Demonstration Project 130307 SUBMITTAL REGISTER.xls

XLS spreadsheet 36 KB Posted

Attached to
Exterior Construction Contract Federal contract opportunity
Solicitation number
FA8501-22-R-0002
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

This submittal register outlines the required submissions for an exterior construction contract at Robins Air Force Base. The contract will provide site preparation, demolition, repair, replacement, and minor construction services for facilities, warehouses, and hangars on a firm-fixed price IDIQ basis. Contractors must submit their AF Form 3064 & 3065, schedule of prices, samples of proposed roofing/siding and warranty materials, design analysis, shop drawings, erection drawings, a solid waste disposal plan, list of subcontractors, and details of their proposed project manager and certified foreman within 45 days of the notice to proceed. Closeout documents including AutoCAD and PDF as-built drawings, warranty documentation, manufacturer's inspection reports must also be provided prior to the end of the contract.

View the file

Other files for this federal contract opportunity

Other files attached to Exterior Construction Contract, newest first.
File Type Posted
Solicitation Amendment FA850122R00020001 SF 30 (1).pdf PDF
Picture_2.jpg JPG image
Picture_4.jpg JPG image
Picture_6.jpg JPG image
Picture_7.jpg JPG image
Picture_3.jpg JPG image
Picture_8.jpg JPG image
Picture_1.jpg JPG image
Picture_5.jpg JPG image
Robins ECC PPI_Govt Responses.pdf PDF
RFI 3 21 Feb 22 .pdf PDF
RFI 21 February 2022.pdf PDF
ECC Demonstration Site Visit_17 Feb 22.pdf PDF
Proposal site visit Briefing ECC IDIQ.ppt PPT presentation
RFI 2 11 Feb 22.pdf PDF
ECC RFI 1 Question and Answer 08 Feb 22 .pdf PDF
Solicitation - FA850122R0002 (1).pdf PDF
Safety App UHHZ 210375.pdf PDF
Demonstration Project 130307 Statement of Work .pdf PDF
Exterior Construction Contract (ECC) IDIQ SOW .pdf PDF
Civil Engineering Facility Requirements.pdf PDF
Sample Bid Bond ECC IDIQ.pdf PDF
Special Standards Responsibility Minimum Requirement .pdf PDF
AF Form 2586 Flightline Driving Request.pdf PDF
Demonstration Project 130307 Proposal Worksheet Pricing Worksheet.pdf PDF
AFMAN 31-116 Motor Vehicle Traffic Supervision.pdf PDF
WR-ALC SAFE-T-GRAM.pdf PDF
Wage Determination.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SCHEDULE OF MATERIAL SUBMITTALS
ROBINS AFBPROJECT NO.PROJECT TITLESOLICITATION/CONTRACT NO.
UHHZ130307RPR/RPL ROOF,IND WST TRMT & DISP, B.113
TO BE COMPLETED BY PROJECT ENGINEER
NO. OF COPIES REQUIRED
BEFORE CONSTRAFTER CONSTR
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALOTHER MATERIAL OR DATACLOSEOUTREQUIRED SUBMITTAL
DATEDATE

RECEIVED

IN

CONTRACTING DATE

TO

CIVIL

ENGR. RETURN

SUSPENSE

DATEFOLLOW-UPDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL
APPROVALREMARKS
APPROVEDDISAPPROVED
1AF Form 3064 & 3065 ( Electronic)1Within 45 days of NTP
2Schedule of Prices (Electronic)1Within 45 days of NTP
3Roofing/Siding Material (Electronic)1Within 45 days of NTP
4Sample of Warrany (Electronic)1Within 45 days of NTP
5Design Analysis (Electronic)1Within 45 days of NTP
6Engineered Shop Drawings (Electronic)1Within 45 days of NTP
7Erection Drawings (Electronic)1Within 45 days of NTP
8Soild Waste Disposal Plan (Electronic)1Within 45 days of NTP
9List of Proposed Subcontractors (Electronic)1Within 45 days of NTP
10Project Manager & Certified Foreman (Electronic)1Within 45 days of NTP
11Auto CAD & PDF Drawings, Closeout Package (Hard & CD)4Prior to Closeout
12Warranty (Hard & CD)4Prior to Closeout
13Manufacter's Inspection Report (Hard & CD)4Prior to Closeout
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
NOTE: This Submittal Schedule is for the Contractor's use in assembling and organizing the Submittals to be made to the Government. See individual specification sections for possible additional submittal requirements.
LEGEND:
A - Include with line 9 Operations and Maintenance Manual
B - Include with line 10 Warranty Book
C - Include with line 14 Color Samples

&LFA4600-11-B-0025