Government Responses SABER Question Comment Matrix.xlsx
XLSX spreadsheet 70 KB Posted
- Attached to
- Simplified Acquisition of Base Engineering Requirements (SABER) Federal contract opportunity
- Solicitation number
- FA820121R0007
About this file
This is a request for proposal for construction services under the Simplified Acquisition of Base Engineering Requirements (SABER) contract at Hill Air Force Base in Utah. The purpose is to establish an indefinite-delivery, indefinite-quantity contract covering maintenance, repair, and minor construction work managed by the 75th Civil Engineering Group. Task orders will define specific project requirements. The contract is set aside for 8(a) small businesses. Proposals are due by March 9, 2021. A mandatory site visit will be held on February 17, 2021 with attendance limited to 10 individuals per company. Questions are due by February 23, 2021 with responses by March 2, 2021. The contract includes a seed project, and offerors must complete a pricing matrix and past performance tool provided as attachments.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Basic SOW Solicitation #: FA8201-21-R-0007 - SABER - Question/Comment Resolution Matrix ***FOR GOVERNMENT USE*** Government Response
| Question # | Basic SOW Reference | Discussion | Question/Comment | Sensitivity | ||
| 1 | 8.1 | Quality Control Plan | 8.1 states the QC plan will be submitted at the time of proposal and used throughout the contract. Is this QC plan site specific to Bldg. 100 or will it be for all trades of work that could be encountered during the duration of the contract? If its for the entire SABER program would the government consider removing the page counts for the QC plan? | The QC plan is for the basic SABER contract and can be an abbreviated plan addressing only the 6 items outlined in Basic SOW section 8.2. Additional plans will be specific to the task order project if specialty or other trades are used and a QC plan for that trade has not been submitted. Volume II page limit will be increased to 100 pages, excluding Seed Project Material Submittals. | ||
| 2 | 15.4.2 | Design Solution- Drawings with proposal. | ||||
| "The contractor shall provide, as part of the proposal, a basic design solution in narrative format or drawings." | Please clarify if the Contractor is required to provide 35% conceptual drawings with each task order proposal. | Unless otherwise stated in a task order level SOW, all projects will require a design solution in narrative format and/or drawings. Drawings included with the proposal must be thorough enough to allow the Government to determine the Contractor has a complete understanding of the project scope. Generally a 35% conceptual drawing is sufficient, but some projects may require additional detail to ensure the contractor has a complete understanding of the project scope. Drawings are preferred as they may also be used as an initial review of the construction/shop drawing(s) that are required for all projects. Additional FOPR submission information can be found in section 15.4.4 of the Basic SOW | ||||
| 3 | 5. Management Plan | The requirements state "The plan shall have a cover sheet that includes the solicitation number, subsequent contract number, Contractor name, address and business phone number. The contents of the plan shall be fully tabulated and a table of contents will be used." | Please confirm that the requirements in this statement are applicable to the post-award submission of the Management Plan and that a separate cover sheet, full tabulation and table of contents are not required separately and distinctly for the Management Plan submission in Volume II, Subfactor 3- Management Plan as it will be part of the complete technical volume which already has a cover sheet, tabulation and table of contents? | |||
| 4 | ||||||
| 5 | ||||||
| 6 | ||||||
| 7 | ||||||
| 8 | ||||||
| 9 | ||||||
| 10 | ||||||
| 11 | ||||||
| 12 | ||||||
| 13 | ||||||
| 14 | ||||||
| 15 | ||||||
| 16 | ||||||
| 17 | ||||||
| 18 | ||||||
| 19 | ||||||
| 20 |
Seed Project SOW Solicitation #: FA8201-21-R-0007 - SABER - Question/Comment Resolution Matrix ***FOR GOVERNMENT USE*** Government Response
| Question # | Seed Project SOW Reference | Discussion | Question/Comment | Sensitivity | |
| 1 | 4.5 Plumbing - Steam Piping | Steam Vaults & Piping | Will the new steam vault be placed underneath the existing sidewalk that runs parallel to the south side (front face) of building 100 or will the steam vault be place next to the existing side walk? | The government prefers the new vault set in the footprint of the existing sidewalk. However, vault may need to be placed next to to the sidewalk due to existing utilities. | |
| 2 | 4.5 Plumbing - Steam Piping | Steam Vaults & Piping | Will the new steam vault installed in the landscaped area in front of building 100 be set to grade or recessed so that the landscaping will cover the vault? | New steam vault shall be set to grade. | |
| 3 | 4.5 Plumbing - Steam Piping | Steam Vaults & Piping | What months during the year will the steam piping system be allowed to be taken off line for the removal and replacement of vault and piping? | Late May - Early September, depending on the processes at building 100. | |
| 4 | 4.5 Plumbing - Steam Piping | Steam Vaults & Piping | Is the existing underground steam piping 3” and 6” or is it 2”and 4” or is it some other combination of sizes? | 2" and 4". | |
| 5 | Plans | Is a soils report/Geotech report available? | No. | ||
| 6 | Plans | Is there an updated asbestos and lead report for the areas in building 100 that we are to be working in? | See most current Asbestos/LBP report provided by the government. | ||
| 7 | Plans | Is a site plan that shows the existing underground utilities in the area south of building 100 where we shall be excavating available? | See utilities maps provided by the goverment. All utility locations are aprroximate. On site utilities will be located and marked after award. | ||
| 8 | Plans | Is a current building 100 floor plan that shows Bay N (Room 147) and the main comm room (Room 127A) that we are to extend the copper cable out of available? | No. | ||
| 9 | Plans | Is there an existing fire sprinkler plan available for Bay N (Room 147)? | No. | ||
| 10 | Plans | Is there a sheet legend or key for the landscape plan (figure # 8) provided in the seed project SOW? | No. | ||
| 11 | 3.8 Communications Wiring | Communications | Is a Bicsi Tech certification for the communication cabling installer required? | Not required just reccommended per our guidance | |
