This document is a pre-bid Requests for Information (RFI) responses for a federal construction contract (WWYK100209) to repair Perimeter Drive and Industrial Boulevard at Tinker Air Force Base. The project involves full-depth asphalt pavement replacement on Perimeter Drive (approximately 2,800 linear feet), concrete pavement repairs on Industrial Boulevard (18 spot repairs totaling approximately 5,442 square feet), storm drain replacement, grading and drainage improvements, and pavement markings. The solicitation is set aside for Women-Owned Small Businesses (WOSB). The government provided 60+ pre-bid RFIs addressing significant document gaps, specification conflicts, and project scope ambiguities, with government responses clarifying that this is not a design-build contract and that no additional design work is required beyond what is shown in the 35% design drawings.
Key clarifications from government responses include: asphalt mix designs per ODOT specifications (Type A Base/S3 and Type C Surface/S4 or S5); concrete repairs to match existing slab thickness (approximately 8 inches); no curb installation (gutter only); no work inside the airfield fence with RCP replacement only to the fence line; stabilized subgrade equivalent to lime stabilization is acceptable; no stockpiling of materials allowed in the clear zone; all excavated material must be hauled off base; concrete has been tested for asbestos but not coal-tar content; contractor is responsible for traffic control plan submission and outage requests; Airfield Construction Waiver and FAA Form 7460-1 required due to location in clear zone; all government review periods are included in the contractor's performance period; and drawings, specifications, and AutoCAD files are available on the contractor CD. The government will not accept unit pricing for concrete repairs or unsuitable material replacement, requiring lump sum pricing with line-item breakouts instead.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WWYK100209-Repair Perimeter Dr and Industrial Blvd Pre-Bid RFI’s
1. (Solicitation package): The solicitation document (SF 1442 and Sections A through M) is not included in the posted package. Only the drawings (Att 11), submittal register (Att
10) and wage determination were received. Please post the complete solicitation.
PZ to post the entire package documents.
2. (Solicitation, Section A/L): What is the proposal due date, time, and submission method?
PZ to post proposal details after Prebid RFIs are sent back to the contractors.
3. (Solicitation, Section F): What is the period of performance (calendar days after NTP)?
Do liquidated damages apply, and at what daily rate?
PZ to post solicitation details with remaining package documents.
4. (Section L): Please provide Section L (Instructions to Offerors): required volumes, page limits, format, and required forms.
See attachment 2 for Section L.
5. (Section M): Please provide Section M (Evaluation Factors): evaluation factors, their relative importance, and the basis of award (LPTA or best-value tradeoff).
See attachment 3 for Section M.
6. (Solicitation, Section B/K): Please confirm the set-aside is WOSB.
Confirmed.
7. RFI 007 (Perimeter Dr): What is the annual average daily traffic count for the
Perimeter Road? We do not perform an ADT count for 35% designs. As there is no design build requirement this is not needed.
8. (HMA, C-12, A-7-2): What oil type and content is required for the asphalt mix designs?
Refer to TAFB Technical Specifications. ODOT mix design for type A is Base/S3, Type C is Surface/S4 or S5. Type A is the Base course typically 4.0% -5.5% by weight. Type C is surface course typically 4.8% to 6.2%
9. (All sheets, 35% Design): The drawings are marked “35% Design” and the G-01 signature block is blank. Please confirm that there are no design or engineering services required for this project, to include geotechnical investigation.
Confirmed that design or engineering services, and geotechnical investigation are not required.
10. (C-06, C-07): Please provide a detail for “add man bars thru pipe at fence line”: bar size, spacing, material, coating, how they attach, and the number of locations.
See Tinker Specifications in Contractor CD.
11. (C-12, A-7-2, C-10.1; Register lines 44–49, 32 11 29): The drawings call for “6-inch modified subgrade” on Perimeter Dr and “6-inch scarified & compacted subgrade” for the
Industrial Blvd patches. The register includes 32 11 29 Lime Stabilization. Is lime stabilization required or will the GOV consider alternative methods for stabilization, such as geogrid/geofabric? If lime is required, where, at what application rate (% or lb/SY), and at what depth?
Stabilized subgrade equivalent to lime would be acceptable.
12. (C-12, A-7-2; Register lines 51–54, 32 12 15): The drawings call for ODOT “Type A” and
“Type C” asphalt per the ODOT Standard Specifications. The register lists 32 12 15, which is the UFGS hot-mix asphalt section for airfields. Which specification governs mix design, placement, and acceptance testing? Please confirm the current ODOT mix designations that correspond to Type A and Type C. ODOT mix design for type A is Base/S3, Type C is
Surface/S4 or S5.
13. (C-10.1, C-22, C-14, D-6; Register lines 55–61): The register lists both 32 13 11 and 32 13
14 for concrete. The details reference ODOT standards. Which specification governs the
Industrial Blvd patches, gutter, flumes and inlet collars (mix, strength, testing)? Both specifications are necessary for all concrete pavements.
14. (C-04, C-05, C-08 to C-10): Please provide existing pavement thickness and makeup for
Perimeter Dr (including concrete under the asphalt overlay at 6+75–8+50) and for Industrial
Blvd at the patch locations. If existing Industrial Blvd concrete is thicker than 8 inches, should patches match the existing thickness? Are cores or as-builts available? There are no cores for perimeter rd or industrial blvd. Patches on industrial blvd. should match the existing grade of roadway. As-builts are included in the contractor CD.
15. (C-12, A-7-2): If unsuitable soil is found below the subgrade, please confirm that this situation will be handled as a differing site condition.
If unsuitable soil is found, we will evaluate the situation through the RFI process. The
Contracting Officer will make the final determination.
16. (C-07, C-10, C-14): Please provide lengths and widths for the PCC flume at Perimeter Dr
~27+50 (“to swale”) and the drainage flume at Industrial Blvd ~22+50. Only the 20 LF curb-less gutter at Industrial ~12+50 is dimensioned. Refer to the SOW for approximate lengths.
17. (C-09): C-09 shows a line labeled “48.75 ft” at about 11+00 with no description. What work is required there? That is width of roadway at that point. Light blue line is what is called out.
