This file is a comprehensive set of questions and answers (Q&A) related to a federal contract opportunity for the Atmospheric Early Warning System (AEWS) AN/FPS-117 Radome Replacement Program. The solicitation is for an Indefinite Delivery/Indefinite Quantity (ID/IQ) contract issued by the Air Force Life Cycle Management Center to replace radomes at 27 operational Long Range Radar sites across Canada. The contract will span five base years with a two-year option, with an estimated maximum value of $40,214,000. Key details include production and installation of 28-foot composite radome assemblies, spare parts, data deliverables, travel, shipping, training materials, and legacy radome disassembly and disposal.
The contract will be awarded using full and open competition, with a NAICS code of 811210 (Electronic and Precision Equipment Repair and Maintenance) and a small business size standard of $34 million. The anticipated award date is May 2026, with proposal submissions due by September 29, 2025. Pricing will be a combination of fixed-price and cost-reimbursement arrangements. Technical documents are available on SAM.gov and restricted to offerors registered with the Joint Certification Program (JCP) Office. The contract will involve complex logistical challenges, including radome replacement at remote sites in Canada and the United States, with specific considerations for transportation, site access, and environmental conditions.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question # | Attachment Number: | Paragraph/Section/Tab | Offeror Question | Government Response |
| 1 | Attachment 1 - PWS | 1.6 | PWS section 1.6 Technical Orders reference Table 2; please provide all documents referenced in Table 2 to allow estimating disassembly existing radomes and understanding various tower interfaces. Details for the different configurations of tower bases are required to ascertain size of floor openings. | All documents referenced were loaded on SAM.gov. Access can be requested via SAM.gov. |
| 2 | Attachment 1 - PWS | 1.7 | Missing all Guidance documents |
Engineering Specification for the AN/FPS-117 Radar Radome (Document No.: 20250725 CAGE: 98747) AB-199 Drawings AB-259 Drawings Arctic Tower Drawings TM ESSCO Shell Radome Type S27-82
| S-7078-2 Base Mounting Ring Layout (55’ Radome) | All documents referenced were loaded on SAM.gov. Access can be requested via SAM.gov. | ||||
| 3 | Attachment 1 - PWS | 1.7 | PWS Section 1.7 Guidance Documents list several technical documents, in particular Engineering Specification for the AN/FPS-117 Radar Radome (Document No.: 20250725 CAGE: 98747); Can the USG please provide all documents identified in this paragraph. They are required to complete our bid submission. | All documents referenced were loaded on SAM.gov. Access can be requested via SAM.gov. | |
| 4 | Attachment 1 - PWS | 2.0 | This paragraph states "...The Contractor shall achieve a complete, effective, structured preventative maintenance program for the AN/FPS-117 Radar System and Subsystems." However, there are no CLINs or SDRLs associated with Preventative Maintenance (PM). Please clarify. If PM is a contractual requirement, then the pricing matrix, Attachment 5, will need to include additional CLINs. | PWS Revsed to "The Contractor shall achieve a complete, effective, structured radome replacement program for the USAF Long Range Radar program" | |
| 5 | Attachment 1 - PWS | 2.0 | Preventative maintenance for the AN/FPS-117 Radar System is not discussed in any other sections. Is this an error? | PWS Revsed to "The Contractor shall achieve a complete, effective, structured radome replacement program for the USAF Long Range Radar program" | |
| 6 | Attachment 1 - PWS | 2.2 | How many personnel onsite for radome replacement services must have pre-existing US secret clearances? Does this requirement vary between US and Canadian locations? | Personal security clearances are not required for this effort. | |
| 7 | Attachment 1 - PWS | 2.2 | What are the security requirements around field personnel being Canadian or US citizens? Are non-US or non-Canadian staff allowed at the LRR site locations to support radome replacement efforts? | Personal security clearances are not required for this effort | |
| 8 | Attachment 1 - PWS | 2.2 | What are the security requirements for getting personnel on site for the Canadian LRR sites? | Personal security clearances are not required for this effort | |
| 9 | Attachment 1 - PWS | 2.2 | What are the security requirements for getting personnel on site for US LRR sites? | Personal security clearances are not required for this effort | |
| 10 | Attachment 1 - PWS | 2.2 | What are the minimum security clearance requirements for Canadians with Canadian security clearances working on American LRR sites? | Personal security clearances are not required for this effort | |
| 11 | Attachment 1 - PWS | 2.2 | What are the Canadian security clearance requirements? For Canadian LRR Sites and for US LRR sites? | Personal security clearances are not required for this effort | |
| 12 | Attachment 1 - PWS | 2.2 | Is it possible to have uncleared personnel working on LRR sites who are escorted/monitored by cleared personnel? | Personal security clearances are not required for this effort | |
| 13 | Attachment 1 - PWS | 2.5 | Can the Govt please provide the list and contact information for the PRSC Alaska, Canadian Dept of National Defense and O&M Contractors to assist with offerors market research (i.e., in addition to Mitch Rohloff). This will also assist in the pricing required to secure the O&M escorts/helicopter for successful performance. | Transportation and Shipping costs are not to be proposed at this time. To better define capabilities and available resources in Canada, please contact the following: |
- General Canadian Inquiries: Terry Herman: National Defence / Government in Canada - TERRY.HERMAN@FORCES.GC.CA
- Canadian theater/Site specific Inquiries: Nasittuq, Felipe de Laminage, TPS/CSR Coordinator (Cellular# 613-315-2618).
