RFP_Attachment_3a_CLINs_CostPrice_Initial_Submittal.xlsx
XLSX spreadsheet 30 KB Posted
- Attached to
- AC/MC-130J RADIO FREQUENCY COUNTERMEASURES (RFCM) Federal contract opportunity
- Solicitation number
- FA8523-14-R-30015
About this file
RFP Attachment 3a_CLINs CostPrice_Initial Submittal
View the file
Other files for this federal contract opportunity
Show all 39
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLIN Structure
| Attachment 3a |
| Initial Submittal |
| Time Period to | ||||
| Allowed to Exercise CLIN | CLIN | SubCLIN | Noun | Contract |
| Type | QTY | Unit | Unit | |
| Price | Extended |
Price
| Basic Contract: System Design | |||||
| CLIN 0001 | System Design Phase | CPFF | 1 | LOT | |
| CLIN 0002 | Anti-Tamper Plan and Design (CDRL A020) | CPFF | 1 | EA | |
| CLIN 0003 | Data (CDRLs) - A001, A002, A003, A004, A005, A006, A007, A008, A009, A010, A011, A012, A013, A014, A015, A016, A017, A018, A019, A020, A021, A022, A023, A024, A025, A026, A027, A028, A029, A030, A031, A032, A033, A034, A035, A036, B001, B006, B007, B008, B009, B010, B011, B012, B013, B016, B017, B018, B019, B021, B022, B023, B024, B025, B027, B028, B030, D001, D002, D003, D004, D005, D009, E001, E002, E004, E005, E006, E007, E008, E009, E010, E011, E012, E013, E014, E015, E016, E017, E018 | NSP | |||
| CLIN 0004 | Critical Technology Demonstration (Labor excluding Travel) | CPFF | 1 | EA | |
| CLIN 0005 | Long Lead Items - Production Representative Articles | CPFF | 1 | LOT | |
| CLIN 0006 | Travel | CRNF |
| Option 1: Integration and Test (I&T) | ||||||
| Sep 2016- Feb 2019 | CLIN 1001 | Integration and Test | CPIF | 1 | LOT | |
| Sep 2016- Feb 2019 | CLIN 1002 | AT Implementation | CPIF | 1 | LOT | |
| Sep 2016- Feb 2019 | CLIN 1003 | Production Representative Articles | ||||
| 1003AA | Trial Kit/Kit Proof Units (Group A and Group B) | CPIF | 4 | SETS | ||
| 1003AB | Contractor E-Qual/DVT Test Units | CPIF | 1 | LOT | ||
| CLIN 1004 | Trial Kit/Kit Proof Installation | |||||
| Mar 2017- Jun 2017 | 1004AA | MC-130J Trial Kit/Kit Proof Installation | CPFF | 2 | EA | |
| May 2018 - Dec 2018 | 1004AB | MC-130J Kit Proof Installation | CPFF | 1 | EA | |
| May 2018 - Sep 2018 | 1004AC | AC-130J Trial Kit Installation | CPFF | 1 | EA | |
| Jun 2017- Feb 2018 | CLIN 1005 | Developmental Test Support | CPFF | 1 | EA | |
| Jan 2018 -Mar 2019 | CLIN 1006 | Operational Test Support | CPFF | 1 | EA | |
| Sep 2017- Sep 2018 | CLIN 1007 | Other Hardware Deliveries | ||||
| Apr 2017- Feb 2018 | 1007AA | Mission Data Test Station (MDTS) | CPFF | 1 | EA | |
| Apr 2017- Feb 2018 | 1007AB | Stand Alone Control & Display | CPFF | 2 | SETS | |
| Apr 2017- Feb 2018 | 1007AC | Breakout Box | CPFF | 2 | SETS | |
| Sep 2017- Sep 2019 | CLIN 1008 | Data (CDRLs) - A002, A003, A005, A006, A007, A008, A011, A012, A016, A017, A019, A020, A021, A034, A035, B001, B002, B003, B004, B005, B007, B009. B010, B011, B012, B013, B014, B015, B017, B019, B020, B021, B022, B026, B029, D007 | NSP | |||
| Sep 2017- Sep 2019 | CLIN 1009 | Organizational (O)-Level Support Equipment | CPFF | 1 | LOT | |