18. (A-7-2, C-10.1): Compaction requirements conflict. A-7-2: subgrade 95% modified
Proctor, fill below 90% standard. C-10.1: subgrade 95% standard, fill below 80% standard. Which governs for each pavement type? A-7-2 is asphalt, C-10-2 is PCC
(concrete pavement).
19. (C-13, C-14): C-13 and C-14 show existing contours and spot elevations only. Please provide proposed finished grades or a roadway profile, swale grades, limits and cross-sections, and storm drain profiles. At a 35% design, these are not provided.
20. (C-02, C-04, C-06, C-07): What are the “25' OC markers typical”? Raised pavement markers, delineator posts, or station markers? Please provide details and specification.
The station ticks shown are at 50-foot spacing. This is from centerline reference points only. 50 ‘ ticks are used for this drawing set.
21. (C-06, C-07, C-11; Register line 41): Please confirm pavement marking material (paint or thermoplastic) and whether existing markings on Industrial Blvd must be removed. Please also define the limits of the 4-inch dashed white line on Industrial Blvd and the “new 4-inch dashed stripe” at the start of Perimeter Dr. Refer to Tinker specifications in the
Contractor CD for paint type. Typically, the 4” dashed is white. All existing paint will need to be removed where the new striping layout will be added.
22. (C-11): Please provide sign size, sheeting, post type and foundation for the new W4-2R sign. Are any existing signs to be removed or relocated? Existing signs will need to be protected. Sign installation is not required on this project.
23. (D-6): Detail D-6 refers to “storm sewer inlet notes on detail 6a,” which is not in the set.
Please provide detail 6a. Detail 6a has been added.
24. (C-20a): Detail C-20a allows steel or GFRP dowels. Is that the contractor’s choice? Please specify the epoxy adhesive for dowels drilled into existing concrete. See Tinker specifications on epoxy included in the contractors CD.
25. (D-1; Register lines 9, 17): No erosion control plan or silt fence locations are shown. Please confirm whether the contractor files the ODEQ Notice of Intent for stormwater coverage, and provide the expected disturbed acreage. See Tinker Specifications included in the contractor CD and the SOW. Contractor files the ODEQ Notice of Intent.
26. (Register lines 42–43, 32 92 23): The register requires sod submittals, but no restoration limits are shown. Please define sod areas versus seed, and the restoration limits along the swales. Any areas disturbed by construction will be required to be restored. Sod or seeding can be utilized if growth is established.
27. (Register lines 20–21): The register requires a tree removal permit and a tree protection plan, but no trees are shown for removal. Are any trees to be removed?
Register lines 20-21 can be NA. This was incorrectly added to the register. If construction comes near any trees, a tree protection plan will be required.
28. (C-02, C-03): Are depths available for the fuel, gas, electric, communication and wastewater lines crossing the work? Are any known conflicts with the new storm drain to be relocated by the Government? See sheet C-01 Civil Note 1 in the provided plans in the contractor CD. No known conflicts at this time.
29. (C-02, C-04, C-06): The proposed staging area is next to the underground fuel line shown on C-02. Are there load limits or setbacks for equipment and stockpiles? See SOW for approval of staging area requirements. No load limits or setbacks are known. If damage to the staging area occurs the contractor will be required to repair the damaged areas.
30. (C-01, note 4): Removed material goes off base. May clean concrete and asphalt be recycled? Is any material to be salvaged to the Government? See C-O1 note 4.
31. (WD OK20260015; D-6): Detail D-6 requires cutting back and rebuilding brick inlet walls, but the wage determination has no bricklayer classification. Will one be added, or should offerors plan on a conformance request (SF-1444) after award?
PZ to provide any information on wage determination.
32. (WD OK20260015): Please confirm that the Highway wage determination applies to all work under this contract, including the storm drain work, with no separate Heavy determination.
33. (C-12): Please provide a revised paving detail (C-12) as it was discussed in the site walk that the roadway footprint would not change. Roadway footprint varies from beginning to end. C-12 is the typical detail to make the roadway uniform. Roadway foot print will not change.
34. (Storm drain, Sta 16+75 & 17+00): Inlets shown to be rebuilt at STA 16+75 & 17+00 require work inside the airfield fence. Please provide the requirements to work inside this fence, including temporary fencing requirements.
No work to be done on the airfield. RCP is to be replaced up to the airfield fence line.
35. (Storm drain, Sta 16+75 & 17+00; D-6): Regarding the inlets to be rebuilt inside the airfield fence at STA 16+75 & 17+00:
a. -Please provide the existing and proposed inflow and outflow elevations of the structures. Refer to the tinker specifications for inflow and outflow specifications in the Contractor CD.
b. -Per detail D-6, should these structures be single or double grate width? Refer to the tinker specifications for inflow and outflow specifications in the Contractor CD.
c. -Detail D-6 states to reuse existing castings but the existing structure does not utilize castings. Please provide information for the required castings Refer to the tinker specifications for inflow and outflow specifications in the Contractor CD.
36. (Site access): Clarify the construction entrance gate and provide current gate wait times for material deliveries. See plan cover sheet for truck route. Current gate waits times vary day by day.
37. (Equipment height): Is there a maximum height not to exceed for equipment? We will need up to 25' of height clearance for dump trucks and our MTV. See airfield height requirements listed in the specification 00 80 05.
38. (C-02, C-03): Please provide the depths of the existing utilities shown on Sheets C02 and
C03 that are located within the project disturbance limits. See Sheet C-01 general note 1.
39. (C-06, C-07): Please provide a detail for the drainage swales called out on sheets C-
06 & C-07. See sheets C-13 and C14 for elevations
40. (General, airfield fence): Please confirm whether there is work inside the airfield fence. If so, please provide specific requirements for performing work inside/behind the airfield fence, to include removing portion of the existing airfield fence, any temporary fence required, type and size of temporary fence, etc.
See specification 00 80 05 for airfield requirements See revised submittal register in attachment 4.
