This is a Pre-Bid Request for Information (RFI) Q&A document for federal contract WWYK250173, addressing clarifications on a roofing and insulation retrofit project for Building 5703.
The project involves removal and replacement of existing roof systems across multiple sections, installation of new EPDM roofing on Section 1, retrofit metal roof systems on Sections 2 and 3 with constant slope and flashing, replacement of insulated wall panels on north and south walls, and installation of mechanical curbs. Key clarifications provided include: as-builts must be requested from the Contracting Officer; roof demolition scope is defined by drawing sheet R-101, with original 1963 roof structure remaining below Roof Sections 2 and north end of Section 3, while the 1979 south addition below the south end of Section 3 is to be demolished; wall panel specifications are Concept Design level, referencing existing conditions in as-builts and SOW section 5.4.4; all major roof vents and penetrations shown on drawings remain active; and the existing structure is a pre-engineered metal building (PEMB) with metal deck roofing or standing seam. The Contractor is responsible for full design-build engineering services including structural calculations, wind uplift analysis, thermal performance, shop drawings, and code compliance. Materials listed in section 2.8 of the Environmental Management Survey have tested positive for asbestos or lead-based paint. As-built submittals must be provided in fully XREFed AutoCAD format with short file names to prevent unzipping issues, plus PDF copies. The proposal due date will not be extended. Government responses are binding and incorporated into the construction documents.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WWYK250173 Pre Bid RFI Q&A Number Question Answer Answer P.O.C Notes
1 Will As-builts be provided? As-builts should be included, request from CO. -LL
Which is correct? Per 5.1 – 1 Roofing Demolition – section 2&3 “remove to the original metal roof system” or 5.5.1 Roof Structure (1) “Demolish and remove roof deck and retrofit structure from the 1979 reroofing project. The original roof from 1963 and the additional roof from 1977 and support structure are to remain.”
Refer to as-builts. Refer drawing sheet R-101 for roof section locations: The original metal roof and structure is below Roof Section 2 and the north end of Roof Section 3. The 1979 south addition is below the south end of Roof Section 3. - TMD
Per 5.4 (2) “Replace the insulated wall panels on north and south walls” – please provide more specifications, i.e., profile, thickness, and R-value.
This is Concept Design. Refer as-builts for existing profile and manufacturer. Refer SOW 5.4.4 for Concept design. - TMD
4 Will all of the roof vents and other penetrations remain active or will any be discontinued?
All of the major items called out on the drawings are active and will remain. Any other penetrations not called out on the drawings should be evaluated to remain or be demolished by the DOR. - QAG
5 What is the existing roof framing structure and what is the "existing metal deck"?
Refer to as-builts. Structure is a PEMB. Metal deck is roof deck or standing seam. -LL
As our firm was brought into the BOA a week after the posting of this solicitation, we would like to respectfully request that the proposal due date be extended one week.
The proposal due date will not be changed for this reason. - TMD
Per SOW paragraph 1.1 GENERAL and project drawings sheets G-101, C-101, A-101, R-101, and M- 101 (including all keyed demolition and new-work notes), do the provided drawings constitute the complete final design such that the Contractor’s responsibility is limited to constructing the work strictly in accordance with those drawings and the SOW, or is the Contractor required to perform full designbuild engineering services (structural calculations, wind uplift, thermal performance, shop drawings, delegated design elements, code/DoD/AF compliance, etc.)? Contractor requests explicit written confirmation that the Government’s response to this RFI is binding for the duration of the contract.
Yes, as per the documents listing in question 7 and other requirements per the SOW document, the Contractor is required to perform full designbuild engineering services (structural calculations, wind uplift, thermal performance, shop drawings, delegated design elements, code/DoD/AF compliance, etc.). Note:
the Government responses are already part of the construction documents - TMD
Per SOW paragraph 1.7 BIOENVIRONMENTAL REGULATIONS and submittal register preconstruction submittals under 00 72 00 and Attachments 2, 3, and 3a (asbestos/lead abatement procedures, air sampling, waste disposal, etc.), has the Government performed or will the Government provide a comprehensive asbestos/lead/hazardous materials survey for the existing roof, insulation, wall panels, and associated materials on Building 5703 prior to NTP? Contractor requests explicit written confirmation that the Government’s response to this RFI is binding for the duration of the contract.
The materials listed in section 2.8 Environemental Management Survey have already been tested and confired positive for either asbestos or lead base paint.
Per specification section 01 78 00 (Closeout Submittals) and the submittal register requirements for Working As-Built Drawings and Record Drawings, will the Government accept as-built/record drawings furnished only in native editable AutoCAD .dwg format (or Government-approved equivalent), fully layered and XREFed, in addition to any PDF copies?
Contractor requests explicit written confirmation that the Government’s response to this RFI is binding for the duration of the contract.
We require as builts submittals to be in AutoCAD format (completely XREFed) and PDF copies. Also file names for AutoCAD files should be as short as possible to avoid any issue in unzipping zip files.
Number Question Answer Answer P.O.C Notes
Per project drawing sheet R-101 keyed notes 1–6 (removal of existing roofs and installation of new EPDM roof on Section 1, new retro-fit metal roof system on Sections 2/3 with constant slope, flashing, gutters, south entrance canopy, and mechanical curbs), please provide or confirm the complete performance criteria, material specifications (or approved equals), warranty requirements (duration and type), insulation R-values, fastening/attachment details, drainage modifications, and installation standards required for the new roofing systems.
Contractor requests explicit written confirmation that the Government’s response to this RFI is binding for the duration of the contract.
This is Concept Design. Refer as-builts for existing conditions. Refer SOW 5.2 for Concept design. TMD