| T-1A COMBS Pre-soliciation Conference 12 Oct 16 Questions/Answers | ||||
| Number | Document | Reference Material | Question | Answer |
| PSC - 1 | PWS | PWS, Attachment E | Will the Government consider providing frequencies and due dates for the reports (Contract Data Deliverables) identified in PWS Attachment E? | Yes, the PWS has been updated prior to the posting of the Formal RFP on FBO 9 Dec 16 |
| PSC - 2 | ITO | Instructions to Offerors (ITO), paragraph 2.2.3, Table 2.1, Proposal Organization |
ITO, paragraph 5.4, Volume Organization
| Will the Government consider revising ITO Table 2.1 to identify paragraph 5.4 as the appropriate reference for the Price volume (vol III) sections? | the ITO has been updated to reflect the correct section to identify the Price Volume prior to the posting of the Formal RFP on FBO 9 Dec 16 | |||
| PSC - 3 | ITO | ITO paragraph 3.2.5, Sub-factor 3: Small Business Participation Plan | Will the Government please provide Attachment 4, Small Business Subcontracting Requirements, called-out in ITO paragraph 3.2.5 to enable industry to fully develop Small Business strategies for this contract effort? | Documents were updated prior to the posting of the Formal RFP on FBO 9 Dec 16. |
| PSC - 4 | ITO |
PWS ITO paragraph 3.2.5, Sub-factor 3: Small Business Participation Plan states: “…As a minimum, the plan shall describe an approach and plan for subcontracting to Small Businesses in order to meet and maintain the 15% annual Small Business Subcontracting Requirement (by % of total contract value) required by the contract per solicitation, Attachment 4, “Small Business Subcontracting Requirements”. This is in addition to the required Small Business Subcontracting Plan (FAR 52.219-9). (PWS paragraph 1.3.15)
PWS 1.3.15, Small Business Participation Plan and Reporting states: “…The Contractor shall have a Small Business Participation Plan to manage subcontractor performance to meet and maintain the 15% (by % of total contract value) annual Small Business requirement required by this PWS. The Contractor may utilize Second-Tier subcontractors in meeting this requirement. This is in addition to the required Small Business Subcontracting Plan/Comprehensive Subcontracting Plan required by FAR 52-219-9 and DFARS 219.702 Where does the Government desire offerors to include their Small Business Subcontracting Plans that are called-out in ITO 3.2.5 and PWS 1.3.15? Documents were updated prior to the posting of the Formal RFP on FBO 9 Dec 16. These requirements are now referenced in ITO Paragraph 3.2.4 f and PWS 2.1.14. Table 2.1 of the ITO, Proposal Organization, requires the location of the response for ITO Paragraph 3.2.4 in Volume I. Small Business Subcontracting Plan required by FAR 52.219-9 is a separate requirement and shall be included in Volume IV.
PSC - 5 ITO ITO, Section 4.0, Past Performance, paragraph 4.3.1, General, Note, states: “…Request each PPI contract (or effort) not exceed 13 pages, although more or less may be submitted, if necessary and relevant to the T-1A COMBS effort.
ITO paragraph 2.2.3, Table 2.1, Volume II, Past Performance (Factor 2), identifies a 13-page limit for each PPI
| ITO, Section 4.0, Past Performance, paragraph 4.3.2, PPI Relevant Contract Narrative, states: … The Offeror is requested to limit the narrative to a maximum of 5 pages. However, the Offeror may exceed the requested page limit, if determined necessary to fully describe relevancy. | Will the Government consider reconciling the Past Performance Information (PPI) submission page count at 13 each by removing the last two sentences from ITO paragraph 4.3.2? | No, the last two sentences from ITO paragraph 4.3.2 will not be removed. The 13 pages referenced in ITO Paragraph 2.2.3, Table 2.1, Proposal Organization, refers to the entire PPI sheet, which includes period of performance, dollar value, contract type, points of contact, general description of effort, relevancy narrative, etc. The 5 pages referenced in para 4.3.2 of the ITO refers strictly to the relevancy narrative. The 5 pages is part of the 13-page total. |
| PSC - 6 | PWS |
| General | Will the Government consider changing the frequency of mandatory Program Management Reviews (PMR) from an annual, to a semi-annual basis to ensure timely customer-service provider communications on potential mission impacting issues? | Will the Government consider changing the frequency of mandatory Program Management Reviews (PMR) from an annual, to a semi-annual basis to ensure timely customer-service provider communications on potential mission impacting issues? | The government is satified with the frequency of the PMRs identified in the PWS. The contractor is required to support all meetings IAW PWS Para 2.1.4. The communication required by PWS allows for discussion on potential mission impacting issues. |
| PSC - 7 | PWS | PWS paragraph 1.3.15, Small Business Participation Plan and Reporting, states: “The Contractor shall have a Small Business Participation Plan to manage subcontractor performance to meet and maintain the 15% (by % of total contract value) annual Small Business requirement required by this PWS. The Contractor may utilize Second-Tier subcontractors in meeting this requirement.” |
PWS paragraph 1.6.4, Augmentation of GFP and Parts Manufacturing Authority (PMA), states: “… The Contractor shall ensure Parts Manufacturing Authority (PMA) items are not used for engine life limited components, airframe life limited components, or for critical airframe components designated by the Aircraft Structural Integrity Program (ASIP). The Contractor shall ensure PMA parts meet reliability requirements of engine Time-Between-Overhaul (TBO) and Hot Section Inspections (HSI) and do not negatively affect current airframe or engine maintenance and inspection procedures. For primary and secondary structural parts, the Contractor shall obtain Program Office approval prior to acquiring PMA replacement parts. …”
| PWS paragraph 1.6.14, Engines & Landing Gear Maintenance, states: “The Contractor shall accomplish scheduled engine HSI, engine overhauls, and landing gear overhauls using a FAA Federal Aviation Regulation (FAR) Part 145 repair station facility. The Contractor shall ensure engines meet serviceability and functional test requirements applicable to OEM specifications. | Due to the large percentage of total contract value (TCV) that is attributable to parts and materials (most of which is only available through large business OEMs), will the Government consider lowering the Small Business Goal from 15% TCV to 7% TPSD—providing a goal that, although a stretch, is attainable on this contract? | No, the government's requirement is 15%. Market research via Request for Information (RFI) in May 2016 to industry indicated the amount of 15% was attainable. PWS updated prior to the posting of the Formal RFP on FBO 9 Dec 16 to allow utilitzation of Second Tier subcontractors in meeting this requirement. | ||
| PSC - 8 | PWS | PWS paragraph 1.4.2.e states: “At least four (4) times per year, at each operating location, PSA shall travel to collect data and provide training on maintenance best practices. At least six (6) times per year total, PSA shall provide on the job training to T-1A aircraft maintenance technicians, the Government will participate in determining which training and which base. …” | A. Do we understand the travel requirements for the Program Support Analyst (PSA) correctly to be: 4 times per year to 4 MOBs (PSA already located at the Randolph AFB MOB) = 16 trips, plus at least 6 OJT trips (at the direction of the Government), for a total of a minimum of 22 trips annually? If we have miscalculated, will the Government please identify the number of annual PSA trips intended? |
B. Does the Government intend offerors to include travel expenses within CLIN X003F, PSA (FSR Roving), or does the Government intend either to provide a travel CLIN, or intend travel to be considered an over and above expense? A. PWS updated prior to the posting of the Formal RFP on FBO 9 Dec 16
B. Offerors should include travel expenses within CLIN X003F; there will not be a separate CLIN specifically for PSA travel.
| PSC - 9 | PWS | PWS paragraph 1.4.3.3, Temporary Duty, states: “The Site FSR shall support temporary duty assignments away from MOB as requested by the PCO.” | Since FSR travel is accomplished on a PCO-directed basis, does the Government intend for FSR travel expenses to be addressed as over and above expenses, or does the Government intend to initiate a separate Travel CLIN? | Per Event on the O&A subclin at direction of PCO |
| PSC - 10 | PWS | PWS paragraph 1.6.10.1, Automated Data processing (ADP) Reporting System | Will the Government consider revising the last sentence of the second paragraph of PWS 1.6.10.1 to complete the intended sentence? | PWS has been updated prior to the posting of the Formal RFP on FBO 9 Dec 16 |
| PSC - 11 | RFP | Clause 52.212-5, CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS--COMMERCIAL ITEMS (JUN 2016) (IAW FAR 12.301(b)(4)) (RFP Page 21 of 42) |
| Clause 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards--Price Adjustment (Multiple Year and Option Contracts) (May 2014)(29 U.S.C. 206 and 41 U.S.C. chapter 67). (RFP Page 24 of 42) | Would the Government consider re-marking Clause 52.212-5, CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS--COMMERCIAL ITEMS, to indicate Clause 52.222-43 is applicable vice Clause 52.222.44 because this contract is a multiple year and option contract. | Yes, RFP updated prior to the posting of the Formal RFP on FBO 9 Dec 16 |
| PSC - 12 | PWS |
ITO PWS paragraph 1.3.14, Vendor Relationships, states: “The Contractor shall establish and maintain relationships with OEMs and suppliers and shall have access to field service staff, help desks, or other services providing information and advice on solving field problems. The Associate Contractor Agreements (ACA) should address handling of proprietary data, technical data, etc.”
ITO paragraph 3.2.3.b, states: “Provide letters of intent, which sufficiently establish and maintain written agreements with appropriate airframe, engine and parts Original Equipment Manufacturers (OEMs) for engineering support and technical data. The OEM letters of intent must be addressed to the prime contractor. (PWS paragraph 1.3.14)”
CLIN X002, Contractor Operated and Maintained Base Supply (COMBS), states: “The Contractor shall operate and maintain a base supply at each designated MOB to meet performance rates required IAW PWS 1.6.10.1 & 1.6.10.2. The Contractor shall provide all labor, management, overhead, supplies, and storage services necessary to operate the COMBS. The Contractor shall manage and control Government provided spares and support equipment listed in Appendix B, Government Furnished Property (GFP). All GFP, GFE and GSE shall be in FIAR compliant with the guidelines provided in the DoD FIAR Guidance dated April 2016, incorporating all requirements as stated by the Chief Financial Officer (CFO) Act and Office of Management and Budget (OMB) Circular A-123, Appendix A.”
