Table 1 Ref CSD RFP Inquiry or Comment Tracker
| 1 | 3/28/2016: Regarding attachment 3 (entitled CSD DEMANDS...) to the SOL released 4 FEB, please define the values provided under the title, "DEPOT REP GENS." We need to know exactly what these values represent. For example, in FY11, for CSD ending in 2295, Base NRTS demand total was 90; Depot Rep Gens was 19. What does "19" represent? |
| Response: Depot Reparable Generations (DepRepGens) represents demands generated at depot repair facilities from Programmed Depot Maintenance, Engine Overhaul and Next Higher Assembly repairs. For Constant Speed Drives this includes aircraft and engine overhauls performed at the depots. The depot activity finds the CSD/IDG unserviceable, removes it, turns it into supply and places a demand on the supply system for a serviceable part. This demand is filled from serviceable shelf stock. The DepRepGen data is included to show that a small number of demands for CSDs are generated at the aircraft and engine depots. These demands affect the RO percentage. |
| 2 | 3/28/2016: Will the government provide the Hamilton Sundstrand Military Maintenance Bulletin (MMB) 1452 to potential offeror’s for review and evaluation? |
| Response: No, The Hamilton Sundstrand Military Maintenance Bulletin (MMB) 1452 was identified by Hamilton Sundstrand as "PROPRIETARY". The Government will not provide the MMB to potential offerors. However a revised material list reflecting the old to new piece part p/n, quantity and replacement factors has been developed and is posted on FBO within technical data package labeled FD20301502069 04-01-16. |
| 3 | 3/28/2016: Is there an anticipated F-16 C/D CSD reliability improvement anticipated through the implementation of the MMB? If so, what is the magnitude of the improvement in Mean Time Between Failure(MTBF)? |
| Response: AF cognizant engineering has identified that the MMB kit parts are 50% more reliable. The magnitude of CSD MTBF is unknown at this time. |
| 4 | 3/28/2016: Are there internal CSD components that are impacted by the MMB? If so, what are they? |
| Response: Yes, A revised material list reflecting the old to new piece part p/n, quantity, and replacement factors has been developed and is posted on FBO within the technical data package labeled FD20301502069 04-01-16. |
| 5 | 3/28/2016: What is the availability any new components? |
| Response: The MMB 1452 upgrade consist of two part's kits (174-55 and 174-44). -44 piece parts are stock listed and available. The AF will provide sufficient quantiles of -55 kits via GFM to completed the F16 C/D upgrade with planned actions for piece part stock listing. |
| 6 | 3/28/2016: Related to any new internal components, are there projected replacement percentages and will they be provided? |
| Response: Yes, there are projected replacement percentages. A revised material list reflecting the old to new piece part p/n, quantity, and replacement factors has been developed and is posted on FBO within the technical data package labeled FD20301502069 04-01-16. |
| 7 | 3/28/2016: Is there an impact on Air Force Managed Material and DLA drawdown requirements? |
| Response: Yes for AF managed material the 174-55 Kit will be added to GFM, No impact to DLA drawdown requirements |
| 8 | 3/28/2016: What is the time frame for issuance of a TCTO and/or TO update? |
| Response: The time frame for TCTO and/or TO update is Jan 2017 |
| 9 | 3/28/2016: Will this MMB have an impact on the Air Force Ceiling? |
| Response: Yes, the Air Force Ceiling will be reduced approximately $6.1M as a result of additional Air Force GFM provided (Kit P/N 174-55). An RFP amendment -0002 addressing the impacts of the MMB has been issued. |
| 10 | 3/28/2016: We are planning to hand-deliver the subject proposal to Tinker AFB by one of our employees prior to the response date. However, this employee does not have a Contractor ID card. Can you please let me know the proper procedures for obtaining access to Tinker AFB in order for our employee to complete the proposal delivery? Please forward any documents required to be completed. |
| Response: Instead of arranging access to the base, the PCO will meet your employee outside the base. The most convenient place is the small parking lot to the right of Lancer Gate, on Douglas Boulevard. Have your employee contact the PCO to arrange a time and for further directions if needed. |
| 11 | 3/28/2016: Regarding documentation of hand-delivery; upon proposal receipt we ask that you please give us a written receipt with date/time of accepting our proposal. |
| Response: The PCO is willing to document hand-delivery of a proposal through a written receipt. The offeror should present two copies of the desired receipt. The PCO will sign both as originals and retain one for the government’s records. |