Att4_100209_Submittal_Register_Rev1.pdf

PDF 143 KB Posted

Attached to
WWYK100209-Repair Perimeter Dr and Industrial Blvd
Solicitation number
FA813727R0003
Issued by

About this file

This is a Submittal Register for a construction contract at Tinker Air Force Base for the repair of Perimeter Drive and Industrial Boulevard (Project WWYK100209). The document establishes a comprehensive list of 62 required submittals organized by construction phase and discipline, with specific paragraph references, approval authorities, and scheduling requirements.

Preconstruction submittals include health and safety plans, construction phasing plans, airfield construction waivers (due by the 5th of each month for processing), FAA Form 7460-1, restoration plans, storm water pollution prevention plans, spray painting plans, construction debris analysis plans, tree planting/removal permits, baseline construction schedules (due within 10 days of Notice to Proceed), submittal registers, and quality control plans. Certificate submittals encompass welding permits, safety meetings, FOD awareness training, fire ant compliance agreements, monthly hazardous material usage reports (1st week of each month), monthly debris management reports (1st week of each month), and monthly schedule updates. Product data and test report submittals cover affirmative procurement documentation, quality control documentation (weekly with progress reports), warranty letters, and safety data sheets. Closeout submittals require working as-built drawings (two electronic sets and two hard copies), record drawings (two electronic sets and one hard copy), and certifications of EPA and USDA designated items. Additional requirements include weekly contract progress reports using AF Form 3065, a traffic control plan compliant with SDDCTEA Pamphlet 55-17 and MUTCD, and extensive material testing and certification documentation for pavement work including excavation reports, compaction testing, aggregate base course sampling and field density tests, asphalt placement and mix design documentation, concrete mix design and strength testing, and pavement markings and sodding certifications.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

1 00 70 00 07 Certificates Welding, Cutting and Brazing Permit 1.4 G

2 00 71 00 01 Preconstruction Submittals Health and Safety Plan 1.3 G

3 00 71 00 01 Preconstruction Submittals Construction Phasing Plan 1.5 G

4 00 71 00 01 Preconstruction Submittals Airfield Construction Waiver 1.5 G

Must be turned in by the 5th day of the month to make that month Waiver Package. Provide editable form to the CO to be forwarded to Community Planning. Allow 45 days for processing.

5 00 71 00 01 Preconstruction Submittals FAA Form 7460-1 1.5.3 G

6 00 71 00 07 Certificates Safety Meetings 1.3

7 00 71 00 07 Certificates FOD Awareness and Prevention Training 1.4

8 00 72 00 01 Preconstruction Submittals Restoration Plan 1.3.2 G

9 00 72 00 01 Preconstruction Submittals Storm Water Pollution Prevention Plan 1.3.3.2 G

10 00 72 00 01 Preconstruction Submittals AF Form 3952 Chemical/Hazardous Material Request/Authorization 1.4 G

11 00 72 00 01 Preconstruction Submittals Spray Painting Plan 1.9 G

12 00 72 00 01 Preconstruction Submittals Environmental Management System Awareness Training 1.1

13 00 72 00 03 Product Data Affirmative Procurement Documentation or Green Statement 1.3.10 G Provide only one. Reference specification for additional information

14 00 72 00 07 Cerificates Fire Ant Federal Compliance Agreement or state phyto-sanitary certificate 1.3.4.1

15 00 72 00 07 Cerificates Monthly Hazardous Material Usage Report 1.4 G Provide 1st week of each month during construction

16 00 72 00 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data Sheets 1.4

17 00 72 00 11 Closeout Submittals Notice of Termination (ODEQ Form 640-572) 1.3.3.2 G

18 00 72 00 - Attch 5 01 Preconstruction Submittals Construction Debris Analysis Plan 1.2.3 G

19 00 72 00 - Attch 5 07 Certificates Monthly Debris Management Report 2 G Provide 1st week of each month during construction

20 00 72 00 - Attch 11 01 Preconstruction Submittals Tree Planting/Removal Permit 1.1 G

21 00 72 00 - Attch 11 01 Preconstruction Submittals Tree Protection Plan 2.1 G

22 01 32 16.00 20 01 Preconstruction Submittals Baseline Construction Schedule 1.2 G Provide within 10 days of NTP.

