SABER V RFI with Responses 9Oct2026.docx

DOCX document 47 KB Posted

Attached to
SABER V Hill AFB
Solicitation number
FA820126R0020
Issued by

About this file

This file is a Request for Information (RFI) with Government responses related to the SABER V Indefinite Delivery/Indefinite Quantity (IDIQ) contract for construction services at Hill Air Force Base and other Air Force locations in Utah, Wyoming, and Nevada. The RFI addresses 135 clarifications submitted by prospective contractors regarding the seed project scope of work and solicitation requirements, with official Government responses provided as of October 9, 2026.

The seed project involves comprehensive renovation of Building 586 at Hill AFB, including restroom and janitorial closet redesign with new flooring (epoxy), wall tile, plumbing, mechanical, electrical, and fire suppression upgrades; office improvements with new carpet, paint, and lighting; installation of new ceiling grids and HVAC diffusers; epoxy flooring in maintenance bays phased in up to four phases (two in North Bay, two in South Bay); fire alarm system upgrades throughout the entire building; and miscellaneous site work including bollard installation and landscaping. Key clarifications establish that the Technical Volume is limited to 50 pages; past performance submissions must use only prime contractor experience; 35% design-level conceptual drawings (not detailed calculations) are required with proposals; all plumbing work is limited to restroom and janitorial closet footprints; flooring types are specified by area (carpet in offices, ceramic tile in hallways, LVT in breakroom, epoxy in restrooms/bays); the building will remain occupied during construction requiring phased work and porta-johns; as-built drawings will be provided in PDF format with DWG format available post-award; and the correct wage determination for Davis County is UT20260083. The Government confirmed that a rapid mobilization plan requirement was removed, the ground cable grounding work is no longer required, and service work will not take place in Nevada despite initial documentation listing it.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Technical Volume Page Limit: Section L, Table 1 (Proposal Organization) states that the Technical Volume page limit is 60 pages, while the published Q&A refers to a 50-page Technical Volume limit. We believe this may be explained by the addition of Subfactor 5 (Rapid Mobilization and Concurrent Performance Plan), which carries its own 10-page allowance and is not yet reflected in Section L's table of contents or in Section M's evaluation factors. Could the Government confirm whether the 60-page limit represents 50 pages for Subfactors 1 through 4 plus a separate 10-page allowance for Subfactor 5, and whether Section L, Section M, and the Q&A will be reconciled to reflect this?

Response: The Rapid Mobilization Plan has been removed as a requirement. The technical volume page limit is 50 pages. Sections L & M have been updated to reflect this.

2. Subfactor 5 in Section M: Section L, Paragraph 5.2.5 describes a detailed Rapid Mobilization and Concurrent Performance Plan as Subfactor 5 of the Technical Volume (10-page limit), and it appears in Section L's Volume Organization outline, but it is missing from Section L's table of contents and from Section M's evaluation factors. Could the Government confirm whether Section M will be updated to reflect Subfactor 5, and whether it will be evaluated as described in Section L?

Response: The Rapid Mobilization Plan has been removed as a requirement. Sections L & M have been updated to reflect this.

3. What requirements are there for the conceptual drawings due with this proposal?

Response: If it’s Identified in the SOW include it in the drawing (PDF format does not need to be to scale). Provide sufficient information for the government to determine the contractor has full understanding of the project scope.

4. Are the 35% shop drawings/construction drawings due with this proposal or after award?

Response: After award prior to construction start.

5. For the 35% Construction drawings, are we looking to show all architectural, plumbing, mechanical, electrical, IDS, Access control, and fire alarms for the entire building. Or just the reconfiguration of the restrooms, fire alarm plan, and the light layout?

Response: All aspects of the projects include: Architectural, Plumbing, Mechanical, Electrical, IDS, ACC, FA, Etc.

6. 8C states that all new unground rough plumbing need to be replaced. How far are to replace? Does that include out to the Main?

Response: Only replace the underground in the footprint of the restrooms/janitors closet. See updated notes in plumbing section of SOW.

7. 8D States all new hot and cold water lines. How far are we to replace this?

Response: All plumbing lines within restrooms/janitors closet footprint.

a. To the pressure assembly in the mechanical room?

Response: No.

b. To the fire line?