| Sep 2017- Sep 2019 | CLIN 1010 | Training (Operator and Maintainer) | CPFF | 1 | EA | |
| Sep 2017- Sep 2019 | CLIN 1011 | Weapon System Trainer (WST) Data Identification | CPFF | 1 | EA | |
| Sep 2017- Sep 2019 | CLIN 1012 | Travel | CRNF |
| May 2017- Feb 2018 | CLIN 1013 | DT Performance/Schedule Incentive |
| May 2017- Mar 2019 | CLIN 1014 | OT Performance/Schedule Incentive |
| Option 2: Government Purchased Rights | |||||
| Sep 2016- Sep 2018 | CLIN 2001 | Purchased Data Rights | FFP | 1 | LOT |
| Option 3: Government Systems Integration Laboratory (SIL) | |||||
| Sep 2016- Sep 2018 | CLIN 3001 | Government Systems Integration Laboratory (SIL) | FPI(F) | 1 | EA |
| Sep 2016- Sep 2018 | CLIN 3002 | Travel | CRNF | ||
| CLIN 3003 | Data (CDRLs) - A005, A006, A007, A020, B001, B009, B019, D008 | NSP |
| Option 4: Low Rate Initial Production (LRIP) | ||||||
| Oct 2017- Aug 2018 | CLIN 4001 | Low Rate Initial Production | ||||
| Oct 2017- Aug 2018 | 4001AA | Group A (FY17-18) | FPI(F) | NLT 1 - NTE 14 | SETS | |
| Oct 2017- Aug 2018 | 4001AB | Group B (FY17-18) | FPI(F) | NLT 1 - NTE 12 | SETS | |
| Oct 2017- Aug 2018 | 4001AC | O-Level Support Equipment | FPI(F) | 1 | LOT | |
| Oct 2017- Aug 2018 | CLIN 4002 | LRIP Spares (Group B Line Replaceable Units [LRU]) | FPI(F) | 2 | SETS | |
| May 2018- Aug 2019 | CLIN 4003 | LRIP Installs | EA | |||
| May 2018- Aug 2019 | 4003AA | Group A Installs | FPI(F) | NLT 1 - NTE 14 | EA | |
| May 2018- Aug 2019 | 4003AB | Group B Installs | FPI(F) | NLT 1 - NTE 12 | EA | |
| Oct 2017- Sep 2018 | CLIN 4004 | Data (CDRLS) -A002, A003, A005, A006, A007, A008, A011, A012, A016, A017, A019, B012, B013, B016, B021, B027, B030, D002, D003, D005, E001, E002, E004, E005, E006, E010, E011, E012, E014, E015, E016, E017 | NSP | |||
| Sep 2017- Sep 2018 | CLIN 4005 | SE/PM | FFP | 15 | MO | |
| Apr 2015-Jan 2016 | CLIN 4006 | Reserved | ||||
| May 2017- Aug 2018 | CLIN 4007 | Travel | CRNF | |||
| May 2017- Aug 2018 | CLIN 4008 | Site Training | FFP | 2 | EA |
| Option 5: Full Rate Production (FRP) | ||||||
| Oct 2019- May 2020 | CLIN 5001 | FRP 1 | ||||
| Oct 2019- May 2020 | 5001AA | Group A (FY19) | FFP | NLT 1 - NTE 12 | SET | |
| Oct 2019- May 2020 | 5001AB | Group B) (FY19) | FFP | NLT 1 - NTE 9 | SET | |
| Oct 2020- Sep 2021 | CLIN 5002 | FRP 2 | ||||
| Oct 2020- Sep 2021 | 5002AA | Group A (FY20) | FFP | NLT 1 - NTE 12 | SET | |
| Oct 2020- Sep 2021 | 5002AB | Group B (FY20) | FFP | NLT 1 - NTE 9 | SET | |
| Oct 2021- Nov 2022 | CLIN 5003 | FRP 3 | FFP | |||
| Oct 2021- Nov 2022 | 5003AA | Group A (FY-21) | FFP | NLT 1 - NTE 12 | SET | |
| Oct 2021- Nov 2022 | 5003AB | Group B (FY-21) | FFP | NLT 1 - NTE 9 | SET | |
| Oct 2018- Jan 2020 | CLIN 5004 | 1 O-Level SE (FY-19) | FFP | 1 | SET | |
| Oct 2019- Dec 2020 | CLIN 5005 | 2 O-Level SE (FY-20) | FFP | 2 | SET | |
| Oct 2020- Nov 2021 | CLIN 5006 | 3 O-Level SE (FY-21) | FFP | 2 | SET | |
| Oct 2018- Jan 2020 | CLIN 5007 | FRP Spares, Lot 1 (Group B LRU) (FY-19) | FFP | 2 | SET | |
| Oct 2019- Dec 2020 | CLIN 5008 | FRP Spares, Lot 2 (Group B LRU)(FY-20) | FFP | 3 | SET | |
| Oct 2020- Nov 2021 | CLIN 5009 | FRP Spares, Lot 3 (Group B LRU) (FY-21) | FFP | 3 | SET | |
