Atch 6 - Halvorsen Metrics Determination and Incentive Fee Arrangement_Final.docx

DOCX document 32 KB Posted

Attached to
Halvorsen Overhaul Federal contract opportunity
Solicitation number
FA8534-24-R-0007
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

This document is an attachment that outlines the incentive fee arrangement for a Fixed Price Incentive Firm target (FPI(F)) contract for the overhaul of Halvorsen Aircraft Cargo Loaders. The contract includes cost and schedule incentives, with a maximum total price not to exceed 120% of the target cost. The contractor will earn 50% of the total profit as normal profit, and the remaining 50% will be placed in a schedule incentive pool. The schedule incentive will be earned for on-time delivery of the overhauled loaders. The government may, at its sole discretion, remove the schedule incentive and add all the schedule incentive fee dollars to the cost incentive profit pool if the contractor demonstrates the capability to continue on-time overhaul deliveries. The related federal contract opportunity is for a 5-year, FPI(F)/FFP/Indefinite Delivery Requirements-type contract for the overhaul and unscheduled depot-level maintenance of the 25K Halvorsen Aircraft Cargo Loader.

View the file

Other files for this federal contract opportunity

Other files attached to Halvorsen Overhaul, newest first.
File Type Posted
FA8534-24-R-0007 Amend 0001.pdf PDF
Halv OH CDRL Portfolio_9 Sep 24.pdf PDF
Atch 4-Safety Appendix_Final.docx DOCX document
Atch 1. FD2060-24-31666 PWS Halverson OH Bridge Final.docx DOCX document
FA8534-24-R-0007_Final..pdf PDF
Atch 7 - Halvorsen Reg Numbers_Final.xlsx XLSX spreadsheet
Atch 2 QASP Halverson OH Bridge Final.pdf PDF
Atch_9 Pricing_Instructions._Final.pdf PDF
Atch_8-Cost_Proposal_Adequacy_Structure_Final.pdf PDF
Atch 5 - Halvorsen GFE_GFM_Final.xlsx XLSX spreadsheet
Atch 1-FD2060-24-31666 PWS Halverson OH Bridge Final.docx DOCX document
Atch 4-Safety Appendix.docx DOCX document
Atch 5 - Halvorsen GFE_GFM.xlsx XLSX spreadsheet
Atch 7 - Provisions for ROK.docx DOCX document
Atch 8 - Halvorsen Reg nums.xlsx XLSX spreadsheet
Atch 2- FD2060-24-31666 QASP Halverson OH Bridge Final.pdf PDF
Atch 6 - Halvorsen Metrics Determination and Incentive Fee Arrangement.docx DOCX document
FA8534-24-R-0007_Draft.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 6 17 September 2024 Halvorsen Incentive Fee Arrangement

General: This is a Fixed Price Incentive Firm target (FPI(F)) contract with cost and schedule incentives. The maximum total price paid on each task order, including incentives earned, shall not exceed the established ceiling price (120% of target cost). Total Price Paid = Cost (adjusted for over/underrun share) + Normal Profit + Schedule Incentive Profit earned. 50% of the task order profit will be payable to the Contractor as normal profit subject to adjustment IAW FAR Clause 52.216-16, Incentive Price Revision – Firm Target. 50% of the task order profit will be placed in the schedule incentive pool (see Table 1 below).

Table 1

Profit Pool Distribution
Percentage of Total Profit
Dollar Amount
Cost Incentive
50%
$*
Schedule Incentive
50%
$*

I. INCENTIVE ARRANGEMENT FOR OVERHAUL FPI(F) CLINs

1. Cost: The cost incentive will be subject to a share ratio of 50%/50% (Government/Contractor).

2. Schedule: The schedule incentive to be earned will be based on “on-time” delivery of each of the overhauled loaders. The Contractor will earn the schedule incentive for each "on-time" delivery as set forth in the Schedule, based on the due dates established therein. Although the schedule incentive may be obligated at time of task order award, the Contractor is not authorized to invoice for the schedule incentive earned for the "on-time" delivery until all of the following conditions are met:

a. The Contractor has completed the loader overhaul in accordance with the terms of this delivery order on or before the delivery date set forth in the Schedule, with acceptance as documented on a DD Form 250 (see table 3),

b. The Contractor submits a request for payment of the "on-time" schedule incentive along with the signed DD Form 250 as documentation that delivery of the overhauled loader occurred on or before the delivery date set forth in the Schedule of each task order,

c. The Government reviews the submitted documentation and the Contractor provides any additional information necessary to support the Contractor's request for schedule incentive payment, and

d. The Contractor's request for payment of the schedule incentive is approved by the cognizant Contracting Officer as evidenced by the signed request for payment on the "on-time" schedule incentive.

3. Schedule Incentive adjustment: Beginning with this contract, the Government will assess the Contractor’s past Tunner overhaul delivery performance. If the Government determines the Contractor is capable of continuing on-time overhaul deliveries, the Government may, at its sole discretion, remove the schedule incentive and add all schedule incentive fee dollars to the Cost Incentive profit pool distribution in (table 2) below. The Government will unilaterally reinstate the schedule incentive on any future task order if the Contractor fails to meet contractual overhaul delivery dates.

Table 2

Profit Pool Distribution
Percentage of Total Profit
Dollar Amount
Cost Incentive
100%
$*

Table 3 Schedule Incentive Milestone Dates

Schedule Incentive Milestones Target Completion Date

DD250 of each completed Tunner overhauled loader
*

· Note: Loader delivery dates will be filled in at time of task order award