Sheet 1

COMPUTATION AND JUSTIFICATION FOR LIQUIDATED DAMAGES
PROJECT: UHHZ 070225 & UHHZ 030148DATE:14-May-09
I.ENGINEERING/INSPECTION COSTS
GRADE/STEPHOURS/DAY$/HOURTOTAL/DAY
PROJECT MANAGERGS-12/51.5$34.44$51.66
INSPECTORGS-11/53.0$28.73$86.19
CLERICALGS-5/50.5$15.67$7.84
TOTAL ENGINEERING/INSPECTION COST PER DAY$145.69
II.CONTRACTING/ADMINISTRATIVE COSTS
GRADE/STEPHOURS/DAY$/HOURTOTAL/DAY
CONTRACTING OFFICERGS-12/51.0$34.44$34.44
CONTRACT ADMINISTRATORGS-10/52.0$26.15$52.30
CLERICALGS-5/50.5$15.67$7.84
TOTAL CONTRACTING/ADMINISTRATIVE COST PER DAY$94.58
III.STAFF/JUDGE ADVOCATE COSTS
GRADE/STEPHOURS/DAY$/HOURTOTAL/DAY
ATTORNEYGS-12/51.0$34.44$34.44
CLERICALGS-5/50.5$15.67$7.84
TOTAL STAFF JUDGE ADVOCATE COST FOR FIRST DAY*$42.28
*STAFF JUDGE ADVOCATE COSTS ARE NOT APPLICABLE FOR SUBSEQUENT DAYS
IV.ADDITIONAL COSTS TOTAL/DAY
LOSS OF USE OF BUILDING*
LOSS OF USE OF RUNWAYS/TAXIWAYS
LOSS OF USE OF LIVING QUARTERS BY NONCOMPLETION
LOSS OF REVENUE FROM FACILITIES PROVIDING SERVICES OR RECREATION
RENTAL OF BUILDINGS WHILE WAITING FOR PROJECT COMPLETION
QUARTERS ALLOWANCE PAYMENTS
OTHER (SPECIFY)
TOTAL ADDITIONAL COST PER DAY*$0.00
*The Project Manager shall attach a Detailed Breakout to support the Additional Losses and Justify their reasonableness in accordance with FAR 12.202(B).
TOTAL LIQUIDATED DAMAGES FOR FIRST DAY (Sum of blocks I, II, III and IV)$282.55
TOTAL LIQUIDATED DAMAGES FOR SUBSEQUENT DAYS (Sum of blocks I, II and IV)$240.27
IN ACCORDANCE WITH FAR 11.502(B), IT IS THE DETERMINATION OF THE CONTRACTING OFFICER THAT LIQUIDATED DAMAGES (ARE) (ARE NOT) APPLICABLE TO THE PROJECT. THIS DETERMINATION IS MADE BASED UPON THE FACT THAT THE CONTRACTOR (HAS) (DOES NOT HAVE) COMPLETE CONTROL OF THE PACE OF WORK. IT IS FURTHER DETERMINED THAT THE RATE OF ASSESSMENT FOR THE DAILY TOTAL LIQUIDATED DAMAGES IS REASONABLE. THESE LIQUIDATED DAMAGES ARE APPLICABLE IF THE CONTRACTOR FAILS TO COMPLETE THE PERFORMANCE OF THE SPECIFIED WORK DURING THE TIME(S) SPECIFIED IN THE CONTRACT.
C.O. SIGNATURE:DATE: