March 3, 2020 CLARIFICATION QUESTIONS & ANSWERS-Part III

FA8125-20-R-0011

1) In the updated SOW section 1.2, the last sentence reads: The contractor shall be ISO 9000 compliant. Section 7.6 states the contractor shall be ISO 9001 certified. Please clarify?

SOW has been updated. Please see attached updated SOW.

2) Section 1.2 in the updated SOW states all of the major structure of the stand sections to be powder coated. Would the government consider a skydrol resistant 2-part epoxy primer and 2-part epoxy topcoat as an alternative?

The powder coated reference has been replaced with “painted or otherwise coated” in the SOW.

3) Section 7.8 states the period of performance is 12 months from award date. The solicitation states stands 2 and 3 to be delivered on or before 26 Feb 2021. Since we are now past Feb 21, 2020 will this or all three CLINs be updated in the solicitation to reflect revised delivery dates?

Period of performance is 12 months from award date to acceptance of all three stand sets.

4) Should the contractor complete the technical evaluation form or is that for Government use?

Contractors are not required to fill out technical evaluation criteria form. All proposals must however be detailed enough to address how your company successfully plans on meeting these requirements. Please refer to FAR 52.212-2 for more details.