Response: No.

b. Scope also states to demo back to main connection.

Response: Demo back to where the main water line feeds restrooms/janitors closet.

8. Does the Base have any as built drawings or original design plan that can be provided? Any CADD drawings?

Response: Yes, as-builds will be provided in PDF format. DWG format will be provided to the winning bidder.

9. Verifying that the hallways get ceramic tile, offices will get new Carpet tile and the breakroom will get LVT.

Response: Hallway gets ceramic tile, Offices get carpet, Breakroom get LVT.

10. Should new t-grid match existing height?

Response: Yes.

11. Should the bollards have white or yellow stripes. There is a discrepancy in supplied drawing and SOW.

Response: White. Discard the note as yellow in the drawing.

12. SOW states to phase the offices to accommodate users? Yes. Will the main building be occupied during construction. Yes. Will the contractor need to demo, install flooring, ceiling grid, and Electrical. On each office separately? Yes, flooring, ceiling and electrical needs completed per room phasing.

13. The bays will also be phased for epoxy flooring. Are 2 phases acceptable. The north bay west side, then the north bay east side and south bay. Or 3 phases 2 in north bay and 1 for south?

Response: Complete the epoxy flooring in up to 4 phases. 2 in North Bay, 2 in South Bay.

14. Sow states to move furniture. Is the contractor also to move the “furniture” in the bays included.

Response: Government will move the furniture and stands in the bay, but contractor will move furniture in the admin areas.

15. Should the contractor saw cut the joints in the bay prior to epoxy floor install?

Response: Yes, demo all material from control joints. In restrooms- control joints/cracks to be flex fill and epoxied over. Shop bays joints/cracks shall be flex filled and epoxied over.

16. Epoxy Flooring/Cove Base: For the epoxy flooring in the work bays, is the epoxy flooring system to extend vertically up the perimeter walls to form a 4-inch integral cove base?

Response: No.

a. If so, please confirm the required cove height and configuration.

Response: Not required

17. Epoxy Flooring Phasing/Sequence: Please clarify the required phasing and sequence for the epoxy flooring work in the work bays. Is there a Government-required sequence for completing the bay areas, or may the Contractor determine the phasing and sequence as necessary to maintain facility operations?

Response: Contractors and Government will discuss the sequencing to maintain facility operations. Complete the epoxy flooring in up to 4 phases. 2 in North Bay, 2 in South Bay.

18. SOW 6. Architectural. Should the epoxy flooring include the control joint epoxied or flex filled?

Response: In restrooms- control joints/cracks to be flex fill and epoxied over. Shop bays joints/cracks shall be flex filled and epoxied over.

19. SOW 6. Architectural. Is there any exterior paint to be done?

Response: Possible, facia, flashing, bollards should matchs, but contractors may need to touch up.

20. SOW 6.F. Regarding painting the offices, are we expected to remove the wallpaper or leave it in place?

Response: Leave wallpaper in place. Do not paint over.

21. SOW 8.D., should we provide a hot water recirculation line run for the restroom?

Response: No.

22. SOW 8.L., should we provide aluminum cladding on the pipe insulation at the water heater in the janitor closet?

Response: No.

23. SOW 8. Plumbing. Should we replace the drinking fountain near the main door?

Response: No.

24. SOW 8.G, please confirm we are providing a floor drain in each restroom and one in the janitorial closet.

Response: Yes, providing a floor drain in each restroom and one in the janitorial closet.

25. Section M - Volume III – Past Performance (Factor 3) Par. 5.5.1 states that “Offeror may not use past performance as a subcontractor to satisfy recent and relevant past performance.” However, Par. 5.5.1.1.2 Relevancy states “For Government contracts, any relevant Government contract where the Offeror was the Prime Contractor or subcontractor will be considered and reviewed to determine past performance history.” a. Please resolve this apparent contradiction.

Response: Past performance submissions may only use contracts performed as a prime contractor. Section M has been updated to reflect this.

26. BASIC SOW 15.4.2 states:

a. “The Contractor shall provide, as part of the proposal, a basic design solution in narrative format or drawings…..”

b. “Typically, Contractor maximum design for SABER is up to 35%”

c. Under bullet point #2, several “Design Calculations” are stipulated. While some basic Design Calculations can be expected at a 35% level, it is generally unreasonable and unrealistic to expect these calculations with a proposal. i. Please clarify the level of design required with the proposal versus post-award.