| CLIN X004, Flying Hours, states: “The Contractor shall provide all components, parts, equipment, materials, bench stock, and consumables required to support the T-1 fleet to include repair, maintenance, overhaul, replacement and replenishment of aircraft components, parts and consumables. The Contractor shall also provide parts, maintenance and repair support for common/peculiar support equipment and material handling equipment. Services under this CLIN shall be performed IAW PWS 1.6. Acts of God, Bird Strikes, Government caused damage/loss and Government directed items will be separately negotiated as an Over and Above.” | Does the Government intend for bidders to price the costs associated with obtaining Data Licensing Agreements with the OEMs (i.e. Beechcraft) in CLIN X002, Contractor Operated and Maintained Base Supply (COMBS), or CLIN X004, Flying Hours? | Response to be posted at a later date | |
| PSC - 13 | ITO | ITO, paragraph 5.2, page 16 states: “Pricing information in the Price Matrix (Attachment C) is the only Price information that shall be included in Contract Documentation (Volume IV).” |
| ITO, paragraph 5.4, page 22 states that Section 4 of the Price Volume should include Submission of Pricing Matrix. | Is it the Government’s intent for the offeror to include Attachment C only in the Contract Documentation volume, or does the Government want the offeror to include Attachment C in both the Contract Documentation volume AND the Price Volume? | Refer to revised ITO section 5.2 and 5.4. ITO was updated prior to the posting of the Formal RFP on FBO 9 Dec 16 | |||
| PSC - 14 | PWS | PWS paragraph 1.7.3, Depot Maintenance, states: “The Contractor shall have the capacity to perform depot level aircraft inspection and maintenance, aircraft crash and damage repair, emergency depot drop-in maintenance, and modification installation at a certified FAA FAR Part 145 Repair station when directed by the PCO”. | Will the Government please clarify the CLINs associated with depot level aircraft inspection and maintenance, aircraft crash and damage repair, emergency depot drop-in maintenance, and modification installation, and the line items in the pricing matrix to be utilized during these activities? | As directed by PCO via O&A (CLIN X007) | |
| PSC - 15 | ITO | ITO, paragraph 5.3.6, Annual Price Changes, states ”Proposed price increases greater than 5% per period shall be verified and addressed for reasonableness as well as balanced pricing in this section”. | Would the Government consider including an Economic Price Adjustment (EPA) clause to address industry uncertainty and the suggested 5% price increase reasonableness? This would reduce risk of option year and incentive period pricing, and improve price balance and realism of the offerors. | The Government has considered FP with EPA but determined FFP to be more appropriate. | |
| PSC - 16 | ITO | ITO, paragraph 5.3.8, Proposed Fixed Rates: Hourly Labor Rates for Over & Above (O&A) Labor, states “All rates shall be proposed as FFP rates. FFP rates are those rates proposed for all performance periods and are considered fixed at the proposed amount. Offerors are to indicate their understanding of proposed ceiling rates, acknowledging that such rates will apply to out-years (period of performance beyond year one of the basic period) in the future despite what current actuals are running at the time”. | Will adjustments to the hourly labor rates be allowed based upon upward adjustments in accordance with FAR 52.222-43, Service Contract Labor Standards – Price adjustment (multiple year and option contracts)? | Yes. Adjustments must be IAW FAR 52.222-43. | |
| PSC - 17 | PWS | PWS paragraph 1.6.5, Maintenance and Replenishment of Parts and Material, states: “The Contractor shall be responsible for all repair, overhaul, replacement, and replenishment of GFP and GFE. The Contractor shall provide repair of reparables and replenishment of nonreparables and replenishment of consumable material as required by T-1A technical manuals (i.e. coatings, paints, tapes, corrosion prevention/treatment materials, lubricants, adhesives, etc.). …” | Will the Government consider providing offerors with the historical T-1A specific usage of the consumable material identified in PWS paragraph 1.6.5, to enable accurate inclusion into cost per flying hour calculations? | See attached usage date, RFP Attachment 6; updated prior to the posting of the Formal RFP on FBO 9 Dec 16. This report is historical data and provided for planning purposes only and future usage may vary. | |
| PSC - 18 | RFP |
Eval
Pricing Matrix Draft RFP (FA810616R0013_DRAFT_12Sep.pdf) CLIN Structure: The Sub-CLIN Breakout for CLIN X007 within the Draft RFP dated 12 Sep is as follows: X007AA – Over & Above – Program Manager, X007AB – Over & Above – Engineering and X007AC – Over & Above – Mechanic
