.1 Unsatisfactory Contractor performance will result in the COR issuing a negative PAR or
SPM Smart Form “COR Status Report” to the Contractor. The Contractor will be required to respond by the suspense date. The Contractor shall explain the deficiency and identify the corrective action they shall take to resolve the deficiency and prevent recurrence.
2.3.2 If repetitive negative PARs are issued without satisfactory resolution, the COR will initiate the CAR process. However, the MFT reserves the right to issue a CAR at any time based on the severity of the Contractor non-compliance. The COR will prepare and sign the CAR, and forward to the Contracting Officer (CO) for signature. The CO will set a suspense date and submit the CAR to the Contractor for corrective action. The Contractor shall sign and return the
CAR by the established suspense date with a corrective action plan to the CO for acceptance by the MFT. The plan shall include identification of the root cause and a get-well-date. The corrective action will be tracked and documented until the deficiency is resolved to the satisfaction of the MFT. The COR will upload the CAR in SPM to become part of the contract file. If the CAR process fails to resolve the deficiency, the MFT has the prerogative to issue an interim Contractor Performance Assessment Report (CPAR), and the CO has the right to invoke the Inspection of Supply/Services clause(s) identified in the contract/order.
2.3.3 CORs will establish a tracking system for corrective actions that includes date COR submitted CAR to PM/FSM, date reviewed by PM/FSM, date reviewed by CO, date issued by
CO, contractor’s identified root cause, proposed corrective action, contractor follow-up actions, and get-well date.
2.4 Acceptance of Services
PR: FD2060-24-31655 QASP REVISION: 0 7
2.4.1 The Contractor shall submit/process payment requests and receipt/acceptance documents via Wide Area Workflow (WAWF). Services will be accepted by the Program Manager.
2.4.2 CDRL deliverables shall be submitted using MEARS and directly to the MFT member identified on the CDRL. The CDRL will determine submittal requirements; however, separately priced data must be submitted and accepted in WAWF in order for the Contractor to receive payment, and both separately priced and non-separately priced data must be accepted in WAWF in order for the contract line item to be closed out.
3.0 Roles and Responsibilities of Multi-Functional Team (MFT)
3.1 General Responsibilities
3.1.1 The MFT is responsible for ensuring the acquisition utilizes Performance-Based Service(s)
Acquisition (PBSA) methods including establishment of performance thresholds, procedures to evaluate Contractor performance and positive/negative incentives to encourage the highest quality of services.
3.1.2 The MFT is responsible for conducting surveillance of Contractor performance to ensure
Government requirements, including quality of services, cost and schedule, are met. The MFT will provide the results of their surveillance to the Contracting Officer’s Representative (COR) for input into the PARs, or COR Status Reports, and to the MFT member updating the
Contractor Performance Assessment Reporting System (CPARS).
3.1.3 For contracts requiring higher-level quality requirements, the MFT is responsible for developing metrics in tracking the effectiveness of the contractors Quality Control Plan
(QCP)/Quality Management System (QMS) tie to the SS, QASP, and CPARS. Ensure contracts requiring higher-level contract quality requirements include a SS performance objective that encompasses MFT goals related to quality and directly relates to the CPARS category of
“Quality”.
3.1.4 The MFT ensures contract oversight focuses on the adequacy and adherence of the contractor to their proposed QMS. The MFT shall focus on whether the COR or contractor is first in detecting defects and trends, who (COR or contractor) accomplishes more inspections, and, whether the contractor is proactively pursuing key QMS functions to ensure quality related problems or defects do not recur.
3.2 Contracting Officer’s Representative (COR)
3.2.1 The COR is responsible for providing continuous technical oversight of the contractor’s performance. The COR will use the QASP as the primary tool for conducting surveillance of the contractor’s performance. The COR shall keep a surveillance file that accurately documents the contractor’s actual performance. The purpose is to ensure that the contractor meets the performance standards contained in the contract.