Response: Not on this project but on other project you may need to provide calculation to explain equipment sizing, panel loads, air flow req’s, etc. For this SOW we are looking for a conceptual drawing identifying everything in the SOW (PDF format does not need to be to scale). Provide sufficient information for the government to determine the contractor has full understanding of the project scope.

27. BASIC SOW 15.4.2 Par 2.d stipulates: “Pavement/Site Work: Area run-off quantities, drainage capacities, and grading slopes.”

a. These items generally require a survey and the involvement of a civil engineer and therefore may exceed the 35% maximum SABER design requirement.

Response: These requirements are not typical for SABER project, but some work may require this. If needed the contractor will be informed and allowed to bid accordingly.

b. Additionally, it is unreasonable to expect these requirements with a proposal, since they require field work. Please clarify these requirements as they fit within the 35% SABER maximum and clarify if these calculations will be required with task order proposals.

Response: Engineering fee’s need to be included in the proposal. Work identified by the engineer will be cause for contract modification. Example: Roof loads- engineer evaluates existing loads. If the engineer determines the roof cannot support additional loads, we will modify contract to perform recommended work by engineer.

28. BASIC SOW 15.4.2 Par 2.d stipulates: “Energy: provide energy savings and Return on Investment (ROI).” a. These items may exceed the 35% maximum SABER design requirement, since they generally require specialized analyses. Additionally, it is unreasonable to expect these requirements with a proposal. Any financial analysis required by the contractor may require the government to provide financial information on existing conditions that may or may not be appropriate for dissemination to the contractor. Please clarify these requirements as they fit within the 35% SABER maximum, clarify what format the government wants to see these submitted in, clarify what information will be provided to the contractor by the government in order to facilitate these requirements, and clarify whether the government will expect these requirements to be fulfilled with each Task Order proposal.

29. During the site walk with the Government, they mentioned that we are to fix a ground cable that is on the N/E corner of the building and in Section 14.D. a. What does the cable service, and how would the Government like the cable to be grounded?

Response: This is no longer a requirement. This work was inspected and deemed unnecessary to remain. This work is scheduled to be completed prior to project start and is to be removed from all proposals.

30. Seed Project SOW Section 10.E.1 States: “Install all new sprinkler heads throughout building.” a. Was this meant to be throughout the construction area only, or the entire Building 586?

Response: Replace FS Heads throughout entire building.

31. Seed Project SOW section 6A States that “All walls to be framed above the ceiling at least 2’ feet with seismic anchoring…” while in 9C it states “Hard lid ceilings above restrooms/ janitor’s closet. Height as high as can be accomplished.” a. Please clarify. Do the walls in the hard-lid ceiling areas need to be framed 2 feet above the ceilings as well?

Response: Yes, frame walls 2’ above ceiling height.

32. Seed Project SOW Section 6I states “Tile in janitors closet 5’ from floor to ceiling on all walls.”. a. Are we to add tile 5’ form the floor, or “from floor to ceiling?”

Response: Tile floor to ceiling in janitor’s closet, match restrooms. See section 6I.

33. Could the Government please clarify the flooring types in each area (i.e. flooring schedule).? The SOW has flooring types overlapping in different areas.

Response: Carpet in Office’s, Tile in hallway, LVT in Breakroom, Epoxy in restroom’s/janitor closet, and work bays.

34. Can the Government provide separate PDFs of all the conceptual drawings within the SOW?

Response: The government will provide as-builds PDF drawings.

35. Seed Project SOW 9D- It states to install exhaust fans for both restrooms and the janitor’s closet. a. It looks like there is 1 Inline Exhaust Fan that exhausts both restrooms and the janitor’s closet, do we need to install three separate exhaust fans or only replace the 1 inline exhaust fan?

Response: Replace the 1 Inline exhaust fan. Size accordingly.

36. Does the Government want the HVAC controls tied back to EMCS?

Response: There are no EMCS controls, but wire in as existing is.

37. Seed Project SOW Sections 4C and 5A: a. Does the Government know the thickness of the slab?

Response: From As-Built files it states that the floor thickness is anywhere from 6 to 8 inches thick.