Evaluation Factors for Award, Section 2.4.6.2, Pricing Methodology, Estimated Quantities Table provides the following Sub-CLIN Breakout for CLIN X007: X007AA – O&A Labor Rate (Fixed), X007AB – O&A Labor Rate (Overtime), X007AC – Material Handling Rate and X007AD – Parts & Material (Not Flying Hrs)
| Draft T-1A COMBS Pricing Matrix: The Pricing Matrix provided with the 12 Sep Draft RFP identifies a completely different CLIN structure dealing with Over & Above: X006 – Over & Above – Fixed price Per Event/Occurrence, X006AA/AE – Sched. Eng. Hot sect. insp. – 2500 hours, X006AB/AF - Scheduled engine overhaul - 5000 hours, X006AC/AG - Landing gear overhaul – nose gear, X006AD/AH - Landing gear overhaul – main gear and X007 – Over & Above – Hourly Labor Rates and Material/Subcontract Markup Used in Post Award O&A Negotiations | Will the Government please revise the CLIN structures identified in the RFP, Evaluation Factors for Award, and T-1A Pricing Matrix to ensure consistency? | Yes and it has been updated prior to the posting of the Formal RFP on FBO 9 Dec 16 | |||
| PSC - 19 | PWS | PWS, Page 11 | Section 1.3.20 states COMBS Site Foreman as a Key Personnel position. No minimum experience requirements are provided in the PWS, as are for other Key Personnel. Does the Government have minimum experience requirements for the COMBS Site Foreman position? | No, the qualifications for the COMBS site foreman position is the responsibility of the contractor. | |
| PSC - 20 | ITO |
PWS ITO and PWS, Page 12 (ITO) and 9 (PWS) In accordance with PWS 1.3.15 and ITO 3.2.5, the Small Business Subcontracting Plan is in addition to the Small Business Participation Plan. Will the Government consider including the Small Business Subcontracting Plan in Volume IV? Documents were updated prior to the posting of the Formal RFP on FBO 9 Dec 16. These requirements are now referenced in ITO Paragraph 3.2.4 f and PWS 2.1.14. The requirements of ITO paragraph 3.2.4 f. are in addition to the required Small Business Subcontracting Plan (FAR 52.219-9). Table 2.1, Proposal Organization, requires the location of the response for ITO Paragraph 3.2.4 in Volume I. Small Business Subcontracting Plan requirements contained in FAR 52.219-9 and DFARS 252.219-7003 shall be provided with Volume IV.
| PSC - 21 | ITO | ITO, Page 12 | ITO 3.2.5 references Attachment 4, “Small Business Subcontracting Requirements” and we are not able to locate the document. Does the Government intend to release Attachment 4 with the final RFP? | Documents were updated prior to the posting of the Formal RFP on FBO 9 Dec 16. |
| PSC - 22 | General | General | The Government is procuring a new T-1A Avionics Suite to be installed on 178 T-1A aircraft over the next 4 years. How then will a COMBS contractor bid for unknown components for the remaining years of the COMBS contract? | The initial spares for the T-1A Avionics Modernization Program will be provided as GFP and the contractor will be responsible for failed components. |
| PSC - 23 | General | General | Will the Government confirm that offerors price the COMBS CLIN assuming that the existing equipment will be used for the entire period of performance with the expectation that there will be a contract mod once the avionics upgrade award has been made and an implementation schedule has been finalized?” | No. The USG does not intend a contract mod to cover parts replaced under the avionics modification. |
| PSC - 24 | PWS | PWS 1.5.1, Page 44 | In reference to long lead parts and estimated delivery date, - Where can a bidder find a list of long lead parts? | The Government will not provide a list of long lead parts. It is the contractor's responsibility to identify the long lead items. |
| PSC - 25 | PWS | PWS Paragraph 1.3.14 requires an offeror “Provide letters of intent, which sufficiently establish and maintain written agreements with appropriate airframe, engine and parts Original Equipment Manufacturers (OEMs) for engineering support and technical data. The OEM letters of intent must be addressed to the prime contractor.” | A. Has the Engine OEM indicated to the Government that they will sell parts to any qualified and applicably rated FAA Part 145 Repair Station that wins the bid? |
B. Would a long term procurement history with the OEM of a qualified and applicably rated FAA Part 145 Repair Station be a sufficient substitute for the OEM letter of intent, should the OEM fail or refuse to provide the LOI prior to the Bid deadline?
C. Would the government consider purchasing any parts an OEM claims are proprietary and will not sell to a qualified and applicably rated FAA Part 145 Repair Station and adding them as GFP. A. The government has not had conversations with the Engine OEM regarding this requirement. It is the offeror's responsibility to establish any necessary agreement with the Engine OEM.
