STATEMENT OF WORK - 01005

14 May 2009 UHHZ 070225, Const/Pave Area South Of Building 359

PART 1 - GENERAL

1.01 STATEMENT OF WORK: This is a general overview of the project. Also see Section 01020, Construction Design and Performance Requirements, and 01030, Design after Award.

A. Location: Accomplish Work at Robins AFB, GA.

B. Preaward Submittals. Submit the following before award during non-competitive negotiations:

1. Cost - Cost breakout with base bid, design cost, and options on separate sheets. Provide complete breakouts in similar fashion for each subcontractor.

2. Schedule - A schedule from award to construction complete in MS Project or Excel format

3. AE Firm - The name of the AE firm and any subs they will be using. Note that the Government reserves the right to approve/disapprove the lead design firm and the design subcontractors. See section 01030 for details.

C. Price: The original contracted price includes special work times for utility outages and repair of damages. The words "at no additional cost to the Government" apply to all such situations whether stated or not.

D. Contract Documents: Follow details shown by the specifications and drawings, interpreted in accordance with contract clauses. The DFARS clause 252.236-7001, Contract Drawings and Specifications, is hereby incorporated by reference if not listed in the Standard Form 1442 of the contract. Note especially the clause's instructions regarding designer intent.

E. Project Scope, Objectives, and Criteria. This is not the usual contract for construction, but is a contract for Design and Construction. (Design/Build) The work includes the following:

1. Construct a pervious parking lot in the grassy area south of building 359 in order to provide overflow parking and as a showcase of LEED approved parking technology.

2. The parking stalls shall be constructed using a grass paver system similar to the GrassPave2 and the driveway shall be constructed using technology similar to GravelPave.

3. Provide an underground infiltration system that will ties into the current storm water management system.

F. General Congestion:

1. Work area is restricted to the grassy area south of the building 359.

2. Contractor staging area will be limited to area indicated on drawing cover sheet.

1.02 CONTINUED OCCUPANCY:

A. Access: Building 359 shall remain in full operation during the time of the project. The contractor will be given full access to the project area.

B. Security: none C. Beneficial Occupancy: The Government reserves the right to take beneficial occupancy of parts of the project area before the total project completion date. This is not final acceptance, and identified deficiencies must still be corrected.

1.03 HOURS OF WORK:

A. Standard work hours for this project are 7:00AM to 4:00 PM local time, Monday through Friday. Work must stop on official Government holidays and work curtailment days, unless specifically approved in advance.

B. Alternate Work Hours

1. If the Contractor desires to work another set of standard hours, such as four 10-hour days, submit written request five (5) workdays before the date desired to work the different standard.

2. OMIT

3. The Government reserves the right to refuse these requests. However, they will usually be approved unless they negatively affect the base or the using activity. For example, the using activity may have difficulty paying overtime for escorts in controlled areas. In addition, work requiring inspector presence such as placing concrete may not be possible outside normal hours on short notice. Digging outside of normal hours will normally not be approved.

C. All references to days mean calendar days unless otherwise noted.

D. OMIT

1.04 SUBMITTALS:

A. General: Provide the following submittals in accordance with instructions found in Section 01300, Submittals and Contractor Furnished Items. The contractor may submit manufacturer’s data in lieu of the required certificate of compliance if he desires. The government requires manufacturer’s data if an “X” appears under the “Mfg. Data Required” column.

B. Material Submittals: Omitted.

C. Other Submittals: Provide the following submittals as required by the contract or as directed by the Contracting Officer.

Inspector
Para #DescriptionDate RequiredCheck Mark
1.01 EEvacuation Notice21 days prior_______
1.03 BAlternate Work Hours5 days prior_______

PART 2 - PRODUCTS - OMITTED

PART 3 - EXECUTION

3.01 COMMENCEMENT OF WORK

A. Project Schedule: See the schedule requirements detailed in Section 01300 and in Section 01030, paragraph 7. No design or construction shall commence until the Government has approved the schedule at the Kickoff Meeting after Award.

B. Construction Prohibition: Do not order any materials or start any construction until all submitted drawings are stamped and signed by the contractor's professional architects or professional engineers, and they subsequently are signed by Robins AFB approval personnel that are listed in Section 01030, paragraph 7.

C. Noncompliance Impacts: Any contractor costs resulting from noncompliance with these requirements are the sole expense of the contractor. Noncompliance shall not be cause for contract extensions or other considerations, but they may be cause for the Government to charge the contractor for liquidated damages for all negative impacts upon the Government.

3.02 COORDINATION: The superintendent (or contractor on-site project manager) shall coordinate work between different disciplines.

A. Avoid conflicts between new mechanical, electrical, architectural, and civil systems. Also, avoid conflicts between new work and existing structural or physical aspects or features of the facility. Request guidance from the Technical Representative of the Contracting Officer, and then perform such work at no additional cost to the Government.

B. Locations shown are approximate and may be moved if approved by the Technical Representative of the Contracting Officer. Show such variations on as-built drawings and do them at no additional cost to the Government.

C. Manufacturers' recommendations and/or requirements, if more stringent than the specifications and drawings, shall be followed at no additional cost to the Government.

3.03 GOVERNMENT-FURNISHED PROPERTY will not be provided in this project.

A. OMIT

B. OMIT

C. OMIT

3.04 AS-BUILTS: Also see Section 01300 and Section 01310 for submittal items such as as-builts that apply to all projects.