| Oct 2020- Jan 2021 | CLIN 5010 | FRP Installs | FFP | NLT 1 - NTE 12 | EA | |
| Oct 2020- Jan 2021 | 5010AA | FRP Installs (Group A) (FY19) | NLT 1 - NTE 12 | EA | ||
| Oct 2020- Jan 2021 | 5010AB | FRP Installs (Group B) (FY-19) | NLT 1 - NTE 9 | EA | ||
| Oct 2021- Dec 2022 | CLIN 5011 | FRP Installs | FFP | |||
| Oct 2021- Dec 2022 | 5011AA | FRP Installs (Group A) (FY20) | NLT 1 - NTE 12 | EA | ||
| Oct 2021- Dec 2022 | 5011AB | FRP Installs (Group B) (FY-20) | NLT 1 - NTE 9 | EA | ||
| Oct 2022- Nov 2023 | CLIN 5012 | FRP Installs | FFP | |||
| Oct 2022- Nov 2023 | 5012AA | FRP Installs (Group A) (FY-21) | NLT 1 - NTE 12 | EA | ||
| Oct 2022- Nov 2023 | 5012AB | FRP Installs (Group B) (FY-21) | NLT 1 - NTE 9 | EA | ||
| Oct 2022- Nov 2023 | CLIN 5013 | Data (CDRLs) - A002, A003, A005, A006, A007, A008, A011, A012, A016, A017, A019, A021, B012, B013, B016, B021, B027, B030, D002, D003, D005, E001, E002, E004, E005, E006, E010, E011, E012, E014, E015, E016, E017 | NSP | |||
| Oct 2018 - Nov 2021 | CLIN 5014 | SE/PM | FFP | 1-37 | MO | |
| Apr 2015-Jan 2016 | CLIN 5015 | Reserved | ||||
| Oct 2018 - Nov 2021 | CLIN 5016 | Travel | CRNF | |||
| Oct 2018 - Nov 2021 | CLIN 5017 | Reserved |
| RFCM Sustainment | |||||
| Option 6: Interim Contractor Support | |||||
| Mar 2018-Mar 2021 | CLIN 6001 | ICS | CPFF | 1 | LO |
| CLIN 6002 | Data (CDRLS) - A002, A003, A005, A006, A007, A008, A011, A012, A016, A017, A019, A020, A021, A032, B012, B013, B016, B021, B023, B027, B028, B030, D001, D002, D003, D005, D009, E001, E002, E003, E004, E005, E010, E011, E012, E013, E014, E015, E016, E017 | NSP | |||
| Mar 2018-Mar 2021 | CLIN 6003 | Travel | CRNF |
| Option 7: Depot Activation | |||||
| Jun 2018-Mar 2021 | CLIN 7001 | Depot Activation | FPI(F) | 1 | LOT |
| Jun 2018-Mar 2021 | CLIN 7002 | D-Level SE and install | FPI(F) | 1 | EA |
| Jun 2018-Mar 2021 | CLIN 7003 | Data (CDRLs) -A002, A003, A005, A006, A007, A008, A011, A012, A016, A017, A019, A020, A021, A032, B023, B028, D001, D002, D003, D004, D005, D006, D007, D009, E004, E005, E010, E013, E014 | NSP | ||
| Jun 2018-Mar 2021 | CLIN 7004 | Travel | CRNF |
| Option 8: Technical Data Package (TDP) | |||||
| Jun 2018-Mar 2021 | CLIN 8001 | TDP | FFP | 1 | LOT |
| Jun 2018-Mar 2021 | CLIN 8002 | Other Engineering Data | FFP | 1 | LOT |
| Jun 2018-Mar 2021 | CLIN 8003 | Data (CDRLs) - A002, A003, A005, A006, A007, A008, A011, A012, A016, A017, A019, A021, E001, E002, E003, E004, E005, E010, E011, E012, E015, E016, E017 | NSP | ||
| Jun 2018-Mar 2021 | CLIN 8004 | Travel | CRNF |
Quantities
| RFCM | FY14 | FY15 | FY16 | FY17 | FY18 | FY19 | FY20 | FY21 | FY22 | FY23 | FY24 | FY25 | Total | |
| Quantities | ||||||||||||||
| EMD - A | 2 | 2 | 4 | |||||||||||
| EMD - B | 2 | 2 | 4 | |||||||||||
| LRIP -Group A | 2 | 12 | 14 | |||||||||||
| LRIP -Group B | 2 | 10 | 12 | |||||||||||
| FRP - Group A | 12 | 12 | 12 | 12 | 12 | 12 | 12 | 84 | ||||||
| FRP - Group B | 9 | 9 | 9 | 9 | 9 | 9 | 9 | 63 | ||||||
| Group B Spares | 0 | 2 | 2 | 3 | 3 | 10 | ||||||||
| Installs | 2 | 2 | 6 | 9 | 12 | 12 | 12 | 12 | 12 | 79 |