| 12 | 3.8 Communications Wiring | Communications | Does the communication room cut over (power and communication cables) need to be completed in off hours? | Cutover will likely be on a weekend coordinated with the Facility Manager | |
| 13 | 3.8 Communications Wiring | Communications | What is the acceptable downtime for the communication cables and equipment within the Bay N, Room 147 comm rack? | Cutover will likely be on a weekend coordinated with the Facility Manager | |
| 14 | 3.8 Communications Wiring | Communications | How many existing CAT5/CAT6 cables are terminated in the Bay N (Room 147) comm rack? | Approximately 300 | |
| 15 | Personnel | The seed project SOW call for a full-time superintendent. Is a dedicated full time quality control and safety person required for the seed project or can one qualified person act as the superintendent, quality control and safety person? (i.e., One qualified full-time person vs three dedicated full-time people)? | The Superintendent is the only fulltime person required. The Quality Control and Safety person(s) can perform spot inspections to meet the requirements of the Basic SOW. The Superintendent may perform the duties and responsibilities of the QC and Safety person(s) IF they meet the requirements and hold the qualification's outlined in the Basic SOW. | ||
| 16 | 4.3 Exterior Paint | Painting | Currently the concrete window sills on the south side of the building are not painted. The west side concrete window sills are painted and we are to repaint them as part of the seed project scope of work. Are we to paint the south side concrete window sills? | Yes, repaint the west concrete window sills and paint the south side concrete window sills. | |
| 17 | Painting | Are we to repaint the (3) oil filled primary electrical transformers and steam vault located on the south west corner of the building (near the overhead chillers)? | Do not paint transformers. Paint the steam vault. | ||
| 18 | 3.3 Architectural | Painting | The seed SOW calls for the new communications room door frame to be “power coated”. Can the frame be field painted in lieu of the power coating? | No. | |
| 19 | 4.11 Canopies & 4.13 Pavillion | Painting | The seed SOW calls for the new canopies and pavilion be “power coated”. Can the new canopies and pavilion be field painted in lieu of the power coating? | No. | |
| 20 | 4.11 Canopy | Canopy | Is there any information available on the manufacture or installer of the canopy used a basis of design for the seed project new canopies (south side building 523)? | No. | |
| 21 | 4.11 Canopy | Canopy | The basis of design for the new canopies at building 100 is building 523’s end gabled canopy. If a similar end gabled canopy to the existing one located on the south side of building 523 is installed at building 100 canopy locations # 3 & 4 (west side) the snow will shed off to the right and left and on pedestrians. Are we to assume that the building 100 canopy locations # 3 & 4 shall be a lean-to style canopies that with similar look to the building 523 canopy? | All canopies and pavilion shall be engineer designed and stamped. Or, the contractor shall provide their design/recommendations to a licensed professional Engineer for approval. The contractor shall provide engineers recommendations, if any, and all recommendations shall be incorporated into this Statement of Work. Glass requirements shall meet applicable code for this type of application, to be determined by the engineer. No higher requirements such as blast resistant, explosion proof, etc. are needed. These drawings must be submitted and approved by the government. Submittals can be after award but prior to NTP. | |
| 22 | Design | Will a Registered Communications Distributions Designer (RCDD) be required for the seed project communication room portion of work? | No | ||
| 23 | Design | Will an electrical engineer be required for the seed project communication room portion of work? | |||
| 24 | Design | Will a mechanical engineer be required for the seed project communication room portion of work? | No. | ||
| 25 | Design | Will a structural engineer be required for the seed project new awnings and pavilion portion of work? | Yes. | ||
| 26 | Design | Will a civil engineer be required for the seed project new steam vault and parking lot portions of work? | Yes. | ||
| 27 | 3.8 Communications Wiring item d) | Electrical | The communication room design within the seed SOW reads “The contractor shall provide a dedicated electrical branch circuit panel board for each TR with the following minimum requirements: 120/208 volt, 3-phase or 120/240 volt,1-phase, 24-(or 20 for 1-phase) space panel with a minimum 100 ampere (A) bus rated capacity.” The electrical SOW for the seed project reads: “The contractor shall provide and install all electrical required for the proper operation of new communications room and HVAC equipment installed under this project. Contractor shall field verify quantities needed to support contract task order.” Are we to provide a new 100-amp panel for the TR, or just provide what is needed for the new room HVAC unit, rack power, lights and convenience receptacles? | ||
| 28 | Electrical | Who will be responsible for lowering the existing electrical vault that currently sits where the new parking lot is to be installed? | The Contractor. | ||
| 29 | Electrical | What is voltage of the conductors in the electrical manhole mentioned above? | 12,470 Volts. | ||
| 30 | 3.1 Asbestos | Asbestos and Lead | Will the government provide an asbestos and lead survey inspection report? | See most current Asbestos/LBP report provided by the government. | |
| 31 | 3.3 Architectural | Existing Raised Floors | Does the existing raised floors in the communications rack area currently meet the anti-static requirements? | No. Install new 12" x 12" ESD anti-static carpet tiles. | |
| 32 | 3.8 Communications Wiring | Wireless Antennas | In the communications area there are 2 wireless antennas mounted to the ceiling above the existing rack, what shall be done with these? | Antennas weren't connected to anything so they have been removed. | |
| 33 | 3.8 Communications Wiring | Termination to T568A | The majority of Hill AFB is terminated to T568B, the SOW states to terminate cat6 cables to the T568A configuration unless requested by user and approved by AHJ. | No longer require CATV termination under new plan | |
| 34 | 4 Exterior Requirements | Lead | Can the government verify if there is lead paint present on any items that needs to be repainted, demoed, or replaced? | See most current Asbestos/LBP report provided by the government. | |