PR: FD2060-24-31655 QASP REVISION: 0 8
3.2.2 Works with the MFT in conducting and documenting surveillance on Contractor performance. Reports unethical conduct and instances of fraud, waste and/or abuse to the
Contracting Officer. Inspects and accepts/rejects deliverables during contract/order performance and at close-out to ensure contract/order terms and conditions are met. Develop an inspection schedule that shall comprise of at least ten percent of non-services summary items, as a recommended best practice. Monitors control and disposition of Government property.
Monitors Contractor payment and verifies it is commensurate with Contractor performance.
Documents Contractor performance via PARs, or SPM COR Status Reports, and CARs. Issues
PARs, at a minimum, quarterly and negative PAR(s) or CAR(s), as required.
3.2.2.1 If issuing a PAR, the COR will forward to the CO and the Contractor for signature.
After all signatures have been obtained, the COR uploads the signed PAR in SPM under “COR
Documents” (select “Add Documents”, and then select the Document Type, “Other Surveillance
Document”).
3.2.2.2 If issuing a COR Status Report, the CO will approve the report in SPM after submission.
The COR will print the report in pdf format and email it to the contractor. If the contractor responds to a negative report, the COR should upload the email correspondence with the contractor into SPM.
3.2.3 Registers in PIEE as a COR. Self-nominates in JAM as the designated COR for the contract. If required, files the annual Office of Government Ethics (OGE) Form 450, Confidential Financial Disclosure Report. Establishes and maintains a COR File – training documentation is maintained in JAM, and surveillance documentation is maintained in SPM.
3.2.4 Establish a System for Award Management (SAM) Individual Account after designation as a COR to search and view Service Contract Reporting (SCR) information. After the contractor has submitted the SCR, the COR or Program Manager will review contractor reported information for reasonableness and consistency. If SCR revisions are required, the COR will notify the contractor no later than November 15. By November 30, the contractor shall revise the report, or document the rationale.
3.2.5 Ensure contractor’s Quality Control Plan/Quality Management System (QMS) complies with contract requirements. CORs need to place special emphasis in ensuring the contractor’s
QMS is being followed as written, plus is effective in bringing about the desired results – performance equal to or greater than the SS metrics, plus an inspection and corrective action program that identifies and fixes issues without having to be identified by the Government.
3.3 Contracting Officer’s Representative (COR) Supervisor
3.3.1 Upon the Contracting Officer’s request for COR support, selects a qualified nominee.
Confirms the COR nominee has no personal conflicts of interest, and verifies that the COR has the appropriate clearance for the contract/order. If required, ensures the COR files the annual
OGE Form 450. Ensures the COR takes initial, annual and any additional training required by the contracting activity. Ensures the COR completes 16 hours of refresher training every three years after completion of DAU CLC 222, Contracting Officer’s Representative Online Training.
PR: FD2060-24-31655 QASP REVISION: 0 9
3.3.2 Registers for the SPM Manager Role via PIEE to obtain access to the COR’s Online file in
SPM. Ensures the COR registers in PIEE, and self-nominates as the designated COR for the contract in JAM. Upon email notification of the COR self-nomination, approves the nomination via email link. Conducts regular reviews of the COR Online File to ensure surveillance documentation is timely and complete and conducts an annual review of the COR’s Profile to ensure the COR’s technical experience is complete and up-to-date. Considers performance of
COR duties in their annual appraisal.
3.4 Contracting Officer (CO)
3.4.1 Only individual authorized to enter into contracts and determines if a COR is required. If the requiring activity has not initiated a COR nomination in JAM, the CO submits a Request for
Contracting Officer’s Representative Support memorandum to the requiring activity.
Determines whether a COR is required to file an OGE Form 450. Provides Contract-Specific
Training to the COR.
3.4.2 Upon notification of COR Supervisor approval of the COR’s nomination, reviews the nomination in JAM, and completes the Smart Form Designation Letter. The contract must be awarded and in EDA to complete the designation process in JAM. The CO shall provide a copy of the designation memo to the Contractor. Upon notification of transfer/retirement of the COR, the CO shall complete the Termination Letter in JAM. The CO shall provide a copy of the termination memo to the Contractor, and designate the replacement COR.
