This attachment to a federal contract incentive fee outlines performance metrics and schedule incentives for deliverables. Up to $17 million may be earned for a First Article delivered within 24 months of award, with $100,000 deducted for each issue without approved corrective action and $1 million deducted per month of delay. For Low Rate Initial Production runs after the First Article, $5 million is available if LRIP 1 is delivered within 3 months, LRIP 2 within 5 months, and LRIP 3 within 7 months of the First Article, again with $100,000 deducted for each open issue and $1 million per month of delay. The incentive fee will be based on actual delivery dates against these schedules.
Incentive Fee Attachment
View the file
Other files for this federal contract opportunity
Show all 50
A-10 Thunderbolt Advanced-Wing Continuation Kitting (ATTACK) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLIN 0005
SCHEDULE INCENTIVE ATTACHMENT
In addition to the profit/fee set forth elsewhere in the contract, the Contractor may earn an additional amount of up to $17,000,000 for meeting appropriate performance and schedule metrics as determined through application of the objective criteria outlined below:
First Article (FA) Incentive: An incentive of $12,000,000 may be earned for a First Article delivered within 24 months after contract award. Deductions will be calculated based on calendar months and open issues without approved corrective action as follows:
· $100,000 will be deducted for every issue without approved corrective action at FA delivery
· Request for Variance will be approved or deductions calculated on a case by case basis
· $1,000,000 will be deducted for each month delivery exceeds the 24 month incentivized schedule Low Rate Initial Production (LRIP) Incentive: An incentive of $5,000,000 may be earned for LRIPs delivered after FA as follows:
· LRIP 1 delivery = FA + 3 months
· LRIP 2 delivery = FA + 5 months
· LRIP 3 delivery = FA + 7 months Deductions will be calculated based on calendar months and open issues without approved corrective action as follows:
· $100,000 will be deducted for every issue without approved corrective action at LRIP 3 delivery
· Request for Variance will be approved or deductions calculated on a case by case basis
· $1,000,000 will be deducted for each month delivery exceeds any monthly deadline stated above The incentive fee will be based on delivery date.