| 35 | 4.3 Exterior Paint | Painting | On the West Side of the bldg does that chain link fence need to be painted? | No. | |
| 36 | 3.1 Asbestos Containing Material Lead Based Paint | Asbestos/LBP | What is Asbestos & LBP where Electrical Room is going? Can the government provide the survey's? | See most current Asbestos/LBP report provided by the government. | |
| 37 | 3.5 PLUMBING – COMMUNICATIONS ROOM | Condensate Piping | What material is to be used for the condensate piping? | PVC. | |
| 38 | Figure # 8 - Landscape Plan | Landscape Symbols | Could you confirm the symbols on the Landscape plan? | See updated figure 8. | |
| 39 | 4.9 CAST-IN-PLACE VAULT | Steam Lines in Vaults | What is the size of the steam lines to be placed in the vaults? | Size accordingly. Existing sizes are 2" and 4". | |
| 40 | 4.9 CAST-IN-PLACE VAULT | Existing Vaults | Does the existing vault under existing landscape the need to be demolished or can it be left in place? | All existing vault being replaced with new shall be demolished. | |
| 41 | 4.13 PAVILION | Sidewalk/Concrete | Does the entire sidewalk and curb and gutter where the vaults go need to be demo and replaced? | Yes. | |
| 42 | 4.9 CAST-IN-PLACE VAULT | Vaults | Does the section of vault in the new parking area need the steel plate top? | No. | |
| 43 | 4.5 PLUMBING - STEAM PIPING | Steam Lines | How long can the existing steam lines be down before the new ones take the place of the existing? | Dependent on building 100 steam process, humidity, etc. | |
| 44 | 4.13 Pavilion | Geotech | Is there a Geotech report for the footings or a report close to the work area that could be used for designs of the new footings? | No. | |
| 45 | 3.6 Mechancial Communications Room | Item D Roofing | What kind of roof material in on bldg. 100? | Field verify. | |
| 46 | 3.6 Mechancial Communications Room | Item D Roofing | Is the roof still currently under warranty? If so, who is the warranty through? | Bldg. 100 bay N roof was done back in 2010. The warranties are generally 20 year. Redd Roofing was the contractor and would hold any warranties. | |
| 47 | 4.4 LANDSCAPING | Irrigation/Landscaping | Where is the Irrigation clock’s location to the landscape area? Is there power there to plug it in? | Existing controller is inside the mechanical/utility room located inside of Bay “P” (south side of building), just to the left of the main entrance. Yes. | |
| 48 | 4.3 EXTERIOR PAINT | Painting | While painting of exterior, there is a roll up door that has a sliding gate, would the government like it painted as well? | No. | |
| 49 | 3.3 Architectural | Existing Railing & Test Equipment | Where the new comm room is going there is an octagon shaped railing and stand, will the government be moving these items, or do we need to shrink/move the room to accommodate it? | Yes, the government will relocate these items. | |
| 50 | 3.3 Architectural | Filing Cabinets | In new comm area there are file cabinets and other item's will the government be moving those item's or does the government want us to move them? | Yes, the government will relocate these items. | |
| 51 | 3.3 Architectural | Comm Room | On hard lid in comm room would the government want drywall or plywood on top of hard lid, and would you want insulation in hard lid stud cavities? | 5/8'' Drywall hard lid with 5/8'' fire rate plywood on top of the hard lid. No insulation in the ceiling cavities. | |
| 52 | 4.13 PAVILION | Pavillions | On pavilion would the government like the columns bricked all the way up to plates for roof like the canopy at building 265 Northside. | Yes. | |
| 53 | 4.13 PAVILION | Pavillions | What is the height of the eave on the pavilion? | Full design on pavilion. Provide after award, prior to install, for government approval. | |
| 54 | 4.11 CANOPIES | Canopies | On canopies would the government be opposed to smoked Lexan instead of glass, would save money also would be less hazard if we're to break? | No, install smoked Lexan instead of glass. | |
| 55 | 4.11 CANOPIES | Canopies | On canopy #2 does the government want us to try and build one large canopy or copy bldg. 5 for stair area and try to incorporate a lean to type cover for handicap ramp? | All canopies and pavilion shall be engineer designed and stamped. Or, the contractor shall provide their design/recommendations to a licensed professional Engineer for approval. The contractor shall provide engineers recommendations, if any, and all recommendations shall be incorporated into this Statement of Work. Glass requirements shall meet applicable code for this type of application, to be determined by the engineer. No higher requirements such as blast resistant, explosion proof, etc. are needed. These drawings must be submitted and approved by the government. Submittals can be after award but prior to NTP. | |
| 56 | 4.3 EXTERIOR PAINT - B.) South End | Railings | On some of the railings on stairs anchoring and concrete is falling apart would the government like any area's compromised fixed? | Yes. | |
| 57 | 4.11 CANOPIES | Handicap Ramp | On face of stairs and foundation curbing for handicap ramp the government is wanting painted, there are multiple area's where concrete is cracked and chipped would the government like it patched and repaired | Yes. | |
| 58 | 4.11 CANOPIES | Canopy Heat Tape | On canopies heat tape, is there existing heat tape running in all gutters? If existing power exists does the government want power tied into the existing feed or on its own panel? Where is the closest panels for runs? | Field verify. Existing feed. Field verify. | |
| 59 | 4.11 CANOPIES | Canopy Bollards | The bollards for the new canopies, does the government want 1 per pillar, (4) total? | Yes. 1 bollard per column. | |
| 60 | 4.8 PRE-CAST VAULT | Vaults | On new vault line's running through the sidewalk does the government just want the whole south sidewalk replaced from ally tunnel to the start of west parking lot so all look's new, or end where we turn back towards building? | Yes, replace sidewalk from tunnel to west parking lot. | |
| 61 | 2.1 Submittals | Design Drawings | Are full design drawings expected to be produced for the entire project if awared the seed project or will designs only be required for the Pavlilion and Canopy areas? | Yes, Engineered Stamped design on pavilion, canopy, steam vault and parking lot. Provide after award, prior to NTP, for government approval. | |