| 14 | Attachment 1 - PWS | 2.5 | Is there a prioritized list of which sites to upgrade first? Assuming there are some are in worse shape than others. I.e., is the contract schedule representative of the prioritized list? | There is not a prioritized list, the Government will make determination of which sites work will be performed within each task order. The notional schedule attachment within the PWS was developed to help contractors evaluate potential installation schedules |
| 15 | Attachment 1 - PWS | 2.5 | Are US work visas required to work on the Canadian side? | The Government is unable to provide legal advice regarding US work visa requirements. It is the contractor's sole responsibility to ensure all field personnel have the necessary legal authorization to work in the US and Canada. |
| 16 | Attachment 1 - PWS | 3 | Can we leave behind materials such as scaffolding or does everything need to be returned? | As defined within the PWS "Contractor shall arrange for and store material, packaging, tooling, and equipment at the sites with the local maintenance group, or with Government PM or COR if the local maintenance group is unable or unresponsive." All equipment is the sole responsibility of the contractor and placement or storage must be arranged with each theater |
| 17 | Attachment 1 - PWS | 3 | No detailed specifications were provided. Can the Govt please provide as many specification documents for each site as possible? E.g., radome specs, tower specs (weight/temp limitations), generator (power) capabilities, telecom reqts, manual for each radom, etc.? Without this information, accurate Fixed Price estimates are near impossible. | All documents referenced were loaded on SAM.gov. Access can be requested via SAM.gov. |
| 18 | Attachment 1 - PWS | 3 | Are there associated costs with disposal sites (fees, etc.) in which the offerors need to price? | Disposal costs and associated fees are determined by the contractor and should be included within Radome Installation CLIN |
| 19 | Attachment 1 - PWS | 3 | Can the Govt please provide photos all domes/infrastructures for all sites? | Discovery shall be performed by contractor when tasked by the Government under the Site Survey and Installation Plan Report CLIN |
| 20 | Attachment 1 - PWS | 3.2 | Are there any Davis-Bacon Act construction considerations we need to take into account? | Davis-Bacon Act was not included in this solicitation, but the Service Contract Labor Standards were. Wage determinations for Alaska will be provided in an amendment to the solicitation. |
| 21 | Attachment 1 - PWS | 3.3 | Based on prior experience working in this region, we expect many down days due to weather related delays, e.g., air transport/travel days stuck at LSS and during actual site installs. Is the Over & Above clause to cover payment of these delays outside the Offeror's control? | Anticipated Weather/down days at the sited during the installation period should be included within proposed cost of Radome Install CLIN. Delays during Travel to and from the sites are to be separately proposed within the Travel Clin post award. |
| 22 | Attachment 1 - PWS | 1.6 Table 2 | Missing all documents in table 2 |
31P1-2GPS-14 Illustrated Parts Breakdown, Radome CW-396A/GPS 31P1-2GPS-15 Installation Instructions, Rigid Radome, CW-396A/GPS, CW- 396B/GPS 31P3-2FPS6-232-7 Installation Instructions, Tower, AB-259/FPS-6 31P6-2FPS3-375 Installation Instructions, Arctic Tower, AB-199A/FPS-3 (Koke’e Only)
| TM 87-13 (COTS) ESSCO Model M55-70-9100 Radome | All documents referenced were loaded on SAM.gov. Access can be requested via SAM.gov. | ||||
| 23 | Attachment 1 - PWS | 2.2.4 | What is the classification of the AEWS Radome Replacement program? Classification is not explicitly stated. | Unclassified | |
| 24 | Attachment 1 - PWS | 2.2.7 | 2.2.7 states: "Export of technical information to Canadian personnel shall be governed by Secretary of the Air Force (SAF)/International Affairs Policy Division (IAPD) issued Delegation of Disclosure Letter (DDL)." |
| Is this letter provided to awardee via GFx? | The government will provide to contractor if Government foreign disclosure office requires | ||||
| 25 | Attachment 1 - PWS | 2.5, 3.2 | Are there any CaC Requirements for site accesses for U.S. and Canadian facilities? If so, will the Government sponsor them? | No CAC requirements. See PWS Attachments for gaining access to sites within each theater: Memorandum For Alaska Radar System Support, Pacific Regional Site Access Request (SAR), and Customer Support Request – Third Party Request | |
| 26 | Attachment 1 - PWS | 2.5, 3.2 | What personnel security requirements will be required for U.S. and Canadian citizens? | Personal security clearances are not required for this effort | |
| 27 | Attachment 1 - PWS | 2.5.1 | Can the Govt please provide any current list of GFx that is associated with execution at the long range sites? Offerors need to know what to price. | The Government does not maintain a pre-existing list of Government Furnished Equipment (GFE). Some site may have equipment available therefore it is recommended to work with the POC's within each theater to plan accordingly. Please prepare proposals anticipating no GFE will be supplied. As detailed in the solicitation, the contractor is responsible for identifying all necessary GFE required to successfully perform the de-installation, installation, testing, and disposal of each radome at each site. This assessment is to be documented and submitted as part of the "Site Survey Report", under its designated CLIN. | |
| 28 | Attachment 1 - PWS | 2.5.1 | What is the typical availability of GFE cargo aircraft (fixed and rotary)? Can they be reserved in advance, or should we just assume they will never be available to us? | Transportation is not intended to be proposed at this time, As detailed in the solicitation and subsequent task orders, the contractor is responsible for identifying all necessary GFE and transportation required to successfully perform the de-installation, installation, testing, and disposal of each radome at each site. |
As defined within PWS 3.1.5.1 Transportation Mode Selection "The Contractor shall select the most efficient and cost-effective transportation mode available, taking into account the size, weight, and fragility of the cargo, as well as the urgency of the shipment. The Contractor shall consider using air, land, or sea transportation modes, or a combination of these, to ensure timely and safe delivery of the cargo. The Contractor shall also consider factors such as transportation costs, transit times, and cargo security when selecting the transportation mode. The Contractor shall provide written justification for the selected transportation mode, including a detailed analysis of the costs and benefits associated with each option."