23 01 32 16.00 20 07 Certificates Monthly Updates 1.4 Provide 1st week of each month during construction, or as directed by CO

24 01 32 16.00 20 07 Certificates 3-Week Look Ahead Schedule 1.6 Provide weekly with the Contract Progress Report

25 01 33 00 01 Preconstruction Submittals Submittal Register 1.8 G

26 01 45 00.00 10 01 Preconstruction Submittals Quality Control (QC) Plan 3.2 G

27 01 45 00.00 10 06 Test Reports QC Documentation 3.9 Provide weekly with the Contract Progress Report

28 01 50 00 01 Preconstruction Submittals Request for Contractor Staging Area 1.1 G

29 01 50 00 01 Preconstruction Submittals Photographic Record 1.3

30 01 78 00 03 Product Data Warranty Letter 1.7.1

31 01 78 00 11 Closeout Submittals Working As-Built Drawings 3.1 G Provide (2) electronic sets (optical media) and

(2) hard copies

32 01 78 00 11 Closeout Submittals Record Drawings 3.3 G Provide (2) electronic sets (optical media) and

(1) hard copy

33 01 78 00 11 Closeout Submittals Certification of EPA Designated Items 2.3 G

TITLE: WWYK100209

SUBMITTAL REGISTER

JOB NAME: REPAIR PERIMETER DR & INDUSTRIAL BLVD

LOCATION: Tinker AFB

CONTRACT NO:

CONTRACTOR:

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES APPROVING AUTHORITY

Submittal Register_v3_03/07/22

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES APPROVING AUTHORITY

34 01 78 00 11 Closeout Submittals Certification Of USDA Designated Items 2.4 G

35 SOW 07 Certificates Contract Progress Report(s) 2.4 G Provide weekly throughout life of contract.

Utilize AF Form 3065, Contract Progress Report (or equal)

36 SOW Traffic Control Plan BMTE in accordance with SDDCTEA Pamplet 55-17 and MUTCD.

Provide a traffic plan for each phase of construction.

31 23 06

Excavation and Preparation of Subgrade Reports 1.2

31 23 06

Excavation and Preparation of Subgrade Compaction 3.9.2.2

39 32 11 23 9 Aggregate Base Course Reports 1.2

40 32 11 23 9 Aggregate Base Course Sampling and testing 1.3

41 32 11 23 9 Aggregate Base Course Field Density Tests 1.3

42 32 17 23 3 Pavement Markings Product Data 1.3.1

43 32 92 23 7 Sodding Certificates, Fertilizer 1.2

44 32 92 23 7 Sodding Certificates, Sod 1.2

45 32 11 29 3 Lime- Stabilization Product Data 1.3.1

46 32 11 29 4 Lime- Stabilization Samples 1.3.1

47 32 11 29 6 Lime- Stabilization Tests Reports 1.3.1

48 32 11 29 7 Lime- Stabilization Certificates 1.3.1

49 32 11 29 9 Lime- Stabilization Manufacturer Reports 1.3.1

50 32 11 29 10 Lime- Stabilization Operation Data 1.3.1

51 32.12.10.2 9 Tack Coat Reports 1.2

52 32 12 15 9 Hot Mix Asphalt Placement Plan 1.3

53 32 12 15 9 Hot Mix Asphalt Product data, Mix Design 1.3

54 32 12 15 9 Hot Mix Asphalt Tests Reports 1.3

55 32 12 15 9 Hot Mix Asphalt Samples 1.3

56 32 13 11 9 Portland Cement Concrete General 1

57 32 13 11 9 Portland Cement Concrete Product Data 1.2.2

58 32 13 11 9 Portland Cement Concrete Concrete mix design 1.2.3.1

59 32 13 11 9 Portland Cement Concrete Strength test 1.3.2.2

60 32 13 11 9 Portland Cement Concrete Materials 1.3.1

61 32 13 14 9 Pavement, Non-Airfield Reports 1.2

62 32 16 13 9 Curb and gutters Reports 1.2