| 62 | 3.8 Communications Room | Comm Racks | Is the rack moving from its current location? | Under direction of contracting/CE we have realized this issue. The new plan will be keep the rack in place, you will not pull back the cable and pull it through a conduit, install the fiber (see instrutions when mentioning service loop on fiber), and continue with plan to remove backboard, 66 blocks, an install 25 pair to 24 port patch panel. Test and label new 24 strand fiber and provide results to SCXP PM (Michael Tagliaferro). | |
| 63 | 3.8 Communications Room | Comm Ladder Rack | Is ladder rack required to be installed to support the rack seismically? | No. Comm racks that are being ordered should be the Seismic-certified. | |
| 64 | 3.8 Communications Room | Fiber | Currently there is no service loop on the fiber, and it is pulled tight and not touching the wall. To install this correctly we would need to replace the fiber. With that said what type of fiber and how many feet/where is it going? | We have determined that we will replce the fiber due to position and lack of slack. The new fiber will be a 24 SM strand indoor rated fiber with pre-spliced LC connectors (No hotmelts). The fiber is running to Bay P according to the tag and is approx. a 400 ft run (Shine light to verify) | |
| 65 | Communications Room Existing Cable | Cabling | The intention is to remove the Cat5e cables off the patch panels, pull them up through the ceiling and then back down through a 4” conduit to re-terminate on the patch panels. Most of the cables are too short to do this because there is no service loop in the ceiling and are pulled tight. Re-cabling is the only option if you move the rack. What is your plan with this? Is there any way to get a data map of all the locations that will need to be re-pulled? | Under direction of contracting/CE we have realized this issue. The new plan will be keep the rack in place, you will not pull back the cable and pull it through a conduit, install the fiber (see instrutions when mentioning service loop on fiber), and continue with plan to remove backboard, 66 blocks, an install 25 pair to 24 port patch panel. Test and label new 24 strand fiber and provide results to SCXP PM (Michael Tagliaferro). | |
| 66 | Communications Room Existing Cable | Cabling | If re-cabling happens, how is this going to take place? Is it the intent to pull all the new cables and install a new rack then do a cut over after it is all completed? | Under direction of contracting/CE we have realized this issue. The new plan will be keep the rack in place, you will not pull back the cable and pull it through a conduit, install the fiber (see instrutions when mentioning service loop on fiber), and continue with plan to remove backboard, 66 blocks, an install 25 pair to 24 port patch panel. Test and label new 24 strand fiber and provide results to SCXP PM (Michael Tagliaferro). | |
| 67 | 4.3 EXTERIOR PAINT - B.) South End | LBP/Asbestos | Can the government provide the LBP and Asbestos survey for the comm room and exterior painting? | See most current Asbestos/LBP report provided by the government. | |
| 68 | 4.3 EXTERIOR PAINT - B.) South End | LBP/Asbestos | If the exteiror pait is lead will it need to be abated before paitning due to the loose flaking paint? Or will the contractor just encapuslate the eixtsing pait by painting over it? | Abate. | |
| 69 | 1 General Requirements | Full Time Superintendent | Can a full time super be a subcontractor or will the super be reuqired to be an employee of the GC? | Can be a sub, BUT they must meet the superentindent qualification requirements stated in the basic SOW. Especially the ability to speak on behalf of the prime. See basic SOW 4.2. | |
| 70 | 3.1- Asbestos Containing Material/Led Based Paint | 3.1 Asbestos Containing Material/Lead based paint | Will there be a Asbestos and LBP survey provided | See most current Asbestos/LBP report provided by the government. | |
| 71 | 4.4- Landscaping | m) The contractor shall tie-in all existing irrigation control wires feeding the areas below into the new irrigation controller and ensure those systems are operational from the new timer: | Please provide a drawing and wire schematics indicating the wiring configuration and location of the irrigation controllers in the building...as well as pictures if possible. | Government does not have drawings, schematics or pictures to provide. | |
| 72 | 4.3 Exterior paint | a) The contractor shall prep (to include sanding, grinding, scraping, etc.) and paint the south and west exterior of building as described below. West side – paint from southwest corner over to bay N. Do not paint doors/frames. | Is it required to patch the concrete foundation walls prior to painting? AND if so, to what extent will patching and repair be repaired? | Yes. All patches shall be flat/flush with surrounding concrete and securely bonded to the existing concrete. | |
| 73 | 4.8 pre-cast Vault | d) The contractor shall provide and install removable concrete lids for all other areas including newly landscaped area. | The removable lid detail on figure #10 indicates that the lids have pre-cast lifting points. Will these lifting points need to be filled with grout to eliminate trip hazards? | Yes. | |
| 74 | 4.11 Canopies | b) The contractor shall construct canopies with standing seam metal roof canopy over doors (entry areas). Canopies shall meet BFDS/ACP and be able to withstand wind and snow loads of this area. Contractor shall match the style and appearance of the canopy shown in figure #7. Canopy 2 shall cover entire handicap ramp, match existing size for canopies 3 & 4 and all new canopies shall match in style. All canopies shall completely cover stairs and extend 3’ beyond bottom step. | The detail in Figure #7 indicates a short glass wall on the rake and sides of the canopy near the tops of the canopies. Is glass required on all four canopies to include the handicap ramp on canopy #2? Please clarify the government's intent. | No, install smoked Lexan instead of glass. | |
| 75 | 3.3 Architectural - Communications Room | h) The contractor shall prep floor for ESD anti-static 12” x 12” vinyl floor tile. | Qestiuons: Is the existing carpet installed using release-type glue? If not, will the raised floor panels need to be replaced with new? | No. No, scrape glue and install new 12" x 12" ESD anti-static carpet to existing flooring. | |
| 76 | 3.3 Architectural - Communications Room | i) The contractor shall provide and install ESD anti-static 12” x 12” floor tiles per manufacturers recommendations and instructions. | If 12 x 12 ESD tiles are installed on the raised floor panels, the glue that bonds the tiles must bridge the seams of the raised floor panels. This will keep the raise floor panels from being removed as individual panels. Would this be acceptable? | Yes. Install new 12" x 12" ESD anti-static carpet. | |