38. Seed Project SOW Section 6M a. Does the Government have a preferred label they would like installed?

Response: Black letters on white/clear backing.

39. Seed Project SOW Section 6F a. Will painting be limited to the Hallway?

Response: Office, breakroom, restrooms ceiling, janitor closet ceiling, hallway, and front entry foyer. Do not paint wallpaper.

40. Can the Government provide the following photos:

a. Joint Crack Repair Response: Yes, see “Attachment” to SABER Task Order Statement of work

b. Bollard locations with white stripes.

Response: See page 13 in SOW exterior Map, White stripes.

c. Ground cable to be repaired?

Response: No longer a requirement.

41. Seed Project SOW 14A a. Can the Government provide specifications for the new bollards, diameter, height from finished floor, and thickness? How long do the stripes need to be?

Response: -Bollard hole diameter: 18” @ 42” deep -Bollard Diameter: 6” Round Galvanized Steel (SCH 40) -Bollard Pipe Depth: 38” (4” above bottom) -Bollard Pipe Height (Above Ground): 54” -Full #4 Rebar verticals, #3 horizontal and tied at intersections (match bollard bottom elevation) -1” Crowned concrete at finish grade to bollard -Concrete filled with rounded tooled cap -2” reflective stripe (White in color)

42. Seed Project SOW 6J States a. “Tile to be larger 24”x24” “. For clarification, tile in the restrooms is to be 24”x24”?

Response: Wall Tile are to be 24”X 24”. Flooring is epoxy.

43. Seed Project SOW 6S Calls for Stainless-steel partitions for the restrooms, then asks for color samples. a. Is the intention to install stainless-steel partitions, or colored metal partitions?

Response: Stainless-steel partitions.

44. Seed Project SOW 8E asked us to install a 40-gallon electric water heater, space permitting. a. Is there a fallback size if the 40-gallon won’t work?

Response: 30 gallon.

45. Will the building be occupied during the construction? If so, are we to provide porta-johns?

Response: Yes, provide porta-johns as per SOW section 13.

46. Are we allowed to take the demoed concrete to the Base Landfill?

Response: No, see SOW section 5b.

47. Seed Project SOW Section 4 Demo a. In the offices there are motion sensors on the walls that appear to be for lighting. Will these sensors need to be removed?

Response: No

48. Seed Project SOW Section 7 Electrical a. In the restrooms, is the existing conduit and wire OK to reuse and reconfigure for the new layout?

Response: Yes, follow NEC.

49. Seed Project SOW Section 7D - Dimmer switches for hallway/offices, 3-way for each end of the hallway. Entry switch to be moved next to main entrance door. a. Does the Government really want the hallway to have dimmer switches?

Response: Yes

50. Seed Project SOW Section 7C states “All new switches and outlets throughout the building.” a. Is this to include the Bays?

Response: Just the Admin area

51. Seed Project SOW Section 11 Fire Alarm a. Is it the intent of the Government to have all the wall devices mounted on the ceiling?

Response: Yes

52. Seed Project SOW Section 14 IDS a. Will we be required to install new motion sensors that are on the approved list, since we are touching the existing devices that are not on the current device approval list?

Response: No, See SOW Section 14c

53. Domestic water appears to be connected to the fire line. Does the government want the contractor to remove the PIV and replace it with a valve box?

Response: No

54. Does the government want the contractor to run a new domestic water line into the building?

Response: No

55. Does the government want the contractor to install a hot water recirculation line ran for the restroom?

Response: No

56. Does the government want the contractor to install aluminum jacketing on the pipe insulation at the water heater in the janitor closet?

Response: No

57. Does the government want the contractor to replace the drinking fountain near the main door?

Response: No

58. Does the government want the contractor to install a floor drain in each restroom and one in the janitorial closet?

Response: Yes, install a floor drain in each restroom and one in the janitorial closet.

59. SABER 2027 SOW Par. 23.2 states “all outages shall not exceed five (5) days per outage without prior approval by the SABER PM.” Par. 23.3 states “No outage may exceed 8 hours without SABER PM approval.” a. Please clarify which outage duration limit governs.

Response: You are allowed an outage of up to 5 days, but not to exceed 8 hours per day. Example: FS outage can be approved for 5 consecutive days of outages but each day it can only be down for 8 hours each of the 5 days, and back in service at the end of each day.

60. SABER 2027 SOW Par 7.3 states (regarding the BFDS/IFS) “Where level of effort differs between the standards set forth herein and any such jurisdictional requirements and/or standards of practice occur; the more stringent requirement(s) shall apply. However, if there are conflicting requirements the government standard will govern.” a. This appears to be an apparent contradiction. Please clarify whether the BFDS/IFS governs in cases of contradiction in standards, or whether a “more stringent” standard may override the BFDS.

Response: Always follow the more stringent standard.

61. SABER 2027 SOW Par 20 states: “It is the Contractor’s responsibility to verify all dimensions, locations, equipment specifications (both existing and new) and the facilities supporting utilities. Failure to do so will be at the Contractor's risk and shall not relieve the Contractor from accomplishing the work required by the TO. This is not a justification for a contract modification.” a. Does FAR 52.236-2, Differing Site Conditions, still apply to concealed conditions that are not reasonably discoverable at the site visit for the purposes of contract modification?

Response: Yes, key words are reasonably discoverable.

62. SABER 2027 SOW Par 15.4.2 states: “Contractors are not required to bid on projects that exceed 35% Design.” However Par. 16.2 states that SABER Contractors “….shall submit proposals for all funded TOs. Failure to participate responsibly in site visits and proposal submissions may be reflected in CPARS ratings.” a. Please clarify the following: How is the 35% measured?

Response: Drawings included with the proposal must be thorough enough to allow the Government to determine the Contractor has a complete understanding of the project scope. Design incidental to accomplishing the required tasks outlined in each TO will be required. The extent of these designs will depend upon the complexity of each task. Also, designs shall clearly illustrate compliance with local, state, and federal building construction codes.

63. Is declining to bid on a task order exceeding 35% Design exempt from a CPARS impact?

Response: Yes.

64. What is the procedure for declining to bid on a task order that exceeds the 35% design threshold?

Response: During the RFI stage a rationale for a no bid will need to be submitted for review.

65. SABER 2027 SOW Par 10.1 stipulates a preference for photo documentation of existing conditions. However Par 41.6.10 states that cameras/phones are prohibited in certain RAs, SCIFs, UTTR, etc. a. What is the approved process for photo documentation in restricted areas?

Response: The government will attempt to take photos for the contractors as security allows.

66. SABER 2027 SOW Par 1.2 states: “Individual installation specific requirements shall take precedence over the requirements in this section. Specific requirements will be included in the project Statement of Work (SOW). a. Please clarify the following:

i. Please define what is meant by “this section” in this paragraph.

Response: Entire Basic SOW

i. Please provide an order of precedence for governing standards and documents. (Basic SOW, TO SOW, BFDS/IFS, UFC, etc.)

Response: UFC, IFS, Basic SOW/TO SOW, Etc.

67. SOW, page 3, Conceptual drawing submittal. Please provide as-builts for Bldg. 586. Including any dimensioned floor plans, plumbing (risers, underground, etc.), mechanical (HVAC equipment, ductwork & pipe, etc.), electrical (power, lighting), fire alarm/mass notification system, fire suppression system, etc. so we may develop the conceptual drawing submittal.

Response: The government will provide as-builds PDF drawings.

68. SOW, page 3, note 2 Project Description states to provide “new paint in hallway and new flooring throughout area.” Please clarify if painting applies only to the new walls in the project construction area or to new & existing walls in the entire building/facility.

Response: No walls in the bay to be painted. Office, breakroom, restrooms ceiling, janitor closet ceiling, hallway, and front entry foyer to be painted. Do not paint wallpaper.

69. SOW, page 3, note 2 Project Description states to provide “new ceiling and lights throughout.” Please clarify if we are to install new ceiling and lights in the project construction area, or throughout the entire building.

Response: Only replace the ceilings that are currently present. All lights in admin area are to be replaced with new and the lights in the bay area corridor with matching bay lights.

70. SOW 4.C requires removal of the entire concrete floor area in both restrooms and the janitor’s closet for below-slab plumbing. Please confirm existing concrete floor thickness for demolition.

