This solicitation is for an Exterior Construction Contract to provide labor, supplies, materials, supervision, transportation, equipment and components for exterior construction projects at Robins Air Force Base in Georgia. It will be a firm-fixed price indefinite delivery, indefinite quantity contract for a one year base period and four one-year options to furnish all labor, equipment and materials for site preparation, demolition, repair, replacement, and minor construction of facilities, warehouses, hangars and other structures. Only the Air Force Sustainment Center/Propulsion Zero-Level Integrated Logistics Support Organization will issue task orders under this contract.

View the file

Other files

Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Number Question Request Date Answer Answer Date

1 During the site visit the interior of the building was not opened for inspection.

Is there any significant leaking or damage in the building?

Can photos of the interior condition of the building be provided?

2/22/2022

2 The building has multiple utilities entering it including

Aluminum Sulfate.

What is the function of this building?

Are there any conditions about the chemicals and processes in this building that require special design or execution considerations?

Is this building considered mission critical?

2/22/2022

Building has damage to the edge of the roof structure in the northwest corner. The SOW states “Install new 24‐ gauge 2‐piece compression flashings on all sides and ensure that the new flashing covers the existing building to same elevation where flashing was removed. “

Can the flashing be enlarged to protrct the repairs that will be required at the roof edge? 2/22/2022

Building currently has three penetrations.

Will all penetrations remain? If not, which will be abandoned?

2/22/2022

5 Hazardous material status

Has a survey has been conducted can the results be shared?

2/22/2022

6 The roof deck appears to be concrete but interior inspection was not conducted.

What is the make up of the existing roof deck? Can drawings of the existing roof structure be provided?

2/22/2022

Robins ECC IDIQ

PRE‐PROPOSAL INQUIRIES (PPI)

There are no significant leaks or damage.

Industrial Waste Treatment & Disposal.

No.

Yes.

Flashing shall be enlarged to protect the required repairs.

All penetrations will remain.

No survey has been conducted.

See SOW.

No drawings are available.

Please refer to attached images.

2/24/2022

2/24/2022

2/24/2022

2/24/2022

2/24/2022

2/24/2022

See attached photos.