| 29 | Attachment 1 - PWS | 2.5.3 | Can the Government please confirm if there are required pre-deployment medical clearances? If so, is there a required provider of those medical clearances (i.e., military clinic)? | The Government confirms that there are no specific pre-deployment medical clearances required for contractor personnel performing radome replacement work under this contract, beyond standard occupational health and safety requirements and any requirements stipulated in the solicitation documents. Contractors are responsible for ensuring their personnel are medically fit to perform the required tasks safely. |
| 30 | Attachment 1 - PWS | 2.5.3 | As a Firm Fixed Priced vehicle, will the Government please confirm taxes, tariffs, duties, and/or levies are exempt or reimbursable as ODCs? | The Government appreciates and understands your concerns. It is the offeror's responsibility to include these costs to the best of their ability. To help with some of these issues, Clause 252.225-7013, Duty-Free Entry, will be in incorporated, and also 252.243-7002, Request for Equitable Adjustment, has also been incorporated. |
| 31 | Attachment 1 - PWS | 2.5.3 | Can the Govt please confirm that costs for visas, taxes, tariffs, tax implications, etc. are allowable costs under the Travel CLIN? | Visa costs would be allowable to the travel CLIN, but not Tariffs. |
| 32 | Attachment 1 - PWS | 2.5.3 | Will the Government provide medivac services, if emergencies arise? Or is this something that would be covered under the "Over and Beyond CLIN" and priced by the Contractor? | Over & Above is not an appropriate use. Stated within PWS, The Contractor is responsible for the safety and health of all sub-contractor's employees during the performance of this contract. Contractors are liable to adhere to Occupational Safety and Health Act (OSHA) and the DoDD 4715.1E, Environmental, Safety, and Occupational Health (ESOH), Canadian Occupational Health and Safety Act, R.S.O. 1990, c. O.1 and Canada Labour Code (R.S.C., 1985, c. L-2). |
| 33 | Attachment 1 - PWS | 2.5.3 | Can the Government please confirm what treaties/MOUs are in place between the US and Canadian Governments to assist with pricing tax implications, visa processes, etc.? | United States-Mexico-Canada Agreement (USMCA). Offerors should factor all relevant costs, including tariffs, customs duties, and marking/labeling expenses, into their proposed prices. |
| 34 | Attachment 1 - PWS | 2.5.3 | Due to the information sharing with Canada, will a DD2345 be required for this scope of work? | A DD2345 is required to receive the technical documents identified within the PWS. Paragraphs 1.6 and 1.7. |
| 35 | Attachment 1 - PWS | 2.5.3 | Are any of the radome specs shared with Canada ITAR-controlled? If so, please list them. | Canada is subject to special treatment under the Arms Export Control Act. Information, including radomes specifications are releasable to support continued maintenance of the radome. as stated Distribution authorized to Department of Defense and U.S. DoD contractors only; Critical Information; 10 JAN 2023. Other requests for this document must be referred to AEWS Program Office |
| 36 | Attachment 1 - PWS | 2.5.3.1 | Please confirm that the Government will be the importer and exporter of record to minimize tariff impacts. | The contractor is responsible for acting as the Importer and Exporter of Record for all goods imported into or exported from Canada under this contract. As stated in the PWS, the contractor is responsible for all shipping, marking, and compliance with the United States-Mexico-Canada Agreement (USMCA). Offerors should factor all relevant costs, including tariffs, customs duties, and marking/labeling expenses, into their proposed prices. |
| 37 | Attachment 1 - PWS | 2.5.4 | Will the Government please confirm Gross Receipts taxes will be levied on contractors for the work to be performed in the State of Hawaii and will be reimbursed under the ODC CLIN? | As the Government, we cannot confirm specific tax liabilities. It will be the responsibility of the offeror to discover and include these costs in their proposed pricing. |
| 38 | Attachment 1 - PWS | 3.1.1 Program Management | "The Program Manager or alternate shall be available during administrative duty hours." Since this work will be performed in 4 -5 time zones, can you further define administrative duty hours? | For the purposes of this contract, "administrative duty hours" are defined as the standard duty hours of the Government Program Manager and Contracting Officer Representative (COR). These hours are between 0600 to 1700 Mountain Standard Time (MST), excluding Federal holidays. The Government will provide advance notice of any significant changes to these standard duty hours. |
| 39 | Attachment 1 - PWS | 3.1.1.2.2 Integrated Master Schedule (IMS) | "The format must be in Microsoft Excel and delivered in Adobe Acrobat PDF." In section 4.9, the verbiage is "The format must be in Microsoft Project delivered in Adobe Acrobat PDF." Can the government clarify - should the IMS be in MS Project format or Excel? | Acceptable method of delivery has been revised within PWS a to clarify Excel as an acceptable format |
| 40 | Attachment 1 - PWS | 3.1.1.2.5 | Can the four structures on top of radar antenna be removed to protect them from dust, debris, etc. as part of protection plan? If so, who is responsible for removing, replacing, and recalibrating? | The Government is requesting clarification on which "four structures" this question is referring to. If the Offeror is requesting if parts of the antenna array can be disassembled as part of the protection plan - The Contractor will not be allowed to remove/disassembles parts of the array. |
If the Offeror is referring to other equipment, external to the LRR array, that is located above the array (attached to the legacy radome) - These pieces of equipment will necessarily be required to be removed from the legacy radome during removal.
| 41 | Attachment 1 - PWS | 3.1.1.2.5 | Does the LRR radar antenna have an existing lightening protection system or LPS installed within the radome, separate (or in addition to) the radome LPS? | The LRR does have it's own LPS, separate from the legacy radome LPS. |
| 42 | Attachment 1 - PWS | 3.1.1.2.6 | What LSS sites can be reached by barge, and what size barge can be used? | As detailed in the solicitation, the contractor is responsible for identifying all necessary GFE required to successfully perform the de-installation, installation, testing, and disposal of each radome at each site. This assessment is to be documented and submitted as part of the "Site Survey Report", under its designated CLIN. |
As defined within PWS 3.1.5.1 Transportation Mode Selection "The Contractor shall select the most efficient and cost-effective transportation mode available, taking into account the size, weight, and fragility of the cargo, as well as the urgency of the shipment. The Contractor shall consider using air, land, or sea transportation modes, or a combination of these, to ensure timely and safe delivery of the cargo. The Contractor shall also consider factors such as transportation costs, transit times, and cargo security when selecting the transportation mode. The Contractor shall provide written justification for the selected transportation mode, including a detailed analysis of the costs and benefits associated with each option."
