About this file

This document provides follow-up questions from the Department of the Air Force regarding a potential consolidation of two federal contract opportunities. The opportunities being considered for consolidation are a 72kW Ground Power Unit and a 144kW Universal Load Bank. Industry feedback is requested on the pros and cons of proposing to a consolidated 72kW/144kW effort versus separate efforts for each product. Responses should address whether the company would be willing to propose to a consolidated opportunity and the advantages and disadvantages from the industry perspective of both a consolidated and separate procurement approaches. The point of contact for any questions or correspondence related to these potential opportunities is also provided.

View the file

Other files for this federal contract opportunity

Other files attached to 72kW Ground Power Units (GPU), newest first.
File Type Posted
QA 12.docx DOCX document
DRAFT GPM LM_8 Sep 2021.doc DOC document
Updated Informal Draft RFP FA8532-21-R-0011.pdf PDF
Final Statement of Work (SOW)_1 Sep 21.pdf PDF
Draft CDRLs C010 through C017.pdf PDF
Conference Attachment 1_3d Conceptual Illustration_144KW Generator.PDF PDF
Conference Attachment 2_Timeline.pptx PPTX presentation
Conference Attachment 4_Sections L and M.pdf PDF
Conference Attachment 3_Informal Draft Request for Proposal FA8532-21-R-0011.pdf PDF
GPM_Pre-Solicitation_Conference_Brief.pptx PPTX presentation
RFP Attachment 1 - Past Performance Information (PPI) for Offerors.pdf PDF
RFP Attachment 5 - Relevancy Table.pdf PDF
RFP Attachment 6 - Subcontractor and Teaming Member Consent Form.pdf PDF
RFP Attachment 8 - Client Authorization Letter.pdf PDF
RFP Attachment 9 - GPU Engine Derating Calculation Worksheet --DRAFT WATERMARK ADDED.pdf PDF
RFP Attachment 2 - Oral Presentations for Discussions Slide Deck.pptx PPTX presentation
RFP Attachment 7 - Past Performance Questionnaire.pdf PDF
RFP Attachment 10_Price Spreadsheet.xlsx XLSX spreadsheet
Informal Draft Request for Proposal FA8532-21-R-0011.pdf PDF
Draft GPM Ordering Guide.docx DOCX document
Statement of Work (SOW).pdf PDF
M-900. EVALUATION BASIS FOR AWARD.pdf PDF
RFP Attachment 8 - Client Authorization Letter.pdf PDF
Informal Draft Request for Proposal FA8532-21-R-0001.pdf PDF
RFP Attachment 1 - Past Performance Information (PPI) for Offerors.pdf PDF
RFP Attachment 2 - Oral Presentations for Discussions Slide Deck.pptx PPTX presentation
Document Updates and Pre-Solicitation Conference.docx DOCX document
RFP Attachment 5 - Relevancy Table.pdf PDF
RFP Attachment 10_Price Spreadsheet.xlsx XLSX spreadsheet
Draft CDRLs.pdf PDF
Government Strategy Update for Industry Awareness.docx DOCX document
Draft LM and CLIN Schedule.docx DOCX document
DRAFT GPM LM.doc DOC document
SOW_GPM_2021-05-20.docx DOCX document
Draft Purchase Description Feedback Extension.docx DOCX document
Export Controlled Draft Purchase Descriptions.docx DOCX document
Sample_CUI_Cover_Markings.pptx PPTX presentation
CUI_Training.pptx PPTX presentation
Controlled_Unclassified_Information_Requirements.docx DOCX document
GPM Consolidated Industry Feedback Responses.docx DOCX document
Announcement on Purchase Descriptions.docx DOCX document
Industry QA 6.docx DOCX document
Industry QA 5.docx DOCX document
Follow up QA for Industry Day - Number 4.docx DOCX document
Follow up QA for Industry Day - Number 3.docx DOCX document
Follow up QA for Industry Day.docx DOCX document
72kW GPU - High Level Parallel Testing.pptx PPTX presentation
QA Received from Industry Day.docx DOCX document
72kW Generator Industry Day Briefing 16-17 Sep 2020.pptx PPTX presentation
72GPU TEP.xlsx XLSX spreadsheet
Show all 50

72kW Ground Power Units (GPU) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Follow-up Question for Industry Feedback

1. The Government is considering various options for the 144kW GPU and Universal Load Bank. One option being discussed is the consolidation of the two efforts into one contract. What is your company’s thoughts on proposing to a 72kW/144kW consolidated effort? Would your company be willing to propose to a consolidated effort, or does your company prefer separate efforts for these two GPUs? What are some of the pros and cons from industry’s perspective with both the consolidation and separate efforts?