41. (SOW 3.7, 5.1–5.4, 9; Appendices B and C): The SOW states the drawings in PDF and
AutoCAD format, the specification sections listed in Appendix B, the facility standards in Appendix C, as-built drawings for Perimeter Dr and Industrial Blvd, and Attachments 1–3 are “included on the attached CD.” None of these were posted.
Please post them, along with the editable submittal register cited in SOW 3.7.
PZ to post documents from the contractor CD.
42. (SOW footer, 3.5; Spec 01 33 16.00 10): Related to RFI 009. The SOW footer reads
“WOSB Preliminary (35%) SOW,” and Appendix B includes 01 33 16.00 10, Design Data
(Design After Award). Please confirm the Contractor is not responsible for completing the design from the 35% drawings, and define the working documents required by SOW 3.5 before construction can start. All division 00 and 01 specs are included with every project.
No additional design is required.
43. (SOW 4.1.1, 4.1.2, 4.3.4; C-02, C-04, C-07): Demolition and paving limits differ between the SOW and drawings. The SOW calls for concrete demolition from 0+50 to 8+50 and
27+00 to 28+50, asphalt demolition from 8+50 to 28+00, and new asphalt from 0+50 to
28+50. The drawings show concrete demolition from 0+50 to 6+75 (C-02) or 6+85 (C-04), asphalt overlay on concrete from 6+75 to 8+50, no concrete demolition at the east end, and new asphalt ending at a tie-in to existing concrete at about 28+00 (C-07). Please confirm the demolition and paving limits
Concrete demolition on east end is for northeast concrete edge on industrial blvd.
Concrete demolition for west end is for partial driveway entrance on north side of perimeter rd.
44. (SOW 4.3.3; C-02; Details C-13, C-22): SOW 4.3.3.1 and 4.3.3.2 call for new curb and gutter from 0+50 to 7+00 (north side) and 0+50 to 7+80 (south side), with gutter only beyond those limits. C-02 notes “gutter and no curb.” Please confirm where curb and gutter is required, and whether detail C-13 applies. No curbs to be installed. All documents will be revised to reflect this new requirement.
45. (SOW 2.3, 4.1.3, 4.3.1; C-06, C-07): The SOW calls for replacing “the 36” storm drain structure at Sta. 17+00" with new pipe to 5 ft from the perimeter fence, and “the 18” storm drain structure at Sta. 24+25" with 150 ft of new pipe. Please confirm whether 36-inch and
18-inch are the new pipe diameters, and provide the pipe material, length, slope and inverts at each location, and the structure type at each location. The drawings describe this work as “between airfield fence and perimeter fence.” Please confirm which fence the SOW refers to. Refer to the specification 33 40 00 in the
Contractor CD for appropriate type of pipe. Replace in kind.
46. (SOW 2.3): Phase 1 reduces Perimeter Rd to two lanes on the south half (24 ft) while the north half is constructed, and Phase 2 reverses this. However, both phases state Type III barricades “will be used to close the north half.” Please confirm Phase 2 closes the south half. Is a traffic control plan required for Government approval, and is the Contractor responsible for preparing it? Yes, the south half would be closed with type III barricades during construction. The contractor is responsible for submitting a traffic control plan and submitting outage requests per SOW 1.8.
47. (SOW 4.4.2, 4.4.3; C-08 to C-10): SOW 4.4.2 and 4.4.3 both list full-depth repair locations for the “southbound lane.” Please confirm 4.4.3 refers to the northbound lane. The 17
SOW station ranges also differ from the 18 patches dimensioned on C-08 to C-10. For example, the SOW lists 21+35 to 22+75, while the drawings show three smaller patches between about 22+00 and 22+60. Please confirm which governs for pricing, the SOW ranges or the drawing areas. 4.4.3 refers to the northbound lane. The SOW refers to all patching between 21+35 to 22+75.
48. (SOW 4.2.1, 4.3.2, 4.3.5, 4.4.1, 4.4.4): The SOW’s sheet references don’t match the drawing index:
Industrial Blvd patches reference “C02, C03, C04” (the patches are shown on C-08 to C-10).
SOW is updated with correct page reference
- Grading references “C08 – C014” (contours are on C-13 and C-14 and show existing grades only). Grading references are on plan sheets C-8 to C-12 as well.
- Pavement markings reference “C05 & C06” (markings are shown on C-06, C-07 and C-11).
SOW is updated with correct page reference
- Phasing references “3.D” (phasing is SOW 2.3). SOW is updated with correct page reference
- Dowels reference “C-20” (the detail is C-20a). DT-02 has Dowel reference as C-20a
- Please confirm the intended sheets.
SOW is updated with correct page references. See attachment 1 for revised SOW.
49. (SOW 2.3, 4.3.5.3; C-06, C-07): The SOW requires additional signage for “reduction of lanes,” a “turn lane on perimeter drive,” and “driver instruction of final roadway alignment.” No signs or turn lane are shown on the Perimeter Dr drawings. Please provide sign types, sizes, locations and quantities, and the turn lane location and striping. This is for temporary signage during construction. See G-01 note 3. No new signage is required on this project.
50. (SOW 4.1.4; Spec 32 92 19, 32 92 23): The SOW requires stockpiling sod and topsoil from
7+00 to 26+75 and 8+45 to 28+50 “away from clear zone.” Please confirm whether the stockpiled sod and topsoil is to be reused or new sod is required (32 92 23). Where may stockpiles be placed, and what is the clear zone width? Is seeding (32 92 19) required anywhere? Stockpiling is not needed. New Sod would be required per Tinker
Specification in Contractor CD provided 31 23 06 for topsoil. Seeding and/or sodding is required at disturbed areas per tinker specifications. See RFI 26 for seeding vs sod.
51. (SOW Appendix B; Register lines 51–59): Appendix B lists no hot-mix asphalt specification section and lists 32 13 14 for concrete. The submittal register lists 32 12 15 (HMA) and
32 13 11 (PCC), and neither section is in Appendix B. Please provide the governing HMA specification and confirm 32 13 14 governs all concrete paving, patches, gutter and flumes. UFC 3-250-01 and UFGS 32 12 15.13 have been added to the Amended SOW.