<<<<< END OF SECTION >>>>>

UHHZ 030148, Const/Driveway North, B333/B359

PART 1 - GENERAL

1.01 STATEMENT OF WORK: This is a general overview of the project. Also see Section 01020, Construction Design and Performance Requirements, and 01030, Design after Award.

A. Location: Accomplish Work at Robins AFB, GA.

C. Preaward Submittals. Submit the following before award during non-competitive negotiations:

4. Cost - Cost breakout with base bid, design cost, and options on separate sheets. Provide complete breakouts in similar fashion for each subcontractor.

5. Schedule - A schedule from award to construction complete in MS Project or Excel format

6. AE Firm - The name of the AE firm and any subs they will be using. Note that the Government reserves the right to approve/disapprove the lead design firm and the design subcontractors. See section 01030 for details.

C. Price: The original contracted price includes special work times for utility outages and repair of damages. The words "at no additional cost to the Government" apply to all such situations whether stated or not.

D. Contract Documents: Follow details shown by the specifications and drawings, interpreted in accordance with contract clauses. The DFARS clause 252.236-7001, Contract Drawings and Specifications, is hereby incorporated by reference if not listed in the Standard Form 1442 of the contract. Note especially the clause's instructions regarding designer intent.

E. Project Scope, Objectives, and Criteria. This is not the usual contract for construction, but is a contract for Design and Construction. (Design/Build) The work includes the following:

4. Construct a pervious parking lot in the grassy area south of building 359 in order to provide overflow parking and as a showcase of “green” parking technology.

5. The parking stalls shall be constructed using a grass paver system similar to the GrassPave2 and the driveway shall be constructed using concrete paver technology.

6. Provide an underground infiltration system that will tie into the current storm water management system.

4. Provide sprinkler and ground cover to enhance the esthetics of parking area.

F. General Congestion:

1. Work area is restricted to the grassy area south of the building 359.

3. Contractor staging area will be limited to area indicated on drawing cover sheet.

1.02 CONTINUED OCCUPANCY:

C. Access: Building 359 shall remain in full operation during the time of the project. The contractor will be given full access to the project area.

D. Security: none C. Beneficial Occupancy: The Government reserves the right to take beneficial occupancy of parts of the project area before the total project completion date. This is not final acceptance, and identified deficiencies must still be corrected.

1.03 HOURS OF WORK:

A. Standard work hours for this project are 7:00AM to 4:00 PM local time, Monday through Friday. Work must stop on official Government holidays and work curtailment days, unless specifically approved in advance.

B. Alternate Work Hours

1. If the Contractor desires to work another set of standard hours, such as four 10-hour days, submit written request five (5) workdays before the date desired to work the different standard.

2. OMIT

3. The Government reserves the right to refuse these requests. However, they will usually be approved unless they negatively affect the base or the using activity. For example, the using activity may have difficulty paying overtime for escorts in controlled areas. In addition, work requiring inspector presence such as placing concrete may not be possible outside normal hours on short notice. Digging outside of normal hours will normally not be approved.

C. All references to days mean calendar days unless otherwise noted.

D. OMIT

1.04 SUBMITTALS:

A. General: Provide the following submittals in accordance with instructions found in Section 01300, Submittals and Contractor Furnished Items. The contractor may submit manufacturer’s data in lieu of the required certificate of compliance if he desires. The government requires manufacturer’s data if an “X” appears under the “Mfg. Data Required” column.

B. Material Submittals: Omitted.

C. Other Submittals: Provide the following submittals as required by the contract or as directed by the Contracting Officer.

Inspector
Para #DescriptionDate RequiredCheck Mark
1.01 EEvacuation Notice21 days prior_______
1.03 BAlternate Work Hours5 days prior_______

PART 2 - PRODUCTS - OMITTED

PART 3 - EXECUTION

3.01 COMMENCEMENT OF WORK

A. Project Schedule: See the schedule requirements detailed in Section 01300 and in Section 01030, paragraph 7. No design or construction shall commence until the Government has approved the schedule at the Kickoff Meeting after Award.

B. Construction Prohibition: Do not order any materials or start any construction until all submitted drawings are stamped and signed by the contractor's professional architects or professional engineers, and they subsequently are signed by Robins AFB approval personnel that are listed in Section 01030, paragraph 7.

C. Noncompliance Impacts: Any contractor costs resulting from noncompliance with these requirements are the sole expense of the contractor. Noncompliance shall not be cause for contract extensions or other considerations, but they may be cause for the Government to charge the contractor for liquidated damages for all negative impacts upon the Government.

3.02 COORDINATION: The superintendent (or contractor on-site project manager) shall coordinate work between different disciplines.

A. Avoid conflicts between new mechanical, electrical, architectural, and civil systems. Also, avoid conflicts between new work and existing structural or physical aspects or features of the facility. Request guidance from the Technical Representative of the Contracting Officer, and then perform such work at no additional cost to the Government.

B. Locations shown are approximate and may be moved if approved by the Technical Representative of the Contracting Officer. Show such variations on as-built drawings and do them at no additional cost to the Government.

C. Manufacturers' recommendations and/or requirements, if more stringent than the specifications and drawings, shall be followed at no additional cost to the Government.

3.03 GOVERNMENT-FURNISHED PROPERTY will not be provided in this project.

A. OMIT

B. OMIT

C. OMIT

3.04 AS-BUILTS: Also see Section 01300 and Section 01310 for submittal items such as as-builts that apply to all projects.

<<<<< END OF SECTION >>>>>