43 Attachment 1 - PWS 3.1.1.2.6 What LSS sites can be reached by road and what is the nearest municipality? Transportation is not required to be proposed/costed at this time. As detailed in the solicitation, the contractor is responsible for identifying all necessary GFE required to successfully perform the de-installation, installation, testing, and disposal of each radome at each site.
As defined within PWS Transportation Mode Selection "The Contractor shall select the most efficient and cost-effective transportation mode available, taking into account the size, weight, and fragility of the cargo, as well as the urgency of the shipment. The Contractor shall consider using air, land, or sea transportation modes, or a combination of these, to ensure timely and safe delivery of the cargo. The Contractor shall also consider factors such as transportation costs, transit times, and cargo security when selecting the transportation mode. The Contractor shall provide written justification for the selected transportation mode, including a detailed analysis of the costs and benefits associated with each option."
44 Attachment 1 - PWS 3.1.1.2.6 Are there any LSS sites that can be reached only by plane? As detailed in the solicitation, the contractor is responsible for identifying all necessary GFE required to successfully perform the de-installation, installation, testing, and disposal of each radome at each site. This assessment is to be documented and submitted as part of the "Site Survey Report", under its designated CLIN.
As defined within PWS 3.1.5.1 Transportation Mode Selection "The Contractor shall select the most efficient and cost-effective transportation mode available, taking into account the size, weight, and fragility of the cargo, as well as the urgency of the shipment. The Contractor shall consider using air, land, or sea transportation modes, or a combination of these, to ensure timely and safe delivery of the cargo. The Contractor shall also consider factors such as transportation costs, transit times, and cargo security when selecting the transportation mode. The Contractor shall provide written justification for the selected transportation mode, including a detailed analysis of the costs and benefits associated with each option."
| 45 | Attachment 1 - PWS | 3.1.1.2.6 | Is electricity available on site for contractors to use to for power tools, battery charging, water pumps for leak test? | Please contact the listed POC's within theater to provide you an answer |
| 46 | Attachment 1 - PWS | 3.1.1.2.6 | Will there be starlink capability on site for communications? If not, what is recommended communication protocol for onsite crews to speak with home office or LSS? | Please contact the listed POC's within theater to provide you an answer |
| 47 | Attachment 1 - PWS | 3.1.1.2.6 | What is the average travel time from LSS to LRR via GFE? | Please contact the listed POC's within theater to provide you an answer |
| 48 | Attachment 1 - PWS | 3.1.1.2.6 | For HI site, is any eqpt available from HI ARNG? Can equipment be brought in? | The Government does not maintain a pre-existing list of Government Furnished Equipment (GFE). Some site may have equipment available therefore it is recommended to work with the POC's within each theater to plan accordingly. Please prepare proposals anticipating no GFE will be supplied. As detailed in the solicitation, the contractor is responsible for identifying all necessary GFE required to successfully perform the de-installation, installation, testing, and disposal of each radome at each site. |
| 49 | Attachment 1 - PWS | 3.1.1.2.6 | PWS section 3.1.1.2.6 Site Survey Report states “…To ensure the most efficient use of cost and time, the method of performing the survey is recommended to include a questionnaire submitted to the PMO and O&M Contractor to gather information on the Contractors behalf. This may include photos, measurements, or other technical information. If deemed necessary, travel to the sites shall be performed IAW the travel CLIN of this contract.” If an actual site visit is deemed necessary, where are the labor costs charged/priced for personnel who travel to the site to perform this task? | All personel travel to and from sites should be proposed on the Travel CLIN. Labor costs associated with a site survey should be associated with CLIN 0004 "Site Survey and Installation Plan Report" |
| 50 | Attachment 1 - PWS | 3.1.1.2.6 | Are there any LRR and/or LSS (SRR) sites that can be reached only by plane? | Yes there are LRR locations only reachable by aircraft, SRR locations are reachable only by helicopter |
| 51 | Attachment 1 - PWS | 3.1.1.2.6 | "The site survey report shall cover items within Table 5 and be submitted NLT 90 days after receipt of order" Due to the austere locations and accessibility of the sites will the Government allow site surveys to be done incrementally or extend the NLT date to 1 year after receipt of order? |
| For example, if this is ordered on 1 Oct 25, the site survey would need to be completed NLT 1 Jan 26 which is the winter season and accessibility to sites may be limited. As a result, can the Govt change the NLT 90 days to "NLT 365 days" from ordering period. | The site survey report will be defined as the government projects surveys can be achieved. Not all sites will be tasked within the same period of performance/task order therefore 90 days is an acceptable period of performance to achieve site surveys | ||||
| 52 | Attachment 1 - PWS | 3.1.1.2.6 Table 5 | Since site specific GFE can drastically impact duration of install, can the government please define “baseline” assumptions for equipment availability (e.g., manlifts, scaffolding, etc.) to generate unit install pricing? If no baselines are provided, each offeror could develop unit pricing with considerable variation in equipment assumptions. | The Government does not maintain a pre-existing list of Government Furnished Equipment (GFE). Please prepare proposals anticipating no GFE will be supplied. As detailed in the solicitation, the contractor is responsible for identifying all necessary GFE required to successfully perform the de-installation, installation, testing, and disposal of each radome at each site. This assessment is to be documented and submitted as part of the "Site Survey Report", under its designated CLIN. | |
| 53 | Attachment 1 - PWS | 3.1.3.1.2 | Can the Government confirm a Letter of Support/Govt Sponsorship Letter will be provided for visas? | The Government is unable to provide legal advice regarding US work visa requirements. It is the contractor's sole responsibility to ensure all field personnel have the necessary legal authorization to work in the US and Canada. | |
| 54 | Attachment 1 - PWS | 3.1.4 Radome Assembly and Accessory Production and Shipping | "All material packaging and spares shall be manufactured and prepared for shipment NLT ninety (90) days after receipt of order." Due to numerous unknowns, a 90-day production timeline may be unfeasible. Would the government consider adjusting the stated production time (e.g., 180-days) as radome manufacturers are working multiple contracts across federal customers? This 90-day requirement is overly restrictive and not conducive to current industry conditions. | This requirement is intentional and designed to encourage innovative solutions and efficient processes. Offerors are expected to leverage their expertise and resources to develop a plan that meets the specified timeline or provide a credible delivery period within their proposal. | |
| 55 | Attachment 1 - PWS | 3.1.4.3.1 Radome Packaging Requirements | "Max Weight (lbs.): 2000", "ISO Shipping Container Specifications" Due to weight and shipping constraints will the government allow a trade study to determine best shipping method? | Due to the logistical complexities of transporting materials to remote sites via helicopter and the need to ensure the safe and secure delivery of equipment, the Government requires adherence to the specified ISO shipping container specifications and the 2000 lb weight limit. | |
| 56 | Attachment 1 - PWS | 3.1.4.4.1 Commercial Engineering Design Data and Associated Lists | "The Contractor shall deliver product-level 3D models and 2D drawings for use by the Government." What formats of models and drawings will the government accept? | For TDP data format types, consult the TDP Option Selection Worksheet located within the A014 Technical Data Package pdf portfolio | |
| 57 | Attachment 1 - PWS | 3.1.5 | Once shipping containers arrive by barge to LSS, who is responsible for unloading crates and staging for sling-loading to LRR (or SRR) sites via GFE? | The contractor will be responsible to coordinate with the appropriate theater to stage equipment and material. | |
| 58 | Attachment 1 - PWS | 3.1.5.2 | It is unclear whether or not the Prime and Subs/Vendors need any personal security clearances to access the various long range sites. Are there personal clearances needed? If so, what level? | Security clearances are not required for this effort | |
| 59 | Attachment 1 - PWS | 3.1.5.2 | Based upon the answer to above question, will a DD254 please be provided in an Amendment? | A DD254 is not required. | |
| 60 | Attachment 1 - PWS | 3.1.6 | Caulking used for sealing radome requires storage in temperature controlled environment. If shipped in advance to LSS or site, will the Government provide climate controlled storage facility to store sealant until the summer of radome installation? | Please contact the listed POC's within theater to provide you an answer | |
| 61 | Attachment 1 - PWS | 3.1.6 | Is climate controlled storage available at LSS? If so, what is the cost and/or capacity? | Please contact the listed POCs above to provide you an answer | |
| 62 | Attachment 1 - PWS | 3.2.2 | Missing the Government approved Radar and Site Facility Protection Plan for each specified site. | Per PWS 3.1.1.2.5 "... the Contractor shall develop and submit a comprehensive Radar Protection Plan..." "... shall be submitted to the Government for approval no later than 90 days after receipt of the task order." | |
| 63 | Attachment 1 - PWS | 3.2.5.1 | Is the Government able to provide water source at LRR sites for leak testing? If so, please provide details on what is available | Please contact the listed POC's within theater to provide you an answer | |
| 64 | Attachment 1 - PWS | 3.2.6 | "3.2.6 Contractor Warranty and Liability - The Contractor shall remain liable for the correct installation of the radomes, including any defects or non-conformities, for a period of 12 months from the date of completion of the installation." This is an unreasonable expectation, given the lack of ability to access the radomes post installation period and provide any preventive maintenance on these radomes. Additionally It is assumed that after acceptance (post installation) responsibility of the radomes would transfer to the O&M contractor . |
Will the Govt consider removing this onerous warranty? PWS will be amended to state the 12 month warranty period is intended to cover delamination, leaks, and other faults present in a radome as a result of insufficient installation procedures, manufacturing defects, or damage during shipping. The contractor is not expected, as a baseline, to maintain regular site visits to perform preventative maintenance during or after this warranty period. The length of the 12 month period was chosen to account for infrequent site visits by current O&M teams and seasonal weather playing a large factor in revealing faults.
Per the radome specficiations, "The panels shall be designed to operate under operating conditions without delamination for 20 years." (3.1.2.16) and "Maintenance shall not be necessary in order to assure there is no loss of hydrophobicity or no delamination or panel joint seals over 20 years..." (3.2.6).
| 65 | Attachment 1 - PWS | 3.2.6 | Typical warranty on workmanship for radomes excludes leaks that develop after the radome SAT to include successful water leak test, where such leaks are directly caused by post-installation physical damage due to external impacts (including but not limited to objects striking the radome or biological damage such as birds pecking or removing sealants, weather that exceeds the requirements of the radome), and are not the result of defective workmanship or materials. Please clarify warranty language to exclude leaks due to external impacts. | PWS will be amended to state the 12 month warranty period is intended to cover delamination, leaks, and other faults present in a radome as a result of insufficient installation procedures, manufacturing defects, or damage during shipping. |
| 66 | Attachment 1 - PWS | 3.2.6 | Warranty on workmanship for radomes excludes leaks that develop after the radome SAT to include successful water leak test, where such leaks are directly caused by post-delivery physical damage due to external impacts (including but not limited to objects striking the radome or biological damage such as birds pecking or removing sealants), and are not the result of defective workmanship or materials. Please clarify warranty language to exclude leaks due to external impacts. | PWS will be amended to state the 12 month warranty period is intended to cover delamination, leaks, and other faults present in a radome as a result of insufficient installation procedures, manufacturing defects, or damage during shipping. |
| 67 | Attachment 1 - PWS | 3.2.6.2 | Since external factors outside of the Contractor's control may affect the function of the radar system independent of the work being performed during radome construction, would the Government amend the Correction of Defects statement to read: The Contractor shall correct any defects or non-conformities as a direct result of radome installation at no additional cost to the Government. | The PWS will be revised to state "The Contractor shall correct any defects or non-conformities as a direct result of radome manufacturing and radome installation at no additional cost to the Government." |
| 68 | Attachment 1 - PWS | 3.2.6.3 | For clarity, will the Government amend PWS 3.2.6.3 to state: The Contractor shall then correct the defect or non-conformity within the mutually-agreed upon timeframe. | Government will rename PWS 3.2.6.3 Notification and Correction Process to "Post-Acceptance Defect Resolution" to clarify distinction between Test period and after test has been performed |
| 69 | Attachment 1 - PWS | 3.2.7.1 | Is radome disposal required to go through DRMO? If so, does metal need to be separated out? | As stated within PWS Disposal Requirements, "The Contractor shall ensure that the disposal site is in compliance with all applicable federal, state, and local regulations, including those related to environmental protection and waste management." |
| 70 | Attachment 1 - PWS | 3.2.7.3 | Is the Contractor required to provide personnel on site once crates are packed and while waiting for GFE to assist with moving the debris back to the LSS for contractor disposal at an approved facility in the US? | Please contact the listed POC's within theater to provide you an answer |
| 71 | Attachment 1 - PWS | 3.2.7.6 | In remote sites that are not accessible outside of using GFE, disposal may take several weeks based on GFE availability to remove debris and deliver back to the LSS. Once at the LSS, depending on seasonality, it may need to wait until the following season to be removed/disposed. What percentage of the radome installation CLIN is the Government proposing to retain until debris is removed from the site, via the LSS, and disposed of in the United States? Will they withhold payment if delays in disposing are associated with use of GFE to remove debris from the LSS? | The contractor will not be held responsible for elements not within their control, however Government retains the right to withhold payment until all material has been removed. It is not acceptable of a contractor leave material or equipment on site without working/proposing a solution to remove. As stated within the PWS "In the event that the Contractor is unable to remove the legacy radome material from the site within the required timeframe, the Contractor shall submit a proposal to the Government, outlining a schedule for the removal and disposal of the material. The proposal shall include a timeline for completion of the removal and disposal activities, which shall not exceed one (1) year from the date of notification to the Government Contracting Officer's Representative (COR)." |
| 72 | Attachment 1 - PWS | General | What are the duration windows for staging radomes/tools containers at the LSS sites? What, if any, are the limitations as to when project containers can be delivered to and remain at the LSS sites? | Please contact the listed POC's within theater to provide you an answer |
| 73 | Attachment 1 - PWS | 1.4 Type of Contract | PWS 1.4 does not list Shipping as CRNF but Attachment 5 - Pricing Matrix Worksheet does, please confirm that Shipping is indeed CRNF. | Yes, Shipping, CLIN 0003 and 5003 are CRNF and are not required to be bid as part of the proposal. Costs associated with shipping and travel will be determined on individual orders. |
| 74 | Attachment 1 - PWS | 1.5 Item Description | Will there be preliminary design reviews (PDRs) or critical design reviews (CDRs) required for the radomes? | For this effort, the Requirements Traceability Verification Matrix (PWS 3.1.1.2.4) shall serve the purposes of a preliminary or critical design review. As part of the RTVM process, and within Vol II of the proposal, the contractor will describe their radome product, to include "existing data or evidence that verifies that the Contractor’s radome design meets each requirement listed within the Air Force radome specification. For requirements that have not been previously verified, the Contractor shall provide a testing plan for the validation of the remaining requirements, in accordance with section 4 of the specification" |
| 75 | Attachment 1 - PWS | 2.0 General Requirements | Will the Government provide DSN service if needed? | As stated within PWS "the Contractor shall provide everything needed to accomplish PWS requirements (e.g - office and lab space, office equipment [desks, chairs, etc.] and supplies, computer equipment/software [desktop and/or laptop], telephones and telephone services [including the DSN service], " |
| 76 | Attachment 1 - PWS | 2.2 Security Requirements | What are the minimum security clearance requirements, by nation for Contractor and/or Subcontractors at each project location (LSS, LRR)? | Security clearances are not required for this effort |
| 77 | Attachment 1 - PWS | 2.2.1 Non-Disclosure Agreements (NDA) & 3.1.5 Radome Shipping, Handling, Transportation, and Disposal | What is the export classification of the radars and radomes? | Unclassified CUI REL: USA/ CAN |
| 78 | Attachment 1 - PWS | 2.5 Theater Operations and Support | How will the cost of utilizing O&M contractors be priced? Should it be priced in the FFP or Over & Above CLIN? | It should be priced in the FFP. |
O&A is reserved for unforeseen issues and work that meets the DFARS 252.217-7028 definition (unforeseen work within scope, not covered by existing CLINs, and necessary to complete the contract).