32 13 14 is non-airfield pavement, which can be asphalt, concrete, or any other surface built for driving or walking.
52. (SOW Appendix B): Appendix B includes specification sections for work not shown on the drawings: 32 01 13 seal coats, 32 01 14 asphalt sealer, 32 01 16 cold milling, 32 01 17 crack sealing, 32 01 17.62 fabric reinforcement, 32 01 22 bituminous rejuvenation, and 32 11 11 asphalt treated permeable base. Are any of these required? If so, where?
They are not all necessarily required but are on the SOW for reference in case they are needed.
These are included depending on the means and methods of the contractor.
53. (SOW 3.3.3; Register lines 4–5): Submission deadlines conflict for the Airfield Construction
Waiver and FAA Form 7460-1. The SOW requires submission by the 1st business day of the month with 60 days for review, while the register requires the 5th day of the month with 45 days for processing. Please confirm which governs. SOW governs over the submittal register.
54. (SOW 3.6.2; Detail C-20a): SOW 3.6.2 references UFC 3-250-01, Tables 8.2 and 8.3, for dowel size and spacing, while detail C-20a shows 3/4-inch × 16-inch dowels at 12 inches on center. Please confirm which governs for the 8-inch Industrial Blvd patches. Table 15-2 and Table 15-3 will be referenced in the amended SOW.
55. Since the solicitation and specifications are not issued prior to the RFI deadline, please allow Contractors time to review the solicitation, especially Section L and M, and the specifications, and submit any RFIs pertaining to those documents.
This will be determined by the contracting officer.
56. Is this project funded?
This information is not required by the contractor. Projects are funded by priority at the time of award.
57. Is attendance at the site visit mandatory to bid on this project?
No, however this will be left to the determination of the contracting officer.
58. Please confirm that excess soil/spoils that are to be removed from the jobsite can be removed from Tinker AFB and disposed at a location designated by the Contractor, and that no testing is required prior to haul off base. See Tinker specifications on removal of soil/spoils.
59. Please confirm that there is no hazardous material testing or abatement required with this project. The SOW states the specifications (Appendix B), Tinker AFB standards (Appendix C), Attachments 1–3, relevant as-built drawings and AutoCAD files are on the "attached
CD." None of these were included in the posted solicitation package. Please post the full specification set, Attachments 1–3 (including the Environmental Survey), the Perimeter Dr
/ Industrial Blvd as-builts and the CAD files. Also note SOW 2.7 identifies the RMDF as
Attachment 3, while SOW 9 lists it as Attachment 2 and the Environmental Survey as
Attachment 3 – please confirm.
SOW is updated with correct page references
60. All sheets are marked 35% Design and spec 01 33 16.00 10, Design Data (Design After
Award), is listed. Is the offeror required to complete the design (civil, grading, drainage, pavement) and furnish PE-sealed drawings and survey after award, or will 100% construction documents be issued by amendment before proposals are due? If design is in scope, please define the deliverables and review stages so they can be priced and scheduled. This is not a design build contract. No additional design is required by the contractor.
61. The SOW references sheets that do not match Appendix A: Industrial Blvd repairs are referenced to C-02/C-03/C-04 (index shows C-08/C-09/C-10); grading to "C08–C014"
(contours are C-13/C-14); Perimeter Dr and Industrial Blvd pavement markings to C-05 &
C-06 (those are the Perimeter demo/installation plans; Industrial markings are on C-11).
Please confirm the correct sheet for each item. SOW is updated with correct page references
62. The following details are referenced but not provided: C-10.1 (full-depth concrete repair), C-20, D-6 (storm drain), the "PEC/concrete collar" for the converted inlet at Sta. 7+50, and the "man bars thru pipe at fence line." Sheets DT-01/DT-02 contain only C-13, C-14, C-
20a, C-22, D-1 and D-3. Please issue the missing details.
Plan set in the contractor’s CD has the details that are said to be missing.
63. SOW 4.3.4 calls for 4" Type A + 2" Type C asphalt. Section C-12 shows only 2" Type C over a
6" modified/stabilized layer over 1'-4" compacted native soil, with no 4" Type A course shown. Please provide the complete typical section: each course, thickness and material;
whether the 6" layer is lime-stabilized subgrade (and lime
%), aggregate base or ATPB; and compaction requirements. Also confirm the mix designations – are "Type A" and "Type C" intended as ODOT mixes, and if so which current ODOT Superpave designations (e.g., S3/S4) and binder grade apply? ODOT mix design for type A is Base/S3, Type C is Surface/S4 or S5
64. Concrete is demolished from Sta. 0+50–8+50 and 27+00–28+50, asphalt from 8+50–28+00, and new asphalt is placed from 0+50–28+50. (a) Confirm the concrete sections are replaced with the asphalt section. (b) C-07 notes "Tie into existing concrete (end of new AC pavement)" near the east end, which conflicts with demolishing concrete to 28+50 – please confirm the east tie-in station. (c) Asphalt and concrete demo overlap at 27+00–28+00, and
C-02 notes "asphalt overlay and concrete pavement demo 6+75 to 8+50" – is the existing pavement composite (AC over PCC) in these areas? Please provide existing pavement thicknesses or core data. C-12 shows 4, 12’ lanes. Asphalt will need to transition to the concrete on Industrial Drive. See C-01 note 1
65. SOW 2.3 describes each half of Perimeter Rd as 24' (48' total), while C-12 shows three
12' lanes (36'). SOW 4.3.5.3 also references a turn lane and "final roadway alignment."
Please confirm the final pavement width, number of lanes, turn lane location/length, and whether the road is being narrowed from its existing width. C-12 shows 4, 12’ lanes
(two driving lanes and two shoulders)
66. Demolition and installation limits do not align: (a) curb & gutter demo on the south side between Sta. 0+50–8+50 is not listed, yet new curb & gutter is installed on the south side
0+50–7+80; (b) no curb or gutter is shown on the south side between 7+80 and 8+30; (c) north-side gutter ends at 26+90, but demo runs to 28+50. Please confirm limits on each side and confirm Detail C-13 (barrier curb & gutter) applies where curb is called for and
Detail C-22 (6" gutter, no curb) applies elsewhere. Call out arrows point to demolition of curb and gutter approximate areas. Field verification is necessary.