B. No, the requirement is to have a letter of intent from the OEM to be included in the proposal
C. No
| PSC - 26 | PWS | Reference PWS 1.5.1.1, Phase-in Period, and 1.5.1.2, Phase-in Reporting | Will the Government provide space at each COMBS location to allow the successor contractor to establish the contractors Information Technology (IT) system along with warehouse space for receiving and storage of the contractors spares and materials to support the program during the transition period? | COMBS locations will provide adequate space to facilitate transition. |
| PSC - 27 | RFP | The draft RFP, amended ITO table 2.1 to add a stand-alone section to the Past Performance Volume titled “PPI Relevant Contract Narrative (If Applicable)”, citing ITO paragraph 4.3.2. This information is a duplicate of the information already required within the structure of the PPI tool (Attachment 1.1), Program Details tab. Since both relevancy and problems encountered are already required to be addressed within the PPI tool narrative, we believe paragraph 4.3.2 should not be a separate stand-alone proposal volume section, but is intended as further clarification of the information required within the PPI tool under paragraph 4.3.1 and Attachment 1.1. | Will the Government consider amending ITO Table 2.1 to delete the line from the past performance volume “4.3.2, PPI Relevant Contract Narrative (If Applicable)”, and adding the ITO paragraph reference 4.3.2 to the above line titled “Present/Past Performance Information Sheets (PPIS) (See Attach 1.1)”. We believe having both paragraphs 4.3.1 and 4.3.2 applicable to the narrative required by the PPI Tool Program Details Tab, will further clarify the desired content of past performance citations provided within the PPI Tool. | The ITO has been updated prior to the posting of the Formal RFP on FBO 9 Dec 16; however sections 4.3.1 and 4.3.2 will remain the same. |
| BREAK | BREAK | BREAK | BREAK | BREAK |
| T-1A COMBS Formal RFP 9 Dec 16 Questions/Answers | ||||
| FRFP -1 | ITO |
PWS Both ITO paragraph 3.2.4.f and PWS paragraph 2.1.14 identify the requirement to submit a Small Business Subcontracting Plan, however, we cannot find, within the ITO instructions for Volumes I – Technical, III – Price, or IV – Contract Documentation, where the Government intends Large Business offerors to include their Small Business Plans. Since the Small Business Subcontracting Plans, by their nature, contain pricing information, we assume that this document would be logically provided within either the Price or Contract Documentation volumes. In addition small business plans generally require between 25 and 30 pages to adequately address all the FAR 52.219-9 requirements Does the Government desire offerors to include their Small Business Subcontracting Plans required by ITO 3.2.4.f and PWS 2.1.14, within Volume III – Price, or Volume IV – Contract Documentation? The requirements of ITO paragraph 3.2.4 f. are in addition to the required Small Business Subcontracting Plan (FAR 52.219-9). Table 2.1, Proposal Organization, requires the location of the response for ITO Paragraph 3.2.4 in Volume I. Small Business Subcontracting Plan requirements contained in FAR 52.219-9 and DFARS 252.219-7003 shall be provided with Volume IV.
FRFP - 2 PWS
| RFP | Based upon the nature of this COMBS solicitation, over 95% of the total contract value of this solicitation is derived from the projected cost of parts and materials. There are severe limitations on the use of small business vendors because the majority of the parts must come from OEM vendors, the Performance Work Statement (PWS) places limitations on the use of PMA parts, and Engine HSIs and Overhauls must be accomplished at authorized FAA Part 145 repair facilities, which for the T-1A aircraft is limited to the Original Equipment Manufacturers (OEMs). Although Second-Tier subcontractors can be utilized, based on the high OEM content, we believe there will not be flow-down opportunity. The second-tier subcontractors will either self-perform the repairs and claim no subcontracting opportunity, or request a waiver to submitting subcontracting plans, based on FAR 52.219(j) Subcontracting plans are not required from subcontractors when the prime contract contains the clause at 52.212-5, Contract Terms and Conditions Required to Implement Statutes or Executive Orders—Commercial Items, or when the subcontractor provides a commercial item subject to clause 52.244-6, Subcontracts for Commercial Items, under a prime contract. We therefore feel that a Small Business Goal of 15% of Total Contract Value is not reasonably attainable for a Large Business Prime offeror | Due to the large percentage of total contract value (TCV) that is attributable to parts and materials (most of which is only available through large business OEMs who will claim “commerciality,” and therefore be exempt from providing Small Business plans or reporting, will the Government consider lowering the Small Business Goal from 15% TCV to 7% of Total Planned Subcontracting Dollars (per clause 52.219-9), which is more attainable on this contract? | No, the government's requirement is 15%. Market research via Request for Information (RFI) in May 2016 to industry indicated the amount of 15% was attainable. | |
| FRFP - 3 | ITO | ITO paragraph 3.2.4.f, EFfA paragraph 2.2.2.f, and PWS paragraph 2.1.14 identify the requirement to meet and maintain a 15% annual Small Business requirement. In PWS paragraph 6.3 it identifies that the contractor will be required to provide a Quarterly Small Business Report that must meet 15%, 95% of the time. In the RFP documentation there is not an exact schedule or timeframe at which point the contractor is required to achieve the 15%. In order to mitigate risk a contractor may propose an improvement schedule allowing an approach whereas an offeror may mature their small business subcontracting opportunities over multiple performance periods to reach the ultimate goal of 15%. An example would be that a contractor may propose a schedule with 7% by end of year 1, 10% by end of year 2, 15% by end of year 3 with sustained 15% through the end of contract. This would allow for implementation of strategies and improvements to the approach to ensure not only meeting the 15% requirement but increasing the likelihood of maintaining the 15% Small Business requirement. | If a Contractor presented staggered approach to achieving 15% Small Business Requirement over time would this be considered compliant and acceptable for passing the technical evaluation? |
Also, if the contractors approach/plan for achieving the 15% Small Business requirement is a multi-year schedule would the Performance Evaluation (PWS 6.3) be measured against the contractors proposed plan?