| 77 | 3.4 Electrical - Communication Room | 3.4 d) The contractor shall provide and install new duplex convenience outlets, 1 in room (east wall) and 1 exterior room (south wall). 3.8 q)Provide 125V, 20A duplex convenience receptacles at 6 feet (1800mm) intervals on center around perimeter walls. | Section 3.4 d) specifically requires 1 outlet on the inside and 1 outlet on the outside of the new communication room. Section 3.8 q) calls out for outlets at 6 foot intervals. Which of these are correct for the new communication room? Please clarify. | Follow section 3.8 q and install 1 new duplex convenience outlet on exterior room south wall. | |
| 78 | 1- General Requirements | The contractor shall provide a complete set of Construction drawings prior to beginning any work and provide As-Built drawings upon completion of the project IAW SABER Basic SOW, Sections 22.2 and 27. | Questions: What types of drawings and/or what specific items will the Government require prior to beginning work? And, to what level of detail will the government require in as/built drawings. | Unless otherwise stated in a task order level SOW, all projects will require a design solution in narrative format and/or drawings. Drawings included with the proposal must be thorough enough to allow the Government to determine the Contractor has a complete understanding of the project scope. Generally a 35% conceptual drawing is sufficient, but some projects may require additional detail to ensure the contractor has a complete understanding of the project scope. Drawings are preferred as they may also be used as an initial review of the construction/shop drawing(s) that are required for all projects. Additional FOPR submission information can be found in section 15.4.4 of the Basic SOW. As-built drawings should show the dimensions, geometry, and location of all components of the project and replicate how the Contractor built the project and identify what changes were made throughout the course of constructing the project. | |
| 79 | 3.3 Architectural | The contractor shall construct a 10’ x 10’ communications room with hard lid ceiling. | In the location where the new communications room is to be constructed, there is a hand rail around a piece of equipment. Question: Will the government be moving the existng handrail? And, will the government provide a detail on how the handrail will be reconfigured in order to accomodate the new communications room? | Yes, the government will relocate these items. Handrail and equipment will be relocated and will not interfere with new communications room. | |
| 80 | 3.5 Pluming - Communications Room | The contractor shall pipe condensate drain line to the existing Data Aire Units’ condensate drain line – all piping shall be concealed, provide sufficient slope for proper drainage of condensate. Add condensate pump as needed. | During the site walk, the government mentioned that there was an existing drain below the raised floor that could be used to tie into. Please confirm and/or clarify. | Yes, tie condensate into existing drain below floor. | |
| 81 | 3.6,d- Mechanical | The contractor shall repair any/all roof penetrations associated with the install of the HVAC system. All repairs shall be weather tight and performed by a qualified roofing contractor to avoid any warranty issues | Is the current roof at building 100 under warranty? If so, who holds the warranty? | Bldg. 100 bay N roof was done back in 2010. The warranties are generally 20 year. Redd Roofing was the contractor and would hold any warranties. | |
| 82 | 4.1, g- Parking Area | The contractor shall vacuum sweep the entire project area daily. | Can the area be cleaned in a different method, like sweeping attachments on a skit steer? | Please follow SOW. | |
| 83 | 4.4, g- Landscaping | New irrigation system design and installation shall include the tie-in of existing irrigation feeds to park strips directly in front of buildings 100. | Is it required to coordinate irrigation work with American Water? | Work downstream of the irrigation shutoff valve or backflow preventer does not need to be coordinated with AW. If a new irrigation point of connection to the water main is needed, then yes, AW needs to be involved. | |
| 84 | 4.12, c- Canopies-Electrical | The contractor shall provide and install complete heat tape systems on the canopies and within rain gutters and down spouts | Does the Government want the Heat Tape tied into EMCS? | Yes. In Accordance With (IAW) Base Facility Design Standards (BFDS). | |
| 85 | 3.7, a-DDC Controls-Communications Room | The contractor shall provide and install new Interface Card (similar to Melco-Bems Interface Card) for new ductless split in communications room and provide space temperature sensor and amp sensor | Through research we found that the closest panels are MS3 panels. Does the government want these MS3 panels upgraded, or should we use the existing controls? | No, tie into existing controllers. | |
| 86 | 1,y- General Requirements | Clause H-1 of the Basic Contract is not required for this project | Where can we find Clause H-1? | ||
| 87 | 3.3 Architectural - Communications Room | a) The contractor shall construct a 10’ x 10’ communications room with hard lid ceiling. | Is it the government's intent for a 10' x 10' communications room dimension an inside finished 10' x 10' area? | Yes. | |
| 88 | 4.8 PRE-CAST VAULT | a) The contractor shall install pre-cast concrete vaults as indicated in figure #10 and site visit. See figure #1 for proposed vault location and figure #4 for concrete vault details. Steel lid with asphalt required where vault crosses street. | During the site walk we noticed that the Red Stake indicates a water line running in the sidewalk near the same location as the new steam line vault. What is our minimum clearance to this line vertically and horizontally? | A steam vault cannot be placed on top of a water main running in the same direction. If they cross, then there needs to be 2-ft of vertical separation. The horizontal separation needs to be at one-to-one slope plus one foot from the bottom of the water line to the bottom of the steam vault so that AW can excavate to access the water line without compromising the integrity of the steam vault. I.e. if the water line is 5 feet deep to the bottom, and the steam vault is 3 feet deep to the bottom. Then the separation needs to be 3 feet (1:1 for 2 feet plus 1 foot). | |