67. Please provide for each location: structure type and number (SOW 4.1.3 says "structures" at 17+00), structure dimensions, pipe material and class (RCP class?), pipe length from
17+00 to 5 ft from the perimeter fence, inverts/slopes, and connection at the remaining pipe. Also confirm the 18" line at 24+25 is 150 LF total, not 150 LF per phase. Replace in kind. Total Length is approximately 150 LF total. Field verification is necessary.
68. Storm drain work occurs between the airfield fence and the perimeter fence. (a) Will any fencing be removed and reinstalled by the Contractor? If so, provide the fence type and security requirements during the opening. (b) Please provide the security bar ("man bars") detail – bar size, spacing, material and attachment. (c) Is escort, gate access or security posting required to work in this area, and is it Government-furnished? No work on the airfield. The RCP will be replaced up to the airfield fence line.
69. SOW calls for a "concrete collar" and C-06 calls for a "PEC collar." Please clarify the collar material and dimensions, the new grate type and load rating, and whether the existing cast iron inlet frame is reused or replaced. PEC (Pipe End Collar) is a precast concrete collar.
70. C-05 notes "Demo for new flume" on Perimeter Dr and C-09 notes "New drainage flume" and "Curb-less gutter, 20 LF" on Industrial Blvd. These items are not in the SOW. Please confirm they are in scope and provide their locations and lengths. Please see amended
SOW.
71. Both SOW 4.4.2 and 4.4.3 are labeled "southbound lane" – please confirm which list is northbound. Several ranges also overlap between the two lists (e.g., 0+50–0+75, 1+50–
1+80, 6+00–6+50). The drawings show individual repair areas in square feet. Please confirm the drawing areas govern and provide the total square footage of full-depth repair.
Please see amended SOW
72. Please provide the existing slab thickness, reinforcement and joint spacing, and the replacement section (PCC thickness, flexural/compressive strength, base material and thickness, and reinforcement, if any). Also confirm whether tie bars are required at longitudinal joints and whether joint sealing per 32 13 74 is required at all new joints.
See as built drawings in Contractor CD. See detail C-20a.
73. SOW 4.4.5 states all locations are approximate and will be field verified. For a firm-fixed-price proposal, please confirm offerors should price the quantities shown on the drawings, and state how quantities found in the field above or below those quantities will be adjusted (e.g., a unit price per SF).
Pavement Marking can be verified by the drawings/CAD files/asbuilts/google maps. No adjustments required. Please provide a firm fixed price proposal.
74. Detail C-20a specifies 3/4" x 16" smooth dowels at 12" O.C., 30" from corners. SOW
3.6.2(3) references UFC 3-250-01 Tables 8.2/8.3, which size dowels by slab thickness and may call for larger dowels. Please confirm which governs. Also confirm whether steel and
GFRP dowels are equally acceptable, whether steel dowels must be epoxy-coated, and the epoxy anchoring product requirements. Table numbers have been corrected in the updated SOW.
1. Please confirm the marking material (paint, thermoplastic or preformed tape), and whether temporary markings are required at each phase shift. (b) Several sheets note
"25' OC markers typical" – please confirm whether these are raised pavement markers to be furnished and installed, and their type and color. (c) SOW 4.4.4.1 describes
Industrial Blvd markings as "East to West 0+00–23+00" although that road is stationed
South to North – please confirm limits. (d) Please provide a sign schedule (sign types, sizes, quantities, post type and locations) for the W4-2R "Right Lane Ends" sign and the "additional signage" in SOW 2.3 and 4.3.5.3. b) SOW revised to state “South to
North”. No new signage is required on this project.
2. Phase 2 states Type III barricades "will be used to close the north half" while the south half is built – please confirm the south half is closed in Phase 2. (b) SOW
4.3.5.2 refers to phasing "as described in 3.D"; please confirm this means SOW 2.3.
Corrected in updated SOW
(c) May Industrial Blvd repairs run concurrently with Perimeter Dr phases? That would be a question CO/COR (d) Are flaggers, short-term full closures or detours permitted (e.g., for storm drain crossings and paving at the centerline joint)? See SOW for outage requests and closures. (e) Is a sealed traffic control plan required? Yes, submitted to the government in the submittal process.
3. SOW 2.5 states the work is not in an airfield operations area, yet it and the submittal register require an Airfield Construction Waiver, and the register requires FAA Form 7460-
1. Please confirm both are required. The timing also conflicts: the SOW states 60-day review with submission by the 1st business day of the month, and the register states submission by the 5th day of the month with 45 days processing. Please confirm which governs, and whether the period of performance accounts for this lead time before work may start. Please also state any equipment height limits.
No work will be done within the airfield however, due to being in the clear zone an airfield waiver and FAA Form 7460-1 is required. The RCP will be replaced up to the airfield fence line.
4. The SOW does not state the period of performance. Please provide the number of calendar days. With a target start of December 1, 2026, asphalt and concrete placement may be limited by specified minimum temperatures. Will the Government allow seasonal suspension, or adjust the schedule, for weather that prevents paving within specification limits?
PoP may be decided to be provided by the contracting officer. Any delays in scheduled are detailed out in specification 01 32 16.00 20.
5. C-02 shows underground communication, gas, electric, wastewater and fuel lines within the work limits. Please provide available depths/as-builts for these lines, particularly where they cross the storm drain excavations at Sta. 17+00 and 24+25. Is any relocation or lowering of utilities in scope? For the fuel line, please identify the owner and any special excavation, standby or permit requirements. See Sheet C-01 general note 1. Dig
Permit will be required. No relocation of utilities.
6. SOW 4.1.4(a) and (b) give overlapping stockpile ranges (7+00–26+75 and 8+45–28+50) without stating which side of the road each applies to – please confirm. Both seeding and sodding specs are listed; please state which restoration method applies and its limits. Please also identify the approved topsoil stockpile location "away from the clear zone." No stockpiling of material onsite. See RFI 26 for seeding and sodding.