| 79 | Attachment 1 - PWS | 2.5.1 Equipment and Preparation | What unloading capabilities (fork trucks/cranes and operators), and corresponding capacities, does each LSS have that will be available to offload ISO shipping containers? | Please contact the listed POC's within theater to provide you an answer |
| 80 | Attachment 1 - PWS | 2.5.1 Equipment and Preparation | Is the cost of GFE helicopter or fixed wing support from the LSS to and from LRR sites for materials and/or personnel movement to be included the FFP or Travel or Over & Above CLIN? | Shipping is CRNF and is not required to be bid as part of the proposal. Costs associated with shipping will be determined on individual orders. |
| 81 | Attachment 1 - PWS | 2.5.1 Equipment and Preparation | Will there be a cost to coordinate with the O&M contractor for GFE helicopter or fixed wing support? | Shipping is CRNF and is not required to be bid as part of the proposal. Costs associated with shipping will be determined on individual orders. |
| 82 | Attachment 1 - PWS | 2.5.1 Equipment and Preparation | Is there a maximum weight limit for the GFE helicopter or fixed wing support? | Only Short Range Radar (SRR) radome packaging weight limit is 2000 lbs, constrained by helicopter sling. Long Range Radar (LRR) sites are limited to barge, airlift, over the road particular to each site. |
| 83 | Attachment 1 - PWS | 3.1.1.2.6 | Should FFP CLINs include the cost for all required installation equipment (manlift, scaffolding etc.) or will those costs be part of the Over & Above CLIN pending site survey results for each site? | The Government confirms that the Firm-Fixed Price (FFP) for the Radome Installation CLIN (0006-6006) must include the cost of all installation equipment (e.g., manlifts, scaffolding) that is reasonably anticipated to be required for installation. |
If the Site Survey Report or OEM coordination identifies special equipment available on site that can be used, this equipment can be utilized to the benefit of the installer.
The Over and Above (O&A) CLINs (0008/5008) are not intended to cover predictable equipment costs. O&A is reserved for unforeseen issues and work that meets the DFARS 252.217-7028 definition (unforeseen work within scope, not covered by existing CLINs, and necessary to complete the contract).
| 84 | Attachment 1 - PWS | 3.1.4 Radome Assembly and Accessory Production and Shipping | When will the Government Program Manager provide pre-notification of an upcoming order? | The Government COR/Program Manager will work with the contractor persistently throughout the contract to pre plan orders |
| 85 | Attachment 1 - PWS | 3.1.4.1 Factory Acceptance Test and Report | Will the Contractor be responsible for coordinating the DCMA/ACO QAR inspection? | Yes. |
| 86 | Attachment 1 - PWS | 3.1.4.3.1 Radome Packaging Requirements | Is there a maximum weight limit? | For packaged (disassembled) radomes, weights are limited by transportation method maximums. For installed (assembled) radomes, maximum weight is provided by the specification document (3.1.2.3) |
| 87 | Attachment 1 - PWS | 3.2.3.1 Damage Inspection | If a non-conformity cannot be resolved, will the installation of the radome be delayed/rescheduled at a later time, and if so, will the Over & Above CLIN be used to bill incurred costs? | The Over and Above CLIN is for resolving non-conformities. If a non-conformity cannot be resolved, we would have negotiate the rescheduling and costs incurred under the CLINs work was performed. |
| 88 | Attachment 1 - PWS | 3.2.6.1 Government Testing and Verification | Will the Contractor be required to be present during the Government testing? | The Pre-Installation test will be preformed immediately prior to replacement radome installation, but after the legacy radome has been removed, in order to establish a radome-uninhibited baseline of radar performance. This order of events necessitates that contractors will remain on site in order to reduce the total number of days the radar system is uncovered/inactive. The post-installation test is possible after contractors have left the site. |
| 89 | Attachment 1 - PWS | 3.3 Over and Above | What is in the Over & Above CLIN and what elements of the effort does this cover? | Please see PWS "Over and Above" |
| 90 | Attachment 1 - PWS | Section 1.6, 1.7 | PWS Section 1.6 and 1.7: There are Government supplied Technical Orders (qty 5) and Guidance Documents (Qty 6) listed. How do prospective bidders acquire these documents? (DTIC) | They have been loaded on SAM.gov where access can be requested. Having an active status in the JCP is required for access. |
| 91 | Attachment 1 - PWS | 3 | Can the Government please define its method of testing and accepting each new installation? | The site acceptance testing activities required of the Contractor are listed in PWS 3.2.5.1. The Contractor must develop a formal plan to include these activities and any others the Contractor deems fit, to submit to the Government for approval. Site Acceptance Testing may vary from site-to-site due to environmental or logistical factors, and earlier installations may include additional test activities as part of the Contractor's plan to validate requirements for the RTVM (PWS 3.1.1.2.4) |
The Government will also perform Radar system testing in accordance with PWS 3.2.6.1.