Response: Floor is assumed to be 6-8” thick.

71. SOW 4.G notes to “demo water lines back to main connection”. Please clarify the point of disconnect/reconnection of the water lines. Will it be at the branch line off the main or all the way back to the mechanical room?

Response: All plumbing lines within restrooms/janitors closet footprint. Demo back to where the main water line feeds restrooms/janitors closet.

72. SOW 5.A requires placement of new concrete floor in restrooms & janitor closet.

73. Please confirm new floor thickness.

Response: 6” minimum throughout and gradual overall slope toward floor drains

74. Confirm required reinforcing (i.e. #4 bars 12” on center/each way).

Response: See Section SOW 5. #4 bars 16” on center/each way.

75. Confirm dowel size, spacing & embedment.

Response: #4 rebar 12” on center

76. Can we pump the concrete, or will this have to be wheel barreled? If neither is an option, how would you like us to proceed?

Response: This is contractor discretion, either method is acceptable

77. Please confirm 3500 psi concrete is acceptable Response: Yes, Per UFC 3-301-01/ACI 318 yes, 3,500 psi concrete is acceptable

78. SOW 5.E, clarify sand bedding specification (i.e. what grade?).

Response: Per UFGS 31 23 00, Specified as clean sand capable of passing 100% through a 1/2-inch (13 mm) sieve and no more than 10% to 12% by dry weight passing through a No. 200 sieve to ensure water drains freely and does not wash out the bedding.

79. SOW 6.A calls for 16 ga. studs. Can 18 ga. studs be used for framing in the restrooms?

Response: 18 ga. Is okay for wall studs.

80. SOW 6.C & K, should we plan to match existing ceiling heights?

Response: Yes

81. SOW 6.D references new hard lid ceilings in the restrooms. Will the restroom hard lid ceilings also need to be insulated?

Response: No. If yes, please provide R value.

82. SOW 6.G, please provide “Base Custodial Contract” requirements for restroom accessories.

Response: See SOW 6G for the brand and model for the accessories.

83. SOW 6.H, regarding epoxy floor finish (non-slip), please clarify how much texture needs to be applied. We’re asked to refer to Section 13 for more detail, however the non-slip finish is not clarified in Section 13.

Response: Example would be like the Shark grip product that is an additive mixed into a final topcoat to make epoxy floor slip resistant.

84. SOW 6.I indicates to install tile in “janitors closet 5’ from floor to ceiling on all walls”. Are we installing wall tiles up to 5’ above finished floor or are we installing wall tiles from floor to ceiling? Please clarify.

Response: Tile floor to ceiling in janitor’s closet, match restrooms. See section 6I.

85. SOW 6.N reference flooring finish, please confirm floor finish for offices.

Response: Carpet squares.

86. SOW 6.S, indicates to provide stainless steel partitions. Please clarify if we are providing a natural stainless-steel finish or powder coated finish for the partitions.

Response: Stainless steel partitions.

87. SOW 6.T, indicates to provide Quartz solid surface counter tops with square undermount sinks. Please clarify if we can install the undermount sinks in the field, or if they should be factory mounted.

Response: Contractor discretion.

88. SOW 7 Electrical, does the government want the bug eye exit lights stay or do you want in ceiling photo-luminescence exit signs?

Response: Ceiling non-photo luminescence exit signs.

89. SOW 7.A indicates to “install all new lights throughout the area (excluding work bays)”. Please clarify if we are installing new lights in the project construction area, or throughout the entire building.

Response: All lights in admin area are to be replaced with new and the lights in the bay area corridor with matching bay lights.

90. SOW 7.C indicates to replace “All new switches and outlets throughout building.” Please clarify if we are installing new switches and outlets in the project construction area, or throughout the entire building.

Response: Only in the Admin area/bathroom area. Bays not included.

91. SOW 7.C. Are the comm cover plates to be replaced along with the outlets and switches?

Response: Yes, match outlets and switch covers.

92. SOW 7.E states to match new corridor lights with existing lights in the bay area. The existing lights are high bay lights designed for higher elevations. Can we use the epanl or equivalent for the corridor?

Response: Match style, color, with lower lumens (light output) to account for elevation.

93. SOW 7.I, other than the water heater, are there any other mechanical devices or appliances being installed?

Response: See Sow. Exhaust fan.

94. SOW 8.A requires all fixtures to meet IFS requirements, while 8.H specifically requires square undermount sinks to be white. Please confirm that the specified white square undermount sinks are the Government’s intended fixture selection and are acceptable where IFS requirements may identify a different fixture standard.

Response: White square undermount sinks are approved.

95. SOW 8.E is regarding the new electric water heater. Confirm a commercial heavy duty 40-gallon electric water heater meets this requirement.

Response: Yes

96. Where will the water heater be located?

Response: Janitor Closet

97. Confirm only the steel stand is painted, not the drain pan.

Response: Concur, Steel Stand only.

98. SOW 9.A-C requires new ducting, diffusers/grilles, connected to existing ductwork. Existing HVAC equipment (excluding restroom exhaust fans) will remain.

99. Will HVAC design & calculations be required?

Response: Only when exhaust fan does not have the same air flow as existing.

100. We will be required to balance the existing system?

Response: No

101. We will be required to commission the existing system?

Response: Yes

102. SOW 9.B indicates to provide “new diffusers/grilles throughout the area. (excluding the work bays).” Please clarify if we are installing new diffusers/grilles in the project construction area, or throughout the entire building.

Response: Admin area and bathroom only.

103. SOW 9.D, indicates we are to “install new exhaust fans, existing ducts to remain…….Utilize existing controls.”

104. What control points exist for the exhaust fan(s).

Response: This was available for inspection during site visit.

105. Are the existing controls for the exhaust fans operational?

Response: This was available for inspection during site visit.

106. What size duct are we connecting to?

Response: This was available for inspection during site visit.

107. SOW 10. Fire Suppression. The majority of the fire suppression piping is galvanized; does the government want the galvanized fire suppression piping to be replaced throughout the building on this project?

Response: No

108. If the government doesn't want the piping replaced, do they want the system flushed and camera 50% of the branch lines.

Response: No

109. SOW 10.C requires the Contractor to relocate or add sprinkler heads as needed for the existing and new rooms, while 10.E.1 states, “Install all new sprinkler heads throughout building.” Please clarify if we are replacing sprinkler heads in the project construction area, or throughout the entire building.

Response: Entire building and work bays.

110. SOW 10.E, the current semi-recessed pendent fire sprinklers are chrome with white escutcheons; what color would the government like these to be replaced with?

Response: White

111. SOW 11.A. Please clarify whether the requirement to replace all existing smoke detectors and provide the associated Fire Alarm/Mass Notification upgrades applies only to the project construction area or to the entire building/facility.

Response: Entire building.

112. SOW 11.K. Does the government want the fire alarm strobes moved off the wall in the bay areas.

Response: Yes

113. SOW 12.A, confirm all finishes with color TBD will be selected from standard manufacturer color selections.

Response: Yes

114. SOW 13. Epoxy Floors. Can the maintenance bay space be completed in one phase, or will it require multiple phases to complete?

Response: Complete the epoxy flooring in up to 4 phases. 2 in North Bay, 2 in South Bay.

115. Will the Gov relocate as required any existing equipment in maintenance bay to allow installation of the epoxy flooring?

Response: Yes

116. Will epoxy flooring be installed during normal work hours?

Response: Yes

117. SOW 14, confirm new bollards will be 6” diameter, embedded in concrete 36” below finished grade with a finish height of 36” above grade. If not, please provide a bollard detail specifying the requirements.

Response: Refer to response of RFI #41

118. SOW 16.A, notes to provide engraved laminate sign(s) and commissioning documents for “each outdoor unit”. Please clarify if this regards existing equipment, or if new equipment, please identify the new equipment.

Response: Does not apply

119. Confirm conditions not identified or readily available during the site visit inspection, such as below grade or concealed in walls or above ceiling, if sufficiently different than noted, may be considered a differing site condition.

Response: Yes

120. SOW 6.S, if Women's restroom is expected to be one stall, does the government still want a partition or would the government prefer a vacancy lock with visual indicators?

Response: Yes

121. SOW 10. Fire Suppression. The fire suppression and domestic culinary water come off of the same underground connection; there is an existing PIV that is wired into the fire alarm system that controls that underground.

122. Does the government want existing PIV removed as a part of this project?

Response: No

123. If yes, would the government like the underground valve left so there is an isolation to both systems?

Response: N/A

124. SOW 10. Fire Suppression. Would the government like an additional butterfly control valve added before the existing fire suppression backflow as a part of this project?

Response: Yes

125. Seed project wage determination. FOPR Amendment #1, Section II.G lists "UT20250083" for Davis County, while the FOPR attachment list and Section J (Attachment 10) show UT20260083. Please confirm UT20260083 governs the seed project.

Response: The correct wage determination number is UT20260083.

126. Carter Creek location. Section C and Block 10 list the Carter Creek Recreational Property at Evanston, WY (Uinta County, covered by WY20260041, Attachment 09). The FOPR table lists "Carter Creek, Utah" under Duchesne County (UT20260079, Attachment 07). Which location and which wage determination apply to task orders at Carter Creek?

Response: Carter Creek is in Duchesne County.

127. Nevada. Section L and SOW Section 3 identify Utah, Nevada and Wyoming as the areas serviced, and Little Mountain Test Annex is listed as "UT, NV." No Nevada wage determination is in Section J. Which wage determination applies to a task order with a primary site in Nevada, or will one be added?

Response: Service work will not take place in Nevada. The documents have been updated to reflect this. Should work take place in Nevada the appropriate wage determination will be provided.

128. Site-to-WD mapping. The FOPR assigns wage determinations only for Davis County (Hill AFB). Please confirm the intended mapping for the other sites (UTTR to Box Elder, Little Mountain to Weber, Boulder Seismic to Sublette) and explain the purpose of the Salt Lake County determination (UT20260085, Attachment 11), which is not tied to any listed site. Also, if a UTTR task order falls outside Box Elder County, which determination applies?

Response: At the task order level the applicable wage determination will be provided.

129. Building-only determinations. All six determinations are "Building" type, but the SOW includes site work, utilities, excavation, paving and fencing. Will the Government attach other determination types (heavy, highway) at the task order level, and which governs the work in the meantime?

Response: At the task order level the applicable wage determination will be provided.

130. Missing classifications. The Davis County determination has no asbestos abatement or carpet/resilient flooring classification, and the Duchesne group determination has no painter, roofer, drywall or truck driver classification. The seed SOW includes abatement through a Utah-licensed subcontractor, flooring, drywall and paint. Please confirm that offerers should price these using conformed classifications under 29 CFR 5.5(a)(1)(iii) after award, and how to price them in the proposal.

Response: Questions about the appropriate labor classifications need to be discussed with the Department of Labor.

131. TEP and Section M wording. Section L 4.1.7 and Section M 3.0.1.6 evaluate TEP rates against the applicable wage determinations, but the six TEP categories (Contract Manager, Project Manager/Superintendent, QC Officer, SSHO, Environmental Officer, Draftsman) are management roles, not determination classifications. Section M's heading and the TEP's Hill AFB tab also reference a Service Contract Labor Standards wage determination, while the solicitation contains only Davis-Bacon clauses (no FAR 52.222-41 or 52.222-43). Please confirm that no SCA determination applies and how TEP rates will be tested against the determinations.

132. Response: The Service Contract Act does not currently apply to this requirement. The language has been updated to reflect this.

133. Determination currency over 9.5 years. FAR 52.222-30 is included in Section I, but the method is not stated in the package. Please confirm which method applies and that a task order uses the determination in effect on its award date. Please also confirm that if a determination is revised before the 5 Nov proposal due date, the Government will amend the solicitation.

Response: The most current wage determination at time of award will be used. Should there be an update to any wage determination before the proposal due date, the offeror will need to adjust their proposal accordingly.

134. Pricing Assumptions. Section L limits Pricing Assumptions to four pages. Please confirm that offerors may state wage determination and classification pricing assumptions there without the Government treating them as exceptions to the solicitation.

Response: The offeror may state wage determination and classification pricing assumptions without the Government treating them as exceptions to the solicitation.

135. Project number. The Site Visit attendance sheet (Attachment 21) shows Project 1145859, while the FOPR shows Capital Project No. 1145899. Please confirm which is correct.

Response: The correct Capital Project No. is 1145899.