7. Lime-stabilization submittals are listed in the register. Is there a geotechnical report or soil data (classification, PI, CBR) for Perimeter Dr? Please provide it, and confirm whether lime stabilization is required across the full Perimeter Dr footprint and at the Industrial Blvd repairs. Stabilized subgrade equivalent can be submitted for approval. No geotechnical report available.
8. The submittal register cites 32 12 15 (Hot Mix Asphalt), 32 13 11 (Portland Cement
Concrete) and "32.12.10.2," which are not in Appendix B. The details also say materials and construction shall meet the ODOT Standard Specifications. Please confirm which specification sections govern asphalt and PCC paving, and the precedence between
ODOT and the Tinker AFB/UFGS sections. SOW has been updated to include 32 12 15 and
32 13 11.
9. C-04 and C-06 show a "Proposed Staging Area" – please confirm its location, size and availability, and whether it may be used for material stockpiles. (b) Please confirm the required haul route and truck gate shown on G-01. (c) General Civil Note 4 requires disposal off base – does the Government want any millings or broken concrete stockpiled on base, or may they be recycled by the Contractor? Staging area shown is approximate. Availability of staging area will be unknown until the Contractor submits the staging area request during construction. Confirmed location of haul routes and truck gate on G-01. Millings and broken concrete can be recycled but must be done off base.
10. Only the Highway wage determination was provided. Please confirm it applies to all work, including storm drain structures and pipe, and that no Heavy or Building wage determination applies.
11. Does the Government want the proposed road to be widened IAW Sheet C-12 or stay the same width as existing? Roadway footprint varies from beginning to end. C-12 is the typical detail to make the roadway uniform. Roadway cannot be widened due to being in the clear zone.
12. As the existing road width is appr. 42’ wide, what will the Government determine is the acceptable minimum width of the two-lane road during construction? Lane width is required to be 12’ minimum from centerline. Shoulder can vary depending on the width of the road at any given point.
13. As the curb is not being replaced, grading of the grassy area will be required to ensure proper drainage. Will it be up to the contractor to determine the extends of the regrading efforts? See SOW para 4.3.2 for grading efforts. Additionally, any restoration grading from damage by the contractor will be required to regrade.
14. Elevations are noted on Sheets C-13 and C-14. Information Requested: Please confirm if these are existing or planned grades. These are existing grades and elevations. Contractor is to match as closely as possible while keeping in mind positive drainage.
15. Sheet C-02 states near Sta. 17+00 “Storm Drain Replacement to Fence”. Information
Requested: Please verify that no work is expected within the airfield.
No work on the airfield. The RCP will be replaced up to the airfield fence line.
1. There is existing signage along Perimeter & Industrial Blvd. There is no indication of removals or replacements of existing signage. Information Requested: Please verify if any signage is required for this project. Existing signs are to be protected. No new signage is required on this project.
16. SOW Para. 4.3.5.2 states “All MOT and pavement markings, either temporary or permanent to follow the phasing as described in 3.D.” Information Requested: Please clarify what “MOT” and “3.D” mean. Corrected in updated SOW.
17. Specifications are listed in Appendix B of the SOW but not provided. Information
Requested: Will the Government provide the specifications listed at a later date?
Information is in Contractor CD. PZ to provide the contractors with the contractor CD.
18. Per SOW 4.4.2 and 4.4.3, both station lists are titled "southbound lane," and several ranges overlap (0+10-0+50 / 0+50-0+75; 1+50-1+75 / 1+65-1+80; 6+00-6+25 / 6+15- 6+50;
14+50-14+75 / 14+75-14+80). Please confirm: (a) Whether SOW 4.4.3 is intended to read
"northbound lane." (b) Whether overlapping ranges in opposite lanes are intended as full-width
(both-lane) panel replacements. Pavement repairs overlap on both lanes. Corrections have been made to the updated SOW.
19. Per Drawings G-01 through DT-02 (each title block marked "35% DESIGN"), SOW footer
"WOSB Preliminary (35%) SOW," SOW 3.2.1.2, SOW 3.5, and Appendix B Section 01 33
16.00 10, Design Data (Design After Award), the solicitation drawings are issued at 35% design. Please confirm: (a) Whether the Contractor is required to complete the design to
100% (design-build), or whether the Government will issue a 100% / Issued-for-Construction set before award or NTP. (b) If the Contractor completes the design, the required design submittal stages (e.g., 65%, 95%, 100%), the Government review period for each in calendar days, and whether that review time is excluded from the Contractor's performance period. (c) Whether the
Government-furnished design elements shown in the 35% set (pavement section C-12/A-7-2, PCC repair section C-10.1, dowel detail C-20a, storm details D-3/D-6) remain the Government's design responsibility, with any deficiency in them compensable under FAR 52.243-4. A.) No design is required by the contractor. B.) NA due to no design required. C.) The contractor is to build per the details in the drawings set.
20. Per SOW 1.1, the Contractor must provide a "complete, fully operating, and functioning system," while the same paragraph states that Government-furnished dimensions, utility locations, and data "are to be considered approximate and shall be field verified by the
Contractor." Please confirm that a material variance between the Government-furnished data (station limits, paved widths, existing pavement sections, utility locations, repair areas) and actual field conditions constitutes a Differing Site Condition under FAR 52.236-
2, and that the field-verification requirement does not transfer quantity risk to the
Contractor. All differing site conditions will be evaluated through the RFI process and final determination will be by the Contracting Officer.
21. Per SOW 4.4.2, 4.4.3 and 4.4.5 ("All locations are approximate and will be field verified") and Drawings C-08, C-09 and C-10, the SOW identifies the full-depth repairs by station range only, while the drawings show 18 individual spot repairs with labeled areas totaling
5,442 SF. Please confirm: (a) That the repair areas labeled on Drawings C-08 through C-10
(5,442 SF total) are the basis for pricing, and that the SOW station ranges are for location only. (b) Whether the Government will accept a unit price per SF of full-depth PCC repair to adjust for field-verified repair areas above or below 5,442 SF. (c) Whether final repair limits will be marked jointly by the Government QA Inspector and Contractor before saw cutting.