| 89 | 4.8 PRE-CAST VAULT | a) The contractor shall install pre-cast concrete vaults as indicated in figure #10 and site visit. See figure #1 for proposed vault location and figure #4 for concrete vault details. Steel lid with asphalt required where vault crosses street. | During this site walk we noticed that the Red Stake indicated a power line running parallel to the sidewalk near the new steam vault location. What is our minimum clearance on this line? | The clearance needs to be 10 feet to allow for proper heat dissipation from the steam line to the soil so that it doesn’t reduce ampacity in that section of line. | |
| 90 | 4.8 PRE-CAST VAULT | a) The contractor shall install pre-cast concrete vaults as indicated in figure #10 and site visit. See figure #1 for proposed vault location and figure #4 for concrete vault details. Steel lid with asphalt required where vault crosses street. | Will the government provide as/built or utility maps for use on this proposal? | See utilities maps provided by the goverment. All utility locations are aprroximate. On site utilities will be located and marked after award. | |
| 91 | 4.5 PLUMBING – STEAM PIPING | a) The contractor shall demo steam/condensate piping and all associated components to facilitate new piping in vault. | Where should the new steam lines terminate? At the existing vaults or at the building line? | Building line. | |
| 92 | 4.5 PLUMBING – STEAM PIPING | a) The contractor shall demo steam/condensate piping and all associated components to facilitate new piping in vault. | Are the existing buried steam lines to be abandon in place outside of the new trench areas? | No, demo all steam lines. | |
| 93 | 4.5 PLUMBING – STEAM PIPING | a) The contractor shall demo steam/condensate piping and all associated components to facilitate new piping in vault. | Will the steam pipe in the vault require cathodic protection? | No. | |
| 94 | 4.11 CANOPIES | a) The contractor shall demo existing canopies (4 each) and reinstall all electrical, plumbing, metal, asphalt, concrete and any other items in preparation for the installation of the new canopies and lights. See figure #6 for canopy locations. | During the site walk we noticed that Canopies #1 and #2 are tied into the handrails. Will new handrails be required for these two canopies or should we modify the existing handrails in these locations? | Install new Handrails. New hand rails shall be powder coated to match canopy. | |
| 95 | 3.3 Architectural - Communications Room | b) The contractor shall use 1-5/8” x 3-1/2” metal studs, 16” on center. All hard walls shall extend above the ceiling 1’ with seismic bracing according to code. All studs shall be secured to top/bottom plates with 4 screws, 2 on top of stud, and 2 on bottom of stud. Stud walls/bottom plates shall extend below raised flooring and shall be securely anchored to the concrete floor. Re-install raised flooring to meet up with all walls of room, interior and exterior. | What brand of raised flooring was used in the area where the new communications room will be constructed? What type of support system was used on the existing raised floor? | Government does not have this info. | |
| 96 | 3.3 Architectural - Communications Room | i) The contractor shall provide and install ESD anti-static 12” x 12” floor tiles per manufacturers recommendations and instructions. Color TBD after award. | Would the user be open to using a static dissipating carpet tile in the new communications room? | Yes. Install new 12" x 12" ESD anti-static carpet tiles. | |
| 97 | 4.4 Landscaping | m) The contractor shall tie-in all existing irrigation control wires feeding the areas below into the new irrigation controller and ensure those systems are operational from the new timer: | Please provide a drawing indicating the location of the irrigation controllers in the building as well as pictures if possible. | Existing controller is inside the mechanical/utility room located inside of Bay “P” (south side of building), just to the left of the main entrance. Government does not have pictures to provide. | |
| 98 | 4.11 Canopies | e) The new canopies shall be solidly anchored and seismically secured to concrete footings and to the building per manufacturer’s instructions/recommendations. | Are engineered stamped drawings required? | Yes. Same answer as question 100. | |
| 99 | 4.11 Canopies | f) The contractor shall powder coat new canopies and all related parts to standard Dakota Brown. Reference BFDS (dated 19 October 2020), Section 4.1.2. | An exact Dakota Brown standing seam roof material is not available. Many canopy roofs are wrapped in Burnished Slate. Is this acceptable? Should the powder-coated steel match the Burnished Slate color? | Burnished Slate is acceptable. Yes powder coat steel to match. | |
| 100 | 4.11 Canopies | b) The contractor shall construct canopies with standing seam metal roof canopy over doors (entry areas). Canopies shall meet BFDS/ACP and be able to withstand wind and snow loads of this area. Contractor shall match the style and appearance of the canopy shown in figure #7. Canopy 2 shall cover entire handicap ramp, match existing size for canopies 3 & 4 and all new canopies shall match in style. All canopies shall completely cover stairs and extend 3’ beyond bottom step. | Please clarify the glass/glazing requirement of the canopies (explosion proof, standard etc.). | All canopies and pavilion shall be engineer designed and stamped. Or, the contractor shall provide their design/recommendations to a licensed professional Engineer for approval. The contractor shall provide engineers recommendations, if any, and all recommendations shall be incorporated into this Statement of Work. Glass requirements shall meet applicable code for this type of application, to be determined by the engineer. No higher requirements such as blast resistant, explosion proof, etc. are needed. These drawings must be submitted and approved by the government. Submittals can be after award but prior to NTP. | |
| 101 | 4.13 Pavilion | a) The contractor shall construct new 15’ x 15’ metal pavilion with brick columns, low sloped gable and standing seam metal roof canopy. Pavilion shall meet BFDS/ACP and be able to withstand wind and snow loads of this area. Brick style and color TBD after award. | Are engineered stamped drawings required? | Yes. Full design on pavilion, canopy, steam vault and parking lot. Provide after award, prior to install, for government approval. | |