| No, the requirement is to obtain 15% of the total contract value. If the contractor cannot reach the requirement a get well plan is required per the PWS. If the requirement is still not obtained at the time of government's written assessment of the contractor through the Contractor Performance Assessment Report (CPAR), the assessment for the small business requirement may be reflected negatively towards the contractor's ability to meet the requirement. | ||||
| FRFP - 4 | ITO | ITO paragraph 2.1.8, states: “Proposals and modifications to proposals shall be submitted in sealed envelopes or packages in paper media and electronic media addressed to the CO at the address shown in block 9 of the SF 1449 solicitation, and showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror.” | The SF 1449 is not included in the solicitation. Is page 2 of the solicitation to replace and supersedes the SF 1449? | A combined synopsis/solicitation was issued in lieu of a SF 1449. An amendment to clarify is forthcoming. Page 1 & 2 of the RFP identifies the time and date specified for receipt. Page 10 of the ITO, para 2.6, identifies the POC and address. Page 4 of the ITO, Para 2.2.1, requires the title page of each volume show the solicitation number, name, address, and telephone and facsimile numbers of the Offeror and electronic e-mail address if available. |
| FRFP - 5 | RFP | In order to provide the USG with the best proposal pricing, will you please define the period of performance including the month and year for the 3 month transition / phase in period and the following 9 month full scale performance? | No, the period of performance start date is currently unknown and will depend on the award date of the contract. The Government's estimated effective date of this contract is 4th quarter calendar year 2017. This estimated award date is for informational purposes only and in no way binding to the Government. | |
| FRFP - 6 | ITO | ITO 2.3.1, Page, states: “A page is defined as each face of a sheet of paper containing information. When both sides of a sheet display printed material, it shall be counted as two pages. Page size shall be 8.5 x 11 inches, not including foldouts. Page line spacing shall be 1.15 lines. Except for the reproduced sections of the solicitation document, the text size shall be no less than Times New Roman 12-pt. Tracking, kerning, and leading values shall not be changed from the default values of the word processing or page layout software. Use at least 1 inch margins on the top and bottom and 3/4 inch side margins. Pages shall be numbered sequentially by volume. These page format restrictions shall apply to responses to ENs. These limitations shall apply to both electronic and hard copy proposals | Does the Government intend for offeror’s proposal volumes to incorporate 1.15 line spacing for text, or was 1.5 line spacing intended? | The posted ITO contained an error in section 2.3.1 in reference to the page line spacing at 1.15. The intention of the USG is for the page line spacing to be 1.5. An updated ITO will be posted at a later date. |
| FRFP - 7 | ITO |
PWS ITO paragraph 2.1.3 identifies a requirement to notify the CO of any potential errors in this solicitation, ITO paragraph 5.2.3 illustrates the requirement to adequately understand the contractual requirements for Price Realism and PWS paragraph 1.2 states that the T-1A is equivalent to a Beechcraft 400. To ensure that the USG receives the appropriate overhaul and properly evaluates for Price Realism, would the USG consider revising the PWS to include the specific aircraft model? Although the specific aircraft model is not identified in the PWS, the term "equivalent to a Beechcraft 400" was provided; however, for clarification purposes, the T-1A is the Beechcraft 400T. The bidders library includes the 1T-1A-6 Tech Order that clearly defines the overhaul/replacement requirements for engines and landing gear.
Sheet1
| POST FINAL RFP RELEASE | |||
| 370 | General | Request the AF identify, by publication number, each publication (flight, maintenance, job guide, fault isolation, etc.) that will require updates based on the AMP modification requirements document to enable bidders to determine accurate page counts for firm fixed price bid. | The offeror will be responsible for determining the number of pages based on their analysis of the proposed technical order updates. |
| 371 | General | Are CDRLs and TMCRs available to indicate which Mil-Specs will be used to develop supplemental TOs for the SGML required Maintenance pubs to allow bidder to determine DTD/FOSI needs for the project and FFP page counts? | CDRL and TMCRs are not available indicating MIL-SPECs needed for developing supplemental TOs. For any DTD/FOSI needs, please coordinate through the TMSS office at Wright Patterson. https://techdata.wpafb.af.mil/tmss/index.html |
| 372 | General | Are CDRLs and TMCRs available to indicate which Mil-Specs will be used to develop supplemental TOs for the IPDF required Flight pubs other than the 38784A to allow bidder to determine FFP page counts? | CDRL and TMCRs are not available indicating MIL-SPECs needed for developing supplemental TOs. For any DTD/FOSI needs, please coordinate through the TMSS office at Wright Patterson. https://techdata.wpafb.af.mil/tmss/index.html |
| 373 | General | The Interface Control Document for the UHF was not provided as part of the bidders library. Can the Air Force add the ICD for the UHF to the bidders library? | There is no ICD for the UHF. See TO # 1T-1A-2-23GS-00-1 for the UHF communication schematic. |
| 374 | SRD | Based on SRD 4.2.2 and 4.2.3 requirements we are confused on the audio requirements since the CSO and SUPT have different audio systems/requirements. Is there an AMU-50 Digital Audio DACS in the current CSO PTT? It appears that currently there is only a picture, not an actual system/component. | There is no AMU-50 in the current CSO PTT, only a photographic representation. |
The current PTT has a picture to represent the interphone panel. In addition, numerous other components are represented as pictures. Refer to 4.2.2 of the SRD, "The PTT shall be a representation of the cockpit to include pilot displays, multi-function display(s), auto-pilot controls, audio controls, navigation, and communication controls (MANDATORY)." There is no mention of one PTT to satisfy both CSO and SUPT/PIT. If there are different components in the aircraft, there should be different components (or representations) in the PTT.)