A.) Confirmed for basis of pricing and location only. B.) Non-concur, the government will only accept a lump sum pricing with line item breakouts. C.) The contractor will be responsible for marking out the limits of the 18 individual spot repairs on industrial blvd.
Prior to saw cutting, a meeting can be held with the government to verify the limits of each spot.
22. Per SOW 4.4.2 and 4.4.3, both station lists are titled "southbound lane," and several ranges overlap (0+10-0+50 / 0+50-0+75; 1+50-1+75 / 1+65-1+80; 6+00-6+25 / 6+15-
6+50; 14+50-14+75 / 14+75-14+80). Please confirm: (a) Whether SOW 4.4.3 is intended to read "northbound lane." (b) Whether overlapping ranges in opposite lanes are intended as full-width (both-lane) panel replacements. Corrected in amended SOW.
23. Per SOW Appendix A, Drawing Index, several SOW references do not match the drawing set: SOW 4.2.1 and 4.4.1 cite "CO2, C03, C04" for Industrial Blvd repairs (indexed as C-08 to C-10); SOW 4.2.1 cites Detail "C-20," which is not in the set (C-20a is on DT-02); SOW
4.3.2 cites "C08-C014" for Perimeter Dr grading; SOW 4.3.5.1 and 4.4.4.1 cite "C05 & C06"
(Perimeter demo plans) for pavement markings; and SOW 4.3.5.2 cites phasing "described in 3.D," which does not exist. Please confirm: (a)The governing sheet and detail for each of the references listed above. (b) Whether Detail C-20 exists and, if so, provide it. Corrected in Amended SOW.
24. Per Drawing C-09 ("Curb-less gutter, 20 LF" and "New drainage flume") and Drawing C-10
("Install PCC collar around SD inlet" and "Install drainage flume"), these items are shown on Industrial Blvd but are not listed in SOW 4.2 or 4.4. Please confirm: (a) Whether each item is within the scope of this Order. (b) The station, dimensions and governing detail (C-
14, C-22, D-6 or other) for each item. Corrected in updated SOW
25. Per SOW Appendix B, Specifications, the following sections are listed but no corresponding work is shown on the drawings or described in the SOW: 32 01 13, 32 01 14, 32 01 16 (Cold
Milling), 32 01 17, 32 01 17.62 (Fabric Reinforcement), 32 01
22 (Bituminous Rejuvenation), 32 11 11 (ATPB Drainage Layer), and 32 92 19 (Seeding).
Please confirm: (a) Which of these sections apply to this Order and to what work. (b) That the specification files referenced in SOW 5.2 as "included on the attached CD" will be issued to offerors, since they were not included in the solicitation attachments received. They are not all necessarily required but are on the SOW for reference in case they are needed. These are included depending on the means and methods of the contractor.
26. Per Attachment 10, Submittal Register, lines 51-59 reference Sections 32 12 15 (Hot Mix
Asphalt) and 32 13 11 (Portland Cement Concrete), which are not listed in SOW Appendix
B; Appendix B instead lists 32 13 14 (Pavement, Non-Airfield). The register also contains no entries for 33 40 00, 03 30 00, 03 20 00.00 10, 32 13 74 / 32
01 19, 32 16 13 (beyond reports), or 10 14 00.10. Please confirm: (a) Which specification sections govern HMA and PCC materials, mix design, placement and acceptance. (b)
Whether the Contractor should price the submittals required by the omitted sections, or whether those sections do not apply. These have been added to the updated SOW.
27. Per SOW 4.1.1(1)-(2), 4.1.2 and 4.3.4, and Drawings C-02, C-04 and C-07, the Perimeter Dr removal and paving limits conflict: PCC demolition is 0+50-8+50 (SOW) versus 0+50-6+75 plus AC overlay/PCC 6+75-8+50 (C-02) versus 0+50-6+85 (C-04); AC demolition ends at
28+00 while PCC demolition runs 27+00-28+50; and new AC runs to 28+50 while C-07 notes "Tie into existing concrete (end of new AC pavement)." Please confirm: (a) The existing pavement type and removal limits between Sta. 6+75 and 8+50 and between Sta.
27+00 and 28+50. (b) The station of the end of new AC pavement at the east tie-in. a.) Any asphalt and concrete to be removed within these limits. b.) an exact station is unknown due to the tie-in line crossing several stations from west to east 27+00 – 28+00. Asphalt will need to transition to concrete on Industrial Drive. See C-01 note 1.
28. Per Drawing C-12, the Perimeter Dr typical section shows four 12 ft lanes (48 ft) plus 1 ft-4
in. gutters, while SOW 2.3 describes each phase as two lanes on one 24 ft half, Drawings
C-06/C-07 show a two-lane marking layout, and the C-02 aerial appears narrower than 48
ft. SOW 4.3.5.3 also references a "turn lane" that is not shown. Please confirm: (a)The existing and proposed edge-of-pavement to edge-of-pavement width of Perimeter Dr.
Pavement width varies. The cross section is for uniformity. (b) The final number of lanes and the location and length of any turn lane. The number of lanes for perimeter rd. is 2 traffic lanes and 2 shoulders. See sheets C-6 and C-7. Minimum width of traffic lane to be
12 ft, shoulders can vary depending on the width of any given point in the road.(c)
Whether any widening beyond the existing pavement edge is intended and, if so, the associated earthwork limits. Pavement varies. The cross section is for uniformity.
29. Per Drawing C-12 and Detail A-7-2 ("6 in. Modified Subgrade ... CBR > 8, PI <
14") and SOW Appendix B Section 32 11 29, Lime-Stabilized Subgrade, the stabilization criteria are performance-based but the agent and rate are not stated. Please confirm: (a) The stabilizing agent- (hydrated lime, quicklime, lime kiln dust, fly ash or cement) and the application rate by dry weight to be priced. Means and methods, equivalent to detail. (b) Who is responsible for the stabilization mix design and the associated laboratory testing. Contractor. c) Whether additional agent or depth required for the native soil to achieve PI < 14 and CBR > 8 beyond the priced rate will be treated as a change under FAR 52.243-4. Differing site conditions will be evaluated through the RFI process. Final determination will be made by the Contracting Officer.