| 102 | 4.13 Pavilion | a) The contractor shall construct new 15’ x 15’ metal pavilion with brick columns, low sloped gable and standing seam metal roof canopy. Pavilion shall meet BFDS/ACP and be able to withstand wind and snow loads of this area. Brick style and color TBD after award. | Does the pavilion need finished soffit panels or is open concept acceptable? | Open concept is preferred, but must meet the BFDS, ACP and be approved by the government prior to NTP. Engineered Stamped design is required on the pavilion and canopies. | |
| 103 | 4.13 Pavilion | a) The contractor shall construct new 15’ x 15’ metal pavilion with brick columns, low sloped gable and standing seam metal roof canopy. Pavilion shall meet BFDS/ACP and be able to withstand wind and snow loads of this area. Brick style and color TBD after award. | Can the government specify the style and/or type of brick required? Is there a tyle and/or type of brick the government wants us to match? If so, can you provide pictures? | Match exisiting as close as possible. Staining of brick may be needed to provide a more accurate match. Contractor to provide sample prior to install. | |
| 104 | 4.11 Canopies | b) The contractor shall construct canopies with standing seam metal roof canopy over doors (entry areas). Canopies shall meet BFDS/ACP and be able to withstand wind and snow loads of this area. Contractor shall match the style and appearance of the canopy shown in figure #7. Canopy 2 shall cover entire handicap ramp, match existing size for canopies 3 & 4 and all new canopies shall match in style. All canopies shall completely cover stairs and extend 3’ beyond bottom step. | The canopy we are matching has two tiers..Does the government want a double tiered canopy system? | All canopies and pavilion shall be engineer designed and stamped. Or, the contractor shall provide their design/recommendations to a licensed professional Engineer for approval. The contractor shall provide engineers recommendations, if any, and all recommendations shall be incorporated into this Statement of Work. Glass requirements shall meet applicable code for this type of application, to be determined by the engineer. No higher requirements such as blast resistant, explosion proof, etc. are needed. These drawings must be submitted and approved by the government. Submittals can be after award but prior to NTP. | |
| 105 | 3.8 COMMUNICATIONS WIRING – COMMUNICATIONS ROOM | q) The contractor shall provide a dedicated electrical branch circuit panel board for each TR with the following minimum requirements: 120/208 volt, 3-phase or 120/240 volt, 1-phase, 24-(or 20 for 1-phase) space panel with a minimum 100 ampere (A) bus rated capacity. Feed all loads within the TR, except lighting, from this dedicated TR panel. Loads must include, but are not limited to, convenience receptacles, dedicated rack or cabinet receptacles, and HVAC systems (including exterior units for split systems). Provide 125V, 20A duplex convenience receptacles at 6 feet (1800mm) intervals on center around perimeter walls. When required by the Activity, provide an additional dedicated 125V, 20A circuit on the wall above the entry door for future electronic security system requirements. Coordinate with UFC 4-021-02, Electronic Security Systems (ESS) (dated 1 October 2013 Change 1, 11 September 2019). At a minimum, provide two multi-outlet power strips in each rack or cabinet. One power strip must be 240 or 208V, 1-phase; the other must be 120V 1-phase. To minimize accidental shut-off, equip power strips with indicator lights, but no integral on/off switch. Provide matching (NEMA configured) twist-lock type receptacles fed from dedicated circuits in the TR panel to power each power strip. Install twist-lock receptacles above rack or cabinet, mounted to telecommunications cable tray or in ceiling space. As some rack or cabinet mounted equipment may require larger quantities of electrical power, the designer must consult with the local telecommunications group having jurisdiction to determine exact electrical power requirements for each TR. | Where does this panel need to be located? Can the panel be surface mounted? Where do we get the 100 amp power from for the panel? | ||
| 106 | 3.8 COMMUNICATIONS WIRING – COMMUNICATIONS ROOM | dd) The contractor shall provide, install, terminate, label, and test all rerouted cable according to all installed backbone and horizontal telecommunications cabling and connecting hardware must meet minimum performance requirements and be tested in accordance with TIA-568-C. Provide report of all tests results and certifications to the proponent and telecommunications manager upon completion. | Please clarify which cables require to be rerouted? | Under direction of contracting/CE we have realized this issue. The new plan will be keep the rack in place, you will not pull back the cable and pull it through a conduit, install the fiber (see instrutions when mentioning service loop on fiber), and continue with plan to remove backboard, 66 blocks, an install 25 pair to 24 port patch panel. Test and label new 24 strand fiber and provide results to SCXP PM (Michael Tagliaferro). | |
| 107 | 3.8 COMMUNICATIONS WIRING – COMMUNICATIONS ROOM | hh) The contractor shall pull back all CAT5/CAT6 from hole in sheet rock and reroute back through 4 in conduit. | There is no slack on either end of cat5 cables to the existing rack. Does the government want these left alone or all replaced? | Under direction of contracting/CE we have realized this issue. The new plan will be keep the rack in place, you will not pull back the cable and pull it through a conduit, install the fiber (see instrutions when mentioning service loop on fiber), and continue with plan to remove backboard, 66 blocks, an install 25 pair to 24 port patch panel. Test and label new 24 strand fiber and provide results to SCXP PM (Michael Tagliaferro). | |
| 108 | 3.8 COMMUNICATIONS WIRING – COMMUNICATIONS ROOM | Does the fiber need to be rerouted? Does it need to be pulled through a sleeve? If so, is it long enough to re-terminate? Or, does it need to be replaced? | We have determined that we will replce the fiber due to position and lack of slack. The new fiber will be a 24 SM strand indoor rated fiber with pre-spliced LC connectors (No hotmelts). The fiber is running to Bay P according to the tag and is approx. a 400 ft run (Shine light to verify) | ||
| 109 | 3.8 COMMUNICATIONS WIRING – COMMUNICATIONS ROOM | Does any communications work or other work have to be performed during other than normal hours? | The only time the comm work should be performed other than normal duty hours wll be when cuting over the fiber | ||
| 110 | 3.9 FIRE SUPPRESSION – COMMUNICATIONS ROOM | Does the new communications room need a fire alarm strobe? | No. | ||