3.4.3 Reviews the COR reports on contractor performance in SPM, and approves/rejects PARs, CARs, or COR Status Reports. Reviews the COR Profile and COR Online File, at a minimum, annually. Documents the results of their review on the Annual COR File Inspection Checklist and uploads to SPM under COR Documents (select “Add Documents”, and select category
“Miscellaneous”, Subcategory “Other”, and label as “Annual COR File Inspection Checklist”).
Checklist must be signed by the CO, COR, and COR Supervisor prior to uploading to SPM.
3.5 Quality Assurance Program Coordinator (QAPC)
3.5.1 Supports the MFT in the development of the contract/order quality assurance requirements specifically ensuring the requirements are clearly stated and enforceable. Prior to contract/order award, provides training to CORs and COR management. Ensures training requirements are accomplished in accordance with DoDI 5000.72, DoD Standards for COR Certification.
Monitor records of all COR training records and conducts reviews of SPM records for assigned organizations.
3.5.2 Provides functional, not technical, support for JAM/SPM users including assistance with registration and role activation.
3.6 Contractor
PR: FD2060-24-31655 QASP REVISION: 0 10
3.6.1 Participates as a member of the MFT upon approval of the Justification & Approval (J&A) or Sole Source Justification (SSJ) if the acquisition is sole source, and upon contract/order award, if it is competitive.
3.6.2 The Contractor shall ensure the quality of services through a quality and/or inspection system. In order to meet the government’s quality requirements, a contractor’s QCP/QMS should be robust enough and resourced adequately to execute four key quality functions: 1)
Detection of quality program problems and defects; 2) Identification of root causes for quality related problems/defects; 3) Correction of root causes related to detected problems/defects; and,
4) Follow-up to ensure quality related problems/defects do not recur; a mature QMS requires the contractor be the proactive party on quality issues. The goal is to obtain performance reflective of continuous improvement with no reliance on COR’s surveillance to detect problems/defects, determine root causes, or ensure quality related problems/defects do not recur.
3.6.3 Signs and returns a positive PAR within five business days. Signs and returns a negative
PAR with corrective action identified by the suspense date. Signs and returns a CAR with a corrective action plan by the suspense date.
3.6.4 Report the total amount invoiced and contractor labor hours expended on the services performed during the previous fiscal year. Prime contractor labor hours, including any required
Tier 1 subcontractor information, shall be reported in the System for Award Management
(SAM). The reporting period for contractors is open from October to November for reporting against the prior fiscal year.
3.7 Functional Services Manager (FSM)
3.7.1 The FSM provides primary program oversight, nominates the COR, ensures the COR is trained before performing any COR duties and supports the COR’s performance assessment activities.
3.7.2 The Functional Services Manager has determined these services are not mission-essential and will not continue in the event of a crisis. Reference PWS and QASP signature page.
4.0 Management Strategy
4.1 The MFT will meet and record minutes quarterly to review contractor’s performance. The
COR will issue PARs, or COR Status Reports, documenting both satisfactory and unsatisfactory
Contractor performance, at a minimum, quartely.
4.2 If repetitive negative PARs or a single negative PAR identifying critical Contractor non-compliance are issued without satisfactory resolution, the CO or Contract Specialist will issue a
CAR. However, the MFT, through approval of the Contracting Officer, reserves the right to issue a CAR at any time based on the severity of the Contractor non-compliance. If the CAR process fails to resolve the unsatisfactory Contractor performance, the CO has the right to invoke the Inspection of Supply/Services clause(s) identified in the contract/order.
PR: FD2060-24-31655 QASP REVISION: 0 11
4.3 Incentives
4.3.1 If Contractor performance meets or exceeds contractual requirements, positive incentives may include, but are not limited to, decreased surveillance (by revision to the QASP/Method of
Surveillance), favorable CPARs and exercising options.
4.3.2 If Contractor performance does not meet contractual requirements, negative incentives may include, but are not limited to, increased surveillance, unfavorable CPARs, not exercising options and Government recourse authorized by the Inspection of Supply/Services clause(s) identified in the contract/order.
