About this file

This document contains a request for information and related federal contract opportunity. The request for information seeks clarification on whether teaming agreements and past performance will be recognized for a forthcoming solicitation for exterior construction contract work at Robins Air Force Base in Georgia. The government confirms it will recognize valid teaming arrangements but the prime contractor must still meet special standards of responsibility. The related federal contract opportunity is a firm-fixed price indefinite delivery, indefinite quantity contract for one base year and four option years to provide all labor, materials, equipment, supervision and components for site preparation, demolition, repair, replacement and minor construction projects for facility and building exteriors at Robins Air Force Base, to be issued by the Air Force Sustainment Center on behalf of the Air Force Materiel Command.

View the file

Other files for this federal contract opportunity

Other files attached to Exterior Construction Contract, newest first.
File Type Posted
Solicitation Amendment FA850122R00020001 SF 30 (1).pdf PDF
Picture_4.jpg JPG image
Picture_6.jpg JPG image
Picture_7.jpg JPG image
Picture_2.jpg JPG image
Picture_3.jpg JPG image
Picture_8.jpg JPG image
Picture_1.jpg JPG image
Picture_5.jpg JPG image
Robins ECC PPI_Govt Responses.pdf PDF
RFI 3 21 Feb 22 .pdf PDF
RFI 21 February 2022.pdf PDF
ECC Demonstration Site Visit_17 Feb 22.pdf PDF
Proposal site visit Briefing ECC IDIQ.ppt PPT presentation
ECC RFI 1 Question and Answer 08 Feb 22 .pdf PDF
Solicitation - FA850122R0002 (1).pdf PDF
Demonstration Project 130307 Statement of Work .pdf PDF
Exterior Construction Contract (ECC) IDIQ SOW .pdf PDF
Civil Engineering Facility Requirements.pdf PDF
Safety App UHHZ 210375.pdf PDF
Sample Bid Bond ECC IDIQ.pdf PDF
Special Standards Responsibility Minimum Requirement .pdf PDF
AF Form 2586 Flightline Driving Request.pdf PDF
Demonstration Project 130307 Proposal Worksheet Pricing Worksheet.pdf PDF
Demonstration Project 130307 SUBMITTAL REGISTER.xls XLS spreadsheet
AFMAN 31-116 Motor Vehicle Traffic Supervision.pdf PDF
WR-ALC SAFE-T-GRAM.pdf PDF
Wage Determination.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI#2 Exterior Construction Contract

Question: 1. The Government's response (Attached), states in part that:

"Teaming agreements/commitment letters will not be recognized because the Government is only contractually bound to the prime contractor."

2. However, FAR 9.603 states that "The Government will recognize the integrity and validity of contractor team arrangements; provided, the arrangements are identified and company relationships are fully disclosed in an offer or, for arrangements entered into after submission of an offer , before the arrangement becomes effective."

My interpretation as it currently reads is that the Government response is not consistent with FAR 9.603.

Please advise?

As an example: Concierge Business Solutions, Inc. (Prime contractor, licensed Georgia general contractor, 8a, HUBZone, SDVOSB).

Intends to form a teaming arrangement with an Architectural Services firm (Subcontractor, licensed, architect, 8a, SDVOSB) and a national roofing firm (subcontractor)

Based on the example above, does the Government's response mean that this teaming arrangement and combined past performance will not be recognized by the Government even if it is clearly identified and fully disclosed in our proposal?

Government Response: The Government will recognize and permit valid teaming arrangements for this solicitation. However, in accordance with FAR 9.604(b) the policy recognizing teaming arrangement does not limit the Government’s rights to determine the responsibility of the prime contractor (see subpart 9.1). The Special Standards of Responsibility must be met and obtained from the prime contractor and/or approved Joint Venture Partner. Past performance is not being evaluated as a part of this solicitation.