| 92 | Attachment 2 - Section L | 1.4 | What is the anticipated award date for this Long Range IDIQ? | May 2026 |
| 93 | Attachment 2 - Section L | 1.4 | What are the durations & PoPs for the TOs issued under this IDIQ? | Period of Performance will be dependent on offeror's proposed installation capabilities and timeframes. |
| 94 | Attachment 2 - Section L | 3 | Does the Government consider costs for camp sites/living conditions (e.g., shelters, clothing, food, etc.) at each site during installation, etc. should be priced under the Travel CLIN? | All travel costs, including daily living costs and per diem, are charged through the Travel CLIN (CLIN 0002) on a CRNF basis. |
| 95 | Attachment 2 - Section L | L.1.3.1 | If an offerors proposal contains CUI, will the Government please confirm the offeror can use the DOD SAFE (in lieu of PIEE) as a submission method as offered in PWS Section 2.4.2? If so, please provide submission instructions. | It is confirmed that offerors can use the Solicitation Module within PIEE to submit proposals containing CUI. DAFRS PGI 205.102-70 - The Solicitation Module within the PIEE, provides DoD a secure and auditable mechanism to request and receive proposals from industry. |
| 96 | Attachment 2 - Section L | L.1.4 | Due to the complexities and unknowns at time of FRFP and our inability to engage with the end user during a DRFP stage, would the Govt be willing to conduct 1-on-1s with Industry to answer material questions that will directly and substantively affect the price and technical solutions? | When specific information about a proposed acquisition that would be necessary for the preparation of proposals is disclosed to one or more potential offerors, that information must be made available to the public. The best approach to this would be to receive a list of questions that we can respond to and be shared with the public through SAM.gov. |
| 97 | Attachment 2 - Section L | L.1.4 | Based upon the answer to above, if so, how can we begin scheduling that? We are more than happy to provide our questions in advance of this Industry Day to add as much value to our 1-on-1 as possible. | When specific information about a proposed acquisition that would be necessary for the preparation of proposals is disclosed to one or more potential offerors, that information must be made available to the public. The best approach to this would be to receive a list of questions that we can respond to and be shared with the public through SAM.gov. |
| 98 | Attachment 2 - Section L | L1.4 | Given the technical specifications for this were not received until 21 Aug 25, can the Govt please consider extending the proposal deadline 22 Oct 25 |
| RFP deadline has been extended one week. Proposals will be accepted until 29-Sep-2025 | ||||
| 99 | Attachment 2 - Section L | L1.4 | With two proposals and significant complexity in the submissions, would the Government please consider a two-week extension to the proposal due date? | RFP deadline has been extended one week. Proposals will be accepted until 29-Sep-2025 |
| 100 | Attachment 2 - Section L | L1.4 | The current due date is 22 September 2025. Will the government consider a one month extension to allow suitable time for USG Q&A responses and contractor review? The USG released two solicitations simultaneously for similar radome replacement scope, and the ability for the companies who specialize in these technologies to generate two proposal submittals on the same date is very challenging. Will the USG consider a one month extension? | RFP deadline has been extended one week. Proposals will be accepted until 29-Sep-2025 |
| 101 | Attachment 2 - Section L | L1.4 | Due to the dependence on questions/answers and requested technical documentation missing from the Final RFP package, we respectfully ask for a proposal due date extension of no less than 30 days from date of documentation release? | RFP deadline has been extended one week. Proposals will be accepted until 29-Sep-2025 |
| 102 | Attachment 2 - Section L | L.1.5 | Commercial quotes are generally valid for 30 days, especially for small businesses. The 365 day validity period will not be sustainable for those commercial vendors and will cause an increase in price due to uncertainties in the market - will the Government allow for updated quotes prior to award to ensure CLIN ceilings are set appropriately (especially for the Fixed Price CLINs)? | If an offeror makes the competitive range and discussions are held and concluded, each offeror still within the competitive range shall be given an opportunity to submit a Final Proposal Revision (FPR). |
| 103 | Attachment 2 - Section L | L.2.2.1 | Can the Govt confirm that even thought Data CLIN 0001 is NSP, the PMO/labor needed to create the CDRLs will be estimated within CLINs 0005 & 0006 (etc.)? | Correct. To account for costs when a specific Contract Line Item Number (CLIN) isn't provided, contractors should include these expenses within the existing CLINs for direct or indirect costs. |
| 104 | Attachment 2 - Section L | L.2.2.1 | If the Govt disagrees with above, would Govt consider changing CLIN 0001 from NSP to CPFF? | To account for costs when a specific Contract Line Item Number (CLIN) isn't provided, contractors should include these expenses within the existing CLINs for direct or indirect costs. |
| 105 | Attachment 2 - Section L | L.3.1.5 | Can the Govt please provide this document: Engineering Specification for the AN/FPS-117 Radar Radome” Document No.: 20250725 CAGE: 98747? | All documents referenced were loaded on SAM.gov. Access can be requested via SAM.gov. |
| 106 | Attachment 2 - Section L | L.3.4.1 | For HI and AP Hill Site, what is the designated disposal site? | As defined within PWS Transportation Mode Selection "The Contractor shall select the most efficient and cost-effective transportation mode available, taking into account the size, weight, and fragility of the cargo, as well as the urgency of the shipment. |
| 107 | Attachment 2 - Section L | L1.14.2 versus L1.2.3 | Please clarify if tables and figures count towards the Technical Volume page limit. L1.14.2 states they do not count; however L1.2.3 does not include these as exemptions to page count. Is L1.14.2 meant to state lists of tables and figures do not count? | L1.14.2 will be edited to remove "Tables and figures do not count against the page limitations of their respective volumes." |
| 108 | Attachment 2 - Section L | L1.14.2 versus L1.2.3 | Please clarify if tables and figures count towards the Technical Volume page limit. L1.14.2 states they do not count; however L1.2.3 does not include these as exemptions to page count. | L1.14.2 will be edited to remove "Tables and figures do not count against the page limitations of their respective volumes." |
| 109 | Attachment 2 - Section L | L1.2.2 | Will Administrative markings (e.g., headers/footers) be permitted to be placed within the margins and be no smaller than 10 point, Times New Roman? | "The proposal when printed must fit on 8.5 x 11 size paper, in 12 point, Times New Roman, single line spacing, with one-inch margins. Tables, charts, graphs and figures shall be used when necessary to depict organizations, systems and layout, implementation schedules, plans, etc. and shall be restricted to the 8.5 X 11 size paper and shall be no smaller than 10 point, Times New Roman." |
The solicitation does not forbid markings within the one-inch margins.
110 Attachment 2 - Section L L2.2.1 This section states that "The cost/price of future Task/Delivery Orders will be determined by multiplying the awarded unit prices (from the Pricing Matrix Worksheet) by the actual quantities the Government orders at the time of…