RFI QUESTIONS AND ANSWERS 4.pdf

PDF 32 KB Posted

Attached to
LONG-DISTANCE WIRED TELECOMMUNICATION SERVICES
Solicitation number
FA850126Q0056_Robins_AFB_Long_Distance_Commercial_Telecommunication_Services
Issued by

About this file

This is a Questions and Answers document from Robins Air Force Base addressing contractor inquiries regarding a service cutover contract.

The document addresses two key contractor questions. First, a contractor requested consideration of extending the cutover schedule from 90 days to 120 days after award. Robins rejected this request, citing that the Performance Work Statement (PWS) specifies 90 days and that the government is already constrained on time. Second, a contractor inquired whether Robins would accept responsibility for disconnecting all circuits, equipment, and services provided by the incumbent contractor upon successful cutover, rather than the new contractor bearing this responsibility as stated on page 9 of the Statement of Work (SOW). Robins again declined, confirming that the contractor will retain responsibility for disconnection as specified in the SOW. Both responses indicate that the contract terms are firm and non-negotiable.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI QUESTIONS AND ANSWERS #4

Q - WOULD ROBINS CONSIDER A CUTOVER SCHEDULE CLOSER TO 120 DAYS INSTEAD

OF THE CURRENT 90 DAYS AFTER AWARD?

A - NO, THE PWS STATES 90 DAYS AND WE ALREADY ARE SHORT ON TIME.

Q - WOULD ROBINS REMOVE OR OTHERWISE ACCEPT THE RESPONSIBILITY OF

DISCONNECTING “ALL CIRCUITS, EQUIPMENT, AND SERVICE PROVIDED BY THE

INCUMBENT, UDNER THE PRIOR CONTRACT,” UPON SUCCESSFUL CUTOVER, AS

OPPOSED TO BEING THE CONTRACTOR’S RESPONISIBLTIY? (AS FOUND ON PAGE 9 OF

THE SOW)

A - NO, THE CONTRACTOR WILL BE RESPONSIBLE AS STATED IN THE SOW.