5.0 Annual COR File Inspection: The Contracting Office shall perform, with participation of the
COR and COR supervisor, a yearly administrative review of the COR's online file. The
Contracting Officer will document the results of their review on the Annual COR File Inspection
Checklist. The COR and COR Supervisor will acknowledge the results of the annual inspection via signature on the checklist. The Contracting Officer, or Contract Specialist, will upload the checklist to the COR’s Online file.
6.0 Contractor Performance Assessment Reporting System (CPARS): The total estimated value of the contract exceeds $1,000,000.00; therefore, CPARS reporting is required.
6.1 The MFT will evaluate Contractor performance. The Assessing Official Representative
(AOR) will review the PARs and other information contained in the COR Online File to prepare and substantiate the CPAR. CPARS will be updated, at a minimum annually, documenting
Contractor performance for the contract/order. The MFT should refer to the latest CPARS
Guidance for CPAR processes and timelines, https://www.cpars.gov/sysreq.htm. Users can refer to Table 4.9 for the CPARs Timeline, and “Table 1 for the Business Sector, Dollar Threshold and Reviewing Official” information.
6.2 In evaluating the quality of contractor’s performance, the following performance ratings are used in documenting past performance. The areas rated may include: Quality, Schedule, Cost
Control (if applicable), Management, Small Business Subcontracting (if applicable), and
Regulatory Compliance.
Performance
Rating
Criteria
Exceptional Performance meets contractual requirements and exceeds many to the government’s benefits. The contractual performance of the element or sub-element being assessed was accomplished with no problems and contractor actions were highly effective.
Very Good Performance meets contractual requirements and exceeds some to the government benefits. The contractual performance was accomplished with few minor problems for which corrective actions taken by the contractor were effective.
Satisfactory Performance meets contractual requirements. The contractual performance contains some minor problems for which corrective actions taken by the contractor were satisfactory.
https://www.cpars.gov/sysreq.htm
PR: FD2060-24-31655 QASP REVISION: 0 12
Marginal Performance does not meet some contractual requirements. The contractual performance reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear marginally effective or were not fully implemented.
Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
7.0 Safety Requirements
7.1 Mishap Notification/Investigation: The Contractor shall report mishaps in accordance with the safety requirements identified in the PWS. The Contractor shall ensure the Safety Office, COR, and CO are notified of mishaps.
7.2 MFT Surveillance: MFT member(s) will report any potential safety hazards or actual mishaps to the COR. The COR will monitor Contractor reporting and review any mishap notifications. The COR will address safety and/or health issues in the PAR or CAR, as applicable.
8.0 Trafficking in Persons: IAW DFARS PGI 222.17, Combatting Trafficking in Persons, the
COR will monitor the contractor’s performance regarding trafficking in persons, such that non-compliance with FAR clause 52.222-50, Combatting Trafficking in Persons, is brought to the immediate attention of the Contracting Officer. The Contracting Officer shall report that the contractor, subcontractor, or employee has failed to comply with the requirements of FAR clause
52.222-50. The Contracting Office may use any of the remedies outlined in PGI 222.1704 to report the violations. The COR should refer to the U.S. Department of State website, at http://www.state.gov/j/tip, for the latest guidance of monitoring trafficking in persons.
http://www.state.gov/j/tip
PR: FD2060-24-31655 QASP REVISION: 0 13
MIDDLEBROOKS.DEB MIDDLEBROOKS.DEBORAH.A.1
Digitally signed by
ORAH.A.1280272937 280272937
Date: 2024.03.05 16:23:28 -05'00'
DOUGLAS.ELIZAB
Digitally signed by
DOUGLAS.ELIZABETH.E.159530
ETH.E.1595304802 4802
Date: 2024.04.08 11:58:58 -04'00'
9.0 Signatures
By signing below, you are appointed to the MFT for this acquisition and accept the above responsibilities.
QAPC
Contracting Officer Representative (COR)
COR Supervisor
Contracting Officer
Contractor (Optional) Date
By signing below, you are identifying these services as not mission-essential.
Functional Services Manager (formerly FC/FD)
| 2024-04-10T12:47:09-0400 | |
| COLE.DANA.SIRES.1401654409 |
| 2024-05-08T11:40:04-0400 | |
| HOLDER.AMY.M.1265867720 |
File details come from the government source that posted it. Updated .