CSD__RFP__Inquiry_and_Comment_Tracker_12_Apr__16.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
Constant Speed Drive Performance Based Logistics
Solicitation number
FA8109-15-R-0001
Issued by

About this file

Responses to questions

View the file

Other files

File Type Posted
FA8109-15-R-0001-0003.pdf PDF
FA810915R0001_______0002.pdf PDF
GFP_Attachment_1_5_Apr_16.pdf PDF
FA8109-15-R-0001-0001.pdf PDF
FA8109-15-R-0001_EZ_Source_PPI_Tool.accdb —
CSD_PBL_Preproposal_Conference_Meeting_Minutes.pdf PDF
HO4-Implementation_Agreement.pdf PDF
SPI-015028980.pdf PDF
HO2-Contract_Metric_Price_Adjustment.pdf PDF
HO5-Contract_Exit_or_Termination_for_Default_Consideration.pdf PDF
SPI-000866695.pdf PDF
AFMC-158-Packaging-Requirements.pdf PDF
DI-MGMT-81900-DMSMS-Health-Analysis-Report.pdf PDF
Rose_State_Professional__Training_Center-Map.pdf PDF
DI-MGMT-80004A-T-Management-Plan-Tailoring.pdf PDF
DI-MISC-81832-T-Counterfeit-Prevent-Tailoring.pdf PDF
DI-ILSS-80727-T-GFM-by-NSN.pdf PDF
SPI-001033554.pdf PDF
SPI-000722292.pdf PDF
FA810915R0001.pdf PDF
GFP_Attachment_2_23_Nov_15.pdf PDF
DI-QCIC-81891-T-ATR-Tailored.pdf PDF
Pricing_Matrix_PBL_for_CSD_22_OCT_15_Protected.xlsx XLSX spreadsheet
GFP_Attachment_1_7_Jan_16.pdf PDF
DI-MGMT-80368A_and_80368A-T.pdf PDF
Section_M-Evaluation_Factors_For_Award.pdf PDF
HO3-Partnership.pdf PDF
Statement_Of_Work.pdf PDF
Preproposal_Conference_Charts.pptx PPTX presentation
HO1-Air_Force_Payment_Methods_and_Limitation_of_Government_Liability_Clause.pdf PDF
SPI-011416018.pdf PDF
Section_L-Instructions_To_Offerors.pdf PDF
Contract_Data_Requirements_List.pdf PDF
CSD_PBL_Workshare_IA_pending_Source_Selection_(1_Sep_15).pdf PDF
DI-MISC-80704-T-Part-Usage-Report-Tailoring.pdf PDF
SPI-011482109.pdf PDF
CSD_Inquiry_and_Comment_Tracker_3_Feb.pdf PDF
CSD_Inquiry_and_Comment_Tracker_12_Jan_16.pdf PDF
GFP_Attachment_1_7_Jan_16.pdf PDF
Synopsis_(Revised_23_Oct_15)_-_CSD_PBL.pdf PDF
Synopsis_-_CSD_PBL.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1 Ref CSD RFP Inquiry or Comment Tracker

13/28/2016: Regarding attachment 3 (entitled CSD DEMANDS...) to the SOL released 4 FEB, please define the values provided under the title, "DEPOT REP GENS." We need to know exactly what these values represent. For example, in FY11, for CSD ending in 2295, Base NRTS demand total was 90; Depot Rep Gens was 19. What does "19" represent?
Response: Depot Reparable Generations (DepRepGens) represents demands generated at depot repair facilities from Programmed Depot Maintenance, Engine Overhaul and Next Higher Assembly repairs. For Constant Speed Drives this includes aircraft and engine overhauls performed at the depots. The depot activity finds the CSD/IDG unserviceable, removes it, turns it into supply and places a demand on the supply system for a serviceable part. This demand is filled from serviceable shelf stock. The DepRepGen data is included to show that a small number of demands for CSDs are generated at the aircraft and engine depots. These demands affect the RO percentage.
23/28/2016: Will the government provide the Hamilton Sundstrand Military Maintenance Bulletin (MMB) 1452 to potential offeror’s for review and evaluation?
Response: No, The Hamilton Sundstrand Military Maintenance Bulletin (MMB) 1452 was identified by Hamilton Sundstrand as "PROPRIETARY". The Government will not provide the MMB to potential offerors. However a revised material list reflecting the old to new piece part p/n, quantity and replacement factors has been developed and is posted on FBO within technical data package labeled FD20301502069 04-01-16.
33/28/2016: Is there an anticipated F-16 C/D CSD reliability improvement anticipated through the implementation of the MMB? If so, what is the magnitude of the improvement in Mean Time Between Failure(MTBF)?
Response: AF cognizant engineering has identified that the MMB kit parts are 50% more reliable. The magnitude of CSD MTBF is unknown at this time.
43/28/2016: Are there internal CSD components that are impacted by the MMB? If so, what are they?
Response: Yes, A revised material list reflecting the old to new piece part p/n, quantity, and replacement factors has been developed and is posted on FBO within the technical data package labeled FD20301502069 04-01-16.
53/28/2016: What is the availability any new components?
Response: The MMB 1452 upgrade consist of two part's kits (174-55 and 174-44). -44 piece parts are stock listed and available. The AF will provide sufficient quantiles of -55 kits via GFM to completed the F16 C/D upgrade with planned actions for piece part stock listing.
63/28/2016: Related to any new internal components, are there projected replacement percentages and will they be provided?
Response: Yes, there are projected replacement percentages. A revised material list reflecting the old to new piece part p/n, quantity, and replacement factors has been developed and is posted on FBO within the technical data package labeled FD20301502069 04-01-16.
73/28/2016: Is there an impact on Air Force Managed Material and DLA drawdown requirements?
Response: Yes for AF managed material the 174-55 Kit will be added to GFM, No impact to DLA drawdown requirements
83/28/2016: What is the time frame for issuance of a TCTO and/or TO update?
Response: The time frame for TCTO and/or TO update is Jan 2017
93/28/2016: Will this MMB have an impact on the Air Force Ceiling?
Response: Yes, the Air Force Ceiling will be reduced approximately $6.1M as a result of additional Air Force GFM provided (Kit P/N 174-55). An RFP amendment -0002 addressing the impacts of the MMB has been issued.
103/28/2016: We are planning to hand-deliver the subject proposal to Tinker AFB by one of our employees prior to the response date. However, this employee does not have a Contractor ID card. Can you please let me know the proper procedures for obtaining access to Tinker AFB in order for our employee to complete the proposal delivery? Please forward any documents required to be completed.
Response: Instead of arranging access to the base, the PCO will meet your employee outside the base. The most convenient place is the small parking lot to the right of Lancer Gate, on Douglas Boulevard. Have your employee contact the PCO to arrange a time and for further directions if needed.
113/28/2016: Regarding documentation of hand-delivery; upon proposal receipt we ask that you please give us a written receipt with date/time of accepting our proposal.
Response: The PCO is willing to document hand-delivery of a proposal through a written receipt. The offeror should present two copies of the desired receipt. The PCO will sign both as originals and retain one for the government’s records.