01020 – (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS

Const/Pave Area South of Building 359

INDEX

1. GENERAL

2. PROJECT DESCRIPTION

3. DESIGN REQUIREMENTS

4. SPACE REQUIREMENTS

5. CIVIL DESIGN

6. GEOTECHNICAL DESIGN

7. ARCHITECTURAL DESIGN

8. STRUCTURAL DESIGN

9. MECHANICAL DESIGN

10. ELECTRICAL DESIGN

1. GENERAL

1.1 Commencement of Work

See schedule requirements detailed in Section 01005 (paragraph 3.01), Section 01030 (paragraph 7), and Section 01503. No design (and thus no construction) shall commence until the Government has reapproved the Preaward schedule at the Kickoff Meeting after Award.

1.2 Final Determination of Project Cost

On contracts and modifications to contracts that involve negotiated price proposals, there must be upfront estimates of the quantities of materials required to accomplish the scope of work. The Government reserves the right to revisit these negotiated quantities and types/sizes of materials to verify the actual quantities used by the Contractor. See Section 01030 for details on the Cost Breakout required at the First Final submittal. The Contractor shall upon request submit proof of exact quantities used of each type/size of material, and the final total price of the contracted work shall be based upon actual quantities and not the original estimates, although the amount paid for the design portion will not change. If the Contractor does not provide adequate proof to the satisfaction of the Contracting Officer within 30 days of the announcement of reopened negotiations, then the Contracting Officer may elect to determine a final price by percentage of the originally negotiated price for the construction part. The Government will then only pay this final determined total price.

1.3. Regulatory, Reference Requirements, and Standards: See Appendix A to Section 01020.

1.4. Technical Criteria and Standards

ROBINS ARCHITECTURAL COMPATIBILITY STANDARDS

ROBINS AIR FORCE BASE FACILITY STANDARD

INTERNATIONAL BUILDING CODE (IBC) 2003

UNDERWRITERS LABORATORIES STANDARDS (UL)

UNIFORM FEDERAL ACCESSIBILITY STANDARD (UFAS)

2. PROJECT DESCRIPTION

2.1. See Section 01005, Paragraph 1.01.

2.2. If additional land survey data is required beyond what the Government has provided, it will be the responsibility of the Contractor to obtain that survey data.

3. DESIGN REQUIREMENTS

Design submittals will be as indicated in SECTION 01030, DESIGN SUBMITTAL REQUIREMENTS. Initial submittals establish the design and construction schedule.

4. SPACE REQUIREMENTS

4.1. Administrative type personnel will occupy the facility. The intent of the design is to provide an environmentally friendly parking to showcase “green” technology and provide overflow parking for the occupants of building 359. The Parking lot will be composed of two types of permeable pavement technologies. The parking stalls will be constructed using a series of rings connected on a flexible grid system similar to GrassPave2(see attached). The drive way shall be constructed using permeable concrete pavers.

4.2. Approximately ___50__personnel will occupy the facility.

5. CIVIL DESIGN

5.1. Technical Criteria and Standards

5.1.1. All referenced material under this title in Paragraph 1.

5.2. Site Development

5.2.1. Site Survey

The Contractor shall verify all topographic information prior to design. This would include verification of all underground and aboveground utilities, all surface features, and horizontal and vertical control datum.

5.2.2. Demolition

5.2.2.1. Demolish and remove from site existing site elements as required to achieve design intent.

5.2.3. Erosion Control

The design shall include an Erosion Control Plan in accordance with the State of Georgia "Manual for Erosion and Sediment Control", latest revision at time of contract award. Prior to construction, the Contractor shall provide an Erosion Control Package, which meets all state and local requirements. In addition, all necessary permits shall be obtained by the Contractor and complied with throughout all phases of construction. Any violation to such permits will result in the immediate shutdown of work until corrective measures have been taken at the Contractor's expense.

5.2.4. Curb and Gutters

For new and/or existing streets or drives, combination concrete curb and gutter shall be used. Combination concrete curb and gutter shall be 24" wide. Minimum curb radii at intersections shall be 20 ft. Curbs shall be depressed at entrances to driveways to allow for smooth transition. Rolled combination curb and gutters are not permitted.

5.3. Pavement Design

Concrete pavers and pervious pavement design will be required for this project. Existing paved roads and parking areas will be utilized for this project and will be repaired and/or replaced as required if damaged during construction.

5.4. Removal and Disposal

There are no approved waste areas within the limits of Robins Air Force Base. All waste shall be disposed of off-base at the Contractor’s expense.

5.4.1. Disposal Sites

Off-base disposal of dry debris (nonhazardous waste) may be at any approved local site. Hazardous waste must be disposed of at sites that meet EPA landfill requirements, and are approved by the Contracting Officer.

5.5. Borrow Area

Borrow material shall be obtained from off-base sources and non-Government controlled areas. Approved materials shall be those classified in ASTM D 2487 as GC, GM, SW, SP, SM, SC, ML, and CL and shall be free of trash, debris, roots or other organic matter or stones larger than 3" in any dimension. These requirements shall be addressed in the specifications developed by the Contractor.

5.6. Contractor's Storage Yard

If approved by the Contracting Officer, the Contractor will be allowed limited space to put an office and/or storage trailer for this contract. The location will be as identified by the Technical Representative within 5 miles of project site. Items for this contract stored for the project on Base are the responsibility of the Contractor. Replace all such items stolen, vandalized, damaged, or otherwise unusable at no additional cost to the Government. Site shall be kept clean and orderly.

5.7. Haul Route

*** Show this on drawings, or describe it below. *** See Drawings.

5.8. Grading

A digging permit from the Base is required prior to any excavation operations. Finished floor elevations for the additions shall be 6 inches above the highest point of the adjacent outside finished grade. Drainage shall be diverted away from buildings at a 5 percent slope for the first 10'-0" away from the building then a slope of at least 2 percent thereafter. Collection swales shall be a minimum distance of 20'-0" away from a building. Access road and connecting street grades shall not be less than 0.5 percent or exceed 5.0 percent. Ponding anywhere on the site will not be permitted. A topographic survey of the area is provided and shall be used as part of the original proposal submittal. Any additional survey, testing or mapping required for the design or construction of the project shall be the responsibility of the Contractor.

5.9. Storm Runoff and Drainage System

Reference Section 01560 for permitting requirements.

5.9.1. Existing System

All existing storm drainage inlets which are to remain as part of the new storm drainage system as shown on the plans shall be inspected and, if necessary, thoroughly cleaned of leaves and sediment to facilitate drainage. All components of the existing drainage system utilized shall be analyzed for flow capacity in order to protect surrounding areas from flooding. New roof drains shall be 6 inches minimum PVC pipe.

5.9.2. Storm Runoff

Storm runoff shall be calculated with consideration for the following:

a. Select design values to be used in the storm drainage design calculations, including: rainfall intensity, surface runoff, and retardance coefficients.

b. Selected storm drainage plan with respect to planned connections to the existing storm drainage system, when applicable.

c. Alternate schemes considered in arriving at selected storm drainage plan.

d. Considerations for future expansion and change in land use within the watershed, particularly above the project site.

e. Principal means of collection and disposal of storm water in the new storm drainage system. Include calculations for runoff and estimated sizing of pipe and drainage structures.

f. Method proposed for handling roof runoff from gutter downspouts (roof drain collector system).

g. Connections of building's mechanical drain to outside drainage system, where applicable, and cross-referencing to the appropriate section and design discipline, when required.

h. Types of materials to be specified for storm drains, culverts, and drainage structures, allowing full range of options of suitable materials for each installation.

The design frequency for the collection systems and surface drainage shall be 10 years. The Contractor shall provide a certified storm drainage plan with the final Civil design submittal, verifying that the design will handle runoff as specified, and that the design has analyzed for impact on outfall stream banks and drainage structures on and off the site to water shed basin. The storm drainage system will utilize as its final depositor the existing storm drainage system on site and/or the existing ditching system on site.

5.9.3. Storm Drainage System

Storm drain systems shall be designed so that the hydraulic grade line for the computed design discharged is as near optimum depth as practicable and velocities are not less than 2.0 ft./sec when the drains are one-third or more full.

5.9.3.1. Drainage of Roads and Pavements

Provide a positive crown or sheet drainage to all streets and roads. Pavement collectors for storm water shall be by curb inlets and gutters. Open areas shall be drained by field inlets and an underground collection system, utilize existing system as much as possible. Overland flow shall be held to a minimum.

5.9.3.2. Specific Storm Drainage Criteria

5.9.3.2.1. Design Criteria

The drainage system will be designed in accordance with specific requirements of TM 5-820-1, TM 5-820-3, and TM 5-820-4.

The following values will be used to determine rainfall runoff for a 10-year storm frequency.

a. Minimum Time of Concentration =

20 minutes - turf areas

10 minutes - paved areas

5 minutes - roof areas

b. Intensity - Frequency Curve:

2.7 inches per hour.

c. Runoff Coefficients:

1.00 - paved areas

0.40 - turf areas

d. Rational (CIA) Method will be used.

5.9.3.2.2. Drainage Structures

Formulas for calculating hydraulic capacities will be as follows:

Weir Formula:

Q = CLB 3/2, for grade inlets where:

Q = capacity of grate or grates

C = constant = 3.0

L = length of throat opening

H = depth of water opening (a value of 0.4' will be used)

Minimum Factor of Safety (FS) = 2.0 in grassed areas, 1.5 in paved areas.

Orifice Formula:

Q = 0.7 L (A+Y) 3/2 will be used for curbed inlets on slopes where:

Q = capacity of inlet, in CFS

L = length of clear opening in feet

A = depth of depression of flow line at inlet, in feet

Y = depth of flow in approach gutter, in feet

5.9.3.2.3. Drainage Pipe

Min. Size:

Collectors = 12" dia.

Roof Drains = 6" dia. min. PVC

Roughness Factors:

Concrete Pipe = 0.012

C.M.P. = 0.024

Max. Inlet Capacities:

Type "A" single grate (2'x3') in grassed areas (H = 0.4', FS = 2.0): 4.0 CFS

Route roof drains to nearest storm drain manhole via 6 inch PVC with cleanouts at all "Y's" and "T's."

5.9.3.3. The minimum velocity of flow in conduits during a design storm shall be 2.0 ft/sec. Maximum flow shall not exceed 10 ft/sec.

5.10. Utilities

Show all existing utilities (size and approximate location) on the submittal drawings. Surveying required for this project is the responsibility of the Contractor. The Contractor shall obtain a digging permit, including utility verification, from the Base Civil Engineer’s office.

5.11. Fencing

5.11.1. Contractor Yard (If Applicable)

A temporary security fence shall be provided around the Contractor's yard. Fencing shall be 6 feet high chain link with tan canvas screening.

5.12. Landscaping

General landscaping will be designed in accordance with Base Facility Standard. Also after construction, all disturbed areas shall be seeded with either Centipede or Bermuda grass if planted between April and August. Use Penntine or Falcon fescue if planted between September and March. Areas surrounding the perimeter of the new facility shall be sodded.

5.13. Calculations

Provide design calculations for the following:

5.13.1. Water System

a. Domestic Water Calculations

b. Irrigation System Calculations

5.13.2. Storm Drainage

a. Runoff Calculations

b. Drainage Patterns

c. Storm Drain Calculations

d. Curb and surface inlet calculations

e. Profiles

5.13.3. Sanitary Sewer

a. Sanitary Sewer (average and peak flows demands and velocities)

b. Profiles

6. GEOTECHNICAL DESIGN - An underground infiltration bed will need to the be designed and constructed to handle stormwater that infiltrates parking media. The contractor will be responsible for conducting soil percolation tests to determine the required depth, composition and construction for the infiltration bed.

7. ARCHITECTURAL DESIGN

7.1. Scope and Objectives

Provide an environmental friendly parking lot adjacent to existing impervious parking lot at building 359.

a. Parking lot shall be constructed using grass pavers, concrete pavers or gravel paver systems.

b. An underground infiltration bed will be needed in order to allow for proper drainage of the parking lot.

c. Provide mechanical, electrical, and communication system rooms on the exterior of the facility along the middle of the rear wall. The design-build contractor shall determine the appropriate layouts and sizes of these rooms at an early stage of the design process.

8. STRUCTURAL DESIGN Omitted

9. MECHANICAL DESIGN Omitted

10. ELECTRICAL DESIGN Omitted

<<<<< END OF SECTION >>>>>