30. Per Drawing C-12 and Detail A-7-2, the base course is called out as "6 in. Stabilized
Aggregate Base," while SOW Appendix B lists both 32 11 23, Aggregate Base Course, and 32 11 11, Asphalt Treated Permeable Base. Please confirm whether the base is an unbound aggregate base per 32 11 23 (and which ODOT aggregate type), or a cement-, asphalt- or otherwise-stabilized base, and the stabilizing agent and rate if stabilized.
Means and methods of contractor. Stabilized agg base is compaction of agg base stated in the standard detail C-10-1.
31. Per Detail A-7-2 Notes 2-4 (aggregate base and modified subgrade at 95% Modified
Proctor; fill below at 90% Standard) and Detail C-10.1 Notes 2-3 (subgrade at 95%
Standard; fill below at 80% Standard), the compaction criteria differ between Perimeter Dr and Industrial Blvd. Please confirm: The governing compaction criteria and test method
(ASTM D1557 or D698) for each layer of each section. Whether the 80% value in Detail C-
10.1 Note 3 is intended to read 95%. Perimeter dr. details are for asphalt. Industrial rd. is for concrete pavement repairs.
32. Per SOW 1.1 and SOW 5.4, no geotechnical report, soil borings or subgrade data were provided for 2,800 LF of full-depth roadway replacement and 18 full-depth PCC repairs.
Please confirm: Whether a geotechnical report, boring logs or pavement evaluation exists for Perimeter Dr or Industrial Blvd and, if so, provide it. That removal and replacement of unsuitable subgrade below the design section, as directed by the Government, will be paid as a Differing Site Condition under FAR 52.236-2. Whether the Government will accept a unit price per CY for unsuitable-material undercut and select-fill replacement. These will not be provided as none exists. The government will not accept a CY price. We will only accept a lump sum price with line-item breakouts. Any differing site conditions will be evaluated through the RFI process. Final determination will be made by the contracting officer.
33. Per Drawing C-02 ("Asphalt overlay and concrete pavement demo 6+75 to 8+50") and SOW
4.1.1 and 4.1.2, the existing pavement thicknesses and base layers to be removed are not shown. Please confirm: The existing pavement section (AC thickness, PCC thickness, base type and thickness) for Perimeter Dr from Sta. 0+50-8+50, 8+50-27+00 and 27+00-28+50, and for Industrial Blvd. Whether as-built drawings or core data referenced in SOW 5.4 for these roads will be issued to offerors before proposal submission. That removal of pavement thickness in excess of the Government-furnished section will be treated as a
Differing Site Condition under FAR 52.236-2. Asbuilts are provided in the contractor CD.
No core data available. The government expects all removal to be incorporated into the initial proposal. Any differing site conditions will be evaluated through the RFI process. The contracting officer will make any final determinations.
34. Per Detail C-10.1 (DT-02), the full-depth repair section shows "8 in. PCC" over "6 in.
Scarified & Compacted Subgrade," with a "6 in. Stabilized Aggregate Base" label on the same detail. Please confirm: Whether the PCC repair includes a 6 in. aggregate base course or is placed directly on scarified and compacted subgrade. Whether the repair thickness is 8 in. regardless of existing slab thickness, or is to match the existing slab where it exceeds 8 in. The required PCC strength (flexural or compressive), maximum w/c ratio, and any minimum opening-to-traffic strength or time. Confirmed aggregate base is to be placed on top of the scarified and compacted subgrade per detail C-10.1. Match existing surrounding slab, average slab thickness is approximately 8”. See specifications for PCC strength, w/c ratio, etc.
35. Per Detail C-20a (DT-02), dowels are 3/4 in. diameter by 16 in. minimum, steel or GFRP, at 12 in. on center and held 30 in. from corners, while SOW 3.6.2(3) cites UFC 3-250-01
Tables 8.2 and 8.3 for dowel size and spacing. Please confirm: Corrected on updated SOW
36. Whether Detail C-20a governs, or whether dowel diameter, length, spacing and edge distance are to be selected by the Contractor from UFC 3-250-01 Tables
8.2/8.3 for the 8 in. slab. Whether steel dowels must be epoxy-coated, and the required epoxy anchoring adhesive and embedment depth for dowels drilled intoexisting slabs.
Whether tie bars are required at longitudinal joints with adjacent existing panels, since none are shown. Corrected table numbers on updated SOW
37. Per SOW Appendix B Sections 32 01 19 and 32 13 74, joint sealing is specified, but no joint layout or sealant type is shown on Details C-10.1 or C-20a. Please confirm: The required sealant type and joint reservoir dimensions for the perimeter joints of each
Industrial Blvd repair. Whether cleaning and resealing of existing joints adjacent to the repair panels is within scope. See Tinker specifications for joint sealant criteria.
38. Per Drawing C-07 ("Tie into existing concrete (end of new AC pavement)") and SOW 4.1.1(1)-
(2), new AC pavement abuts existing PCC at the west and east ends of the project, but no transition detail is provided. Please provide the required AC-to-PCC transition detail (butt joint, sleeper slab, or tapered transition) and confirm the saw-cut limits at each tie-in.
Contractor means and methods, follow UFC 3-250-01.
39. Per SOW 4.1.3(a), 4.3.1.1 and 2.3 Phase 1/2 Sub-task 1 ("Replace the 36 in. storm drain structure at Sta. 17+00 and lay new pipe to 5 ft from the perimeter fence") and Drawings
C-06/C-07 (Details D-3 and D-6), the pipe and structure are not defined; Detail D-3 Note
3 lists typical Tinker sizes of 12-24 in. only. Please provide: The new pipe diameter, material and class (e.g., RCP Class III or IV), and length from Sta. 17+00 to the termination point. The upstream and downstream invert elevations and slope. Whether
"36 in." refers to the pipe diameter or to the structure, and the type and dimensions of the replacement structure. The connection method to the existing pipe that remains beyond the 5 ft termination point, and the size and material of that existing pipe.
Size is stated in the SOW, utilized spec…