| 111 | Please provide asbuilts of Building if available? | Government does not have this information. | |||
| 112 | What is the current the roofing system on Bldg. 100? | Contractor should have field verified during site visit. | |||
| 113 | 1 | The Seed SOW References a HAZMAT survey, please provide? | Provided as an attachment. NOTE - This document is not required to be completed or submitted until after task order award, but it must be approved before issue of the project NTP. | ||
| 114 | 4.3 | During the the site Visit, the Owners Rep. stated that all trim was to be painted, besided the gutters. please confirm? | Correct. | ||
| 115 | Att. 14 | The Seed SOW provides a excel spreadsheet to provide pricing, e4clicks typically used for SABERS, produces a user friendly report that is broken down by division is this acceptable to use in-lieu of the excel spreadsheet? | Use excel spreadsheet provided for this basic contract task order. | ||
| 116 | 2.1 | The Seed SOW requires the submission of several products with the bid. Please provide product detail as what was done with the HVAC, DDC and Heat. | Unsure of question, government cannot answer appropriately. | ||
| 117 | 4.7 | Can mechanical excavation be used on the project or is hydro ex required? | Mechanical requires dig permit, hydro does not. Hydro is preferred for utility locating. Follow BFDS 2.6 - 2.10 | ||
| 118 | 4.4f | Please provide the location of the existing irrigation timers and the location of the new timer? | Existing controller is inside the mechanical/utility room located inside of Bay “P” (south side of building), just to the left of the main entrance. New timer shall be located in same room as existing. | ||
| 119 | 4.1i | Please provide soils report so that a determination of soft soil removal can be determined? | Government does not have this info. | ||
| 120 | 3.9 | Please provide fire sprinkler drawings so that proper fire supression can be applied? | Government does not have drawings to provide. | ||
| 121 | 4.3 | During the site visit; There were existing transformers onsite are they to be painted as well? | No. | ||
| 122 | 4.3 | Is the flammable containment shed to be painted? | Yes. Replace stickers to match existing. | ||
| 123 | 4.5 | The section describes the performance of the material, but does not discuss shut downs. How long can the steam service be out of operation? | Dependent on building 100 steam process, humidity, etc. | ||
| 124 | 4.5 | Are the existing valves being replace? | Yes. | ||
| 125 | 2.1 | What steam fittings are currently being used? | Field verify. | ||
| 126 | 2.1 | Which manufacture/ Model, LED Surface Mount Fixtures is required? | New lights must meet the salient characteristics of the SOW and provide suffient lumens to meet the Base Facility Design Standards. | ||
| 127 | 2.1 | What is the make and model of the LED Wall Pack Lighting Fixtures? | Please see SOW. | ||
| 128 | NA | Escort Requirements | Will interior work require escorts? | No. | |
| 129 | 3.3 a | Commuincations Room - Hard Lid Ceiling | Will the hard lid in the communication room match the ceiling height outside the room? If not, what is the desired height inside the room? | Yes. | |
| 130 | 3.3 b | Communications Room - Raised Flooring | Will the raised flooring being removed for the new com room be reused inside the room by removing the carpet and applying the anti-static flooring? Or will new raised flooring be required? | Yes, use existing flooring and replace components as needed. Install new 12" x 12" ESD anti-static carpet tiles. | |
| 131 | 3.3 b | Communications Room - Raised Flooring | Existing items under the raised floor in the footprint of the new room's walls-It was conveyed during the site visit that we could cut our bottom track around these obstacles rather than relocating them. Please confirm. | Correct. | |
| 132 | 3.3 e | Communications Room - Door | Will the new door for the comm room need a louver in it? | No. | |
| 133 | 3.8 q. | Communications Wiring - Communication Room |
q) Communication Room Design:
| "When required by the Activity, provide an additional dedicated 1`25V, 20A circuit on the wall above the entry door for future electronic security system requirments." | Will this be a requirement for the activity? | ||
| 134 | 3.8 q. | Communications Wiring - Communication Room |
q) Communication Room Design:
| "As some rack or cabinet mounted equipment may require larger quantities of electrical power, the designer must consult the local telecommunications group having jurisdiction to determine exact electrical power requirements for each TR" | Who is the local telecom group having jurisdiction? | The local electrical shop at Hill AFB will be the authority | |||||
| 135 | 3.9 | Comm Room - Fire Suppression | The existing fire suppression system is a Pre-Action System. This type of system is very susceptible to corrosion and debris. Would the Government like to have the system flushed and camera the piping where we are adjusting sprinklers in the Comm Room area? | No. Schedule outage to relocate sprinkler head. | |||
| 136 | 3.9 | Fire Suppression | New sprinkler system will only require one backflow preventor. There are three in place now. To what extent would the other two unneeded ones be removed? | Remove unnecessary backflows to AW main. Remove stop and waste. Provide serial numbers of removed backflows to the government. Coordinate process with Mark Persico. | |||
| 137 | 4.2 | Pavement Markings | Will the new asphalt require temporary paint during the 30-day cure period before applying the final pavement markings? | No. | |||
| 138 | 4.2 | Pavement Markings | If used, will the temporary paint for pavement markings require reflective media? | N/A. | |||
| 139 | 4.3 | Exterior Paint | Painting on the South and West sides includes downspouts. Please confirm this is only from the bottom of the gutter down to the outfall, but no gutter is included. If not, please clarify where downspout painting is needed to start and stop. | Correct. | |||
| 140 | 4.4 | Landscaping Drawing | Is figure # 8 to be considered the landscaping plan or will a plan need to be submitted and approved? | Figure 8 is the landscape plan. | |||
| 141 | 4.4 y, z | Landscape Boulders | How many large and medium boulders are required? | 3 Large boulders and 4 medium boulders. | |||
| 142 | 4.5 | Steam Piping - Expansion Joints | Will expansion joints or loops be required for the new steam & condensate piping? | Expansion joints are acceptable. Engineer designed and stamped. |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .