Questions_&_Answers_Part_6.docx

DOCX document 14 KB Posted

Attached to
F-22 Horizontal Stabilizer Fixtures Federal contract opportunity
Solicitation number
FA8224-19-R-A002
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Additional Questions and Answers

View the file

Other files for this federal contract opportunity

Other files attached to F-22 Horizontal Stabilizer Fixtures, newest first.
File Type Posted
Questions_&_Answers_Part_7.docx DOCX document
Questions_&_Answers_Part_5.docx DOCX document
CDRL_A001.pdf PDF
Question_&_Answers_Part_4.docx DOCX document
Statement_of_Work_updated.pdf PDF
Question_&_Answers_Part_3.docx DOCX document
Question_&_Answers_Part_2.docx DOCX document
CDRL_A003.pdf PDF
CDRL_A001.pdf PDF
AFMAN91-203.pdf PDF
CDRL_A002.pdf PDF
Statement_of_Work.pdf PDF
Question_&_Answers.docx DOCX document
Section_L_Past_Performance_Information.docx DOCX document
FA822419RA002_updated.pdf PDF
Tab_12_Section_M.pdf PDF
CDRL_A002.pdf PDF
Tab_12_Section_L.pdf PDF
CDRL_A001.pdf PDF
Tab_12_FA822419RA002.pdf PDF
CDRL_A003.pdf PDF
Tab_12_Statement_of_Work.pdf PDF
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F-22 HORIZONTAL STABILIZER FIXTURES

FA8224-19-R-A002

QUESTIONS & ANSWERS PART 6

Question:

The Solicitation Form 33, Section D, “Packaging and Marking, page 6 of 41. None were listed and we assume these costs should be a part of the Unit cost. Can you please provide the packaging requirements including any special packaging instructions (if known). Or will final packaging method and costs be determined after final design approval including size and weight determinations with the contract be modified accordingly.

Answer:

There are no special packaging instructions. The cost of packaging and shipping should be included in the unit cost.

Question:

The Solicitation Form 33, Section L, “Instructions to Offerors”, paragraph 2.2. Please describe what information is required for Part IV – Contract Documentation. This part is not referenced in Section M as an evaluation factor.

Answer:

The reference to “Part IV – Contract Documentation” was an oversight and should have been removed from Section L. The contract documentation was just a reference to the Solicitation Form 33, but it was determined this would not be needed in Section L or M. Please review the Solicitation Form 33, make any applicable entries on page one and review the clauses for any applicable entries, then sign the first page of the Form 33 and submit a copy of the Solicitation Form 33 with the rest of your proposal when you submit it.