375 SRD Based on SRD 4.2.2 and 4.2.3 requirements we are confused on the audio requirements since the CSO and SUPT have different audio systems/requirements. Can the same PTT be used for both SUPT and CSO versions? We do not find any information directing separate PTT's, but there is the issue of the audio system difference. There is no AMU-50 in the current CSO PTT, only a photographic representation.
The current PTT has a picture to represent the interphone panel. In addition, numerous other components are represented as pictures. Refer to 4.2.2 of the SRD, "The PTT shall be a representation of the cockpit to include pilot displays, multi-function display(s), auto-pilot controls, audio controls, navigation, and communication controls (MANDATORY)." There is no mention of one PTT to satisfy both CSO and SUPT/PIT. If there are different components in the aircraft, there should be different components (or representations) in the PTT.)
| 376 | SOW | Table 11-2 is not in agreement with Appendix B - Production Schedule. This would impact the IMS. | Table 11-2 of the SOW has been changed to align with the production planning schedule in appendix B and will be updated through RFP amendment. | KCL Verified | |
| 377 | Section L | We have converted the file via a conversion program (PDF to Word) however, we cannot remove the "draft" watermark, which means I cannot send out the letters or PP Questionnaire until either: Section L is released without the "draft" watermark, or we will have to retype the entire questionnaire. | |||
| Request the government reissue Section L in Word format ASAP so that we can proceed with the getting the Past Performance documents to the companies. | PK - The watermark word "Draft" has been removed from Section L. This was an administrative oversight and will be resolved through RFP amendment. | ||||
| 378 | Section L | Section L 2.1.1 , Point of Contact, states that written requests for clarification may be sent to the CO [Contracting Officer] at the address located in Section A of the model contract solicitation. Section A would be the SF 1447 which lists Michelle James as the "Buyer" but this is the only name listed in Section A, so is she the contracting officer? | |||
| Section L, 2.6 refers to you as the Contracting Officer. Which is correct and who should the proposals be addressed to? | PK will update Section L for clarity through RFP amendment. | ||||
| 379 | General | Sec L 3.2.5 / Sec M 2.2.3 (a) ACA with current CLS contractor. Ref Question #311, the government acknowledged the request for contact information for the current CLS contractor. | |||
| Request the government provide the contact information for the current CLS contractor so that bidders may comply. | Aero Simulation Inc |
4450 East Adamo, Drive Suite #501 Tampa, FL 33605-5941 Phone: (813) 628-4447, ext 120 Direct Phone: (813) 463-8658 http:www.aerosimulation.com
| 380 | SRD | SRD – Appendix B 3.7.9.4 Verification method(s) not identified. | The SRD appendix B has been changed to reflect demonstrate and inspection as the verification methods for 3.7.9.4 and will be updated through RFP amendment. | KCL Verified |
| 381 | SOW | SOW 6.4.3.1 par 3, What is “FDE”? –not defined in acronym list. | The SOW 6.4.3.1 para 3 has been changed from FDE to OT&E and will be updated through RFP amendment. | KCL Verified |
| 382 | SOW | SOW 7.6 Aircraft Delivery |
What document will be used to accept and transfer the aircraft back to the government?
Who is responsible for accepting the aircraft—the QAR?
| Please clarify/define “coordinate with GFR for release of aircraft.” | SOW para 7.6 updated directing possession of the aircraft transfer from the contractor to the Government via DD Form 1149. GFR changed to Government Representative. The Government Representative will identified after contract award. | KCL Verified | |||
| 383 | Section L | Table 2.2 Requirements Correlation Matrix. According to Sec L, Table 2.1 this table is to be placed in Volume IV only. Should this also be placed in Volume I as a roadmap for the evaluators to ascertain compliance? | The requirements correlation matrix has been added to Section L table 2.1 volume I and will be updated through RFP amendment. | KCL Verified | |
| 384 | Section L | Sec L, 6.5 states that this is a Firm Fixed Price (FFP) contract. RFP, Part I, Section B, h) States “Progress Payments will be utilized for this effort.” |
252.232-7006 (Wide Area Workflow Payments) is based on completion of a CLIN. [There are no procedures contained in the RFP/SOW for determining progress payments.] 52.232-16 Progress Payments (FAR 32.502-4(a) does not apply since payments are based on CLIN completion. [32.501-1 states “progress payments are for accrued costs incurred.” This is a FFP contract; accrual accounting is not required to ascertain/establish progress completion for monthly payments.
RECOMMENDATION: delete FAR 52.232-16 and delete RFP Part I, Section B h).
| PK - ? | |||
| 385 | SOW | SOW 8 Simulators (OFT&PTT) , RFP Appendix B – Schedule | |
| SOW 8 “Modification of the prototype OFT [contractor assumes OFT’s] at the contractor’s facility.” Is the schedule in Appendix B only to show “the requirement” during the base period and the contractor can determine via the IMS when they require the simulators at the contractors facility to modify? Can both prototype OFT’s be at the contractors’ facility at the same time to facilitate compliance with SRD 4.1.3? | Yes Appendix B shows the requirement during the base period and the contractor can determine via IMS when they require the simulators. Yes both prototype OFTs may be at the contractor's facility or the MOB at the same time to facilitate SRD compliance as these OFTs are not from the same MOB. | ||
| SOW 8.1 updated. The words "at each MOB" have been added to the last sentence and will be updated through RFP amendment. | KCL Verified | ||
| 386 | SOW | SOW 5.4 Initial Spares |
Originally 5.4 stated: “adequate spares in place at the MOB NLT - (minus) 30 days prior to the first aircraft and OFT/PTT delivery/completion.”
Currently 5.4 states: “initial spares are immediately ordered upon award of each option.” “quantities are identified in the initial spares CLINS for each option.”
Appendix B contains a schedule for Initial Spare kits for aircraft, OFT and PTT by Option year.
CLIN 1013x is the CLIN for Initial Spares, but is not applicable during the base year?
| Question: How and what quantities are “spares” to be ordered to support prototype and LRIP aircraft, OFT and PTT’s? How are the costs for spares for prototype equipment to be presented/priced and charged since there is not a Base Year CLIN? | Government assumes no spares support will be required during the base period. Costs for spares for prototype will be include in option year CLINs. | ||
| 387 | General | RFP Appendix B – Production Planning Schedule, SOW 8 |
NOTE: The contractor acknowledges that the schedule and quantities are subject to change post-award and all requirements in Appendix B are scheduled “INPUT” dates, not completion dates.
There is a conflict between the SOW 8 requirements and the Appendix B schedule.
Base Period – There is no stated requirement of when the OFT’s and PTT’s have to be in place prior to prototype aircraft delivery.
Question: Is the contractor required to have an OFT and PTT at both Pensacola and Vance 30 days prior to prototype aircraft delivery? The contractor must modify and complete two prototype OFTs (one SUPT and one CSO) and one PTT during base period of performance.
SOW 8 para 2 updated to reflect prototype simulator completion during the base period and will be updated through RFP amendment.
Refer also to question #404.
| KCL Verified | ||
| 388 | SOW | REQUEST FOR CLARIFICTION: |
The updated SOW 4.1 and the updated Q&A contain identical references to DI-MGMT-81861A, para 2.8.2:
Request the Government verify that the following requirements in the updated SOW are what the Government desires and requires:
1. The utilization of Format 6, Paragraph 2.8.2 mandates the use of earned value.
DI-MGMT-81861A, Para 1.4 - The IPMR is used to obtain cost and schedule performance information on contracts requiring compliance with the American National Standards Institute/Electronic Industries Alliance Standard 748 (ANSI/EIA-748), Earned Value Management Systems (EVMS).
Request the Government confirm that Earned Value is the requirement for the T1A AMP.
Earend Value Management is not the requirement for the T-1A AMP. As stated in the SOW, Format 6 is being applied separately as DFARS 252.234-7002 is not applicable. EVM DFARS is Not Applicable to the t-1A AMP.
Additionally DI-MNGT-81861A para 1.4 ends with "where applicable". ANSI/EIA-748 refers to cost and incentive type contracts and agreements not Firm Fixed Price and as such T-1A AMP is not applicable.
Additional references: DFARS Subpart 234.2 and the IPMR Implementation Guide dated January 24, 2013 available at www.acqnotes.com/acqnote/tasks/integrated-program-management-report-ipmr 389 SOW 2. DI-MGMT-81861A, Para 3.7.1.3. – IMS Content Elements The IMS shall have traceability to the Integrated Master Plan (IMP) (if applicable), Organizational Breakdown Structure (OBS), Control Accounts, WBS and Statement of Work. The WBS in the IMS shall be consistent with the Format 1 structure if applicable.
Request the Government confirm that the IMP must be imbedded in the IMS, an Organizational Breakdown Structure must be established and submitted, Control Accounts must be established, SOW traceability must be imbedded in the IMS, and a 3 level Work Breakdown structure is required as a minimum. DI-MGMT-81861A Format 6 (IMS) para 3.7.1.3 lists IMS Content Elements required.
Note that Format 6 is being applied separately which omits references to Formats 1 through 5 and 7.
Additional reference is the IPMR Implementation Guide dated January 24, 2013 available at www.acqnotes.com/acqnote/tasks/integrated-program-management-report-ipmr 390 SOW 3. DI-MGMT-81861A, Para 3.7.1.3.4.1 – Control Accounts Every discrete task/activity, work package, and planning package shall be clearly identified and directly related to a Control Account. Work packages and planning packages shall be individually represented and summarized to and reconciled with the total budget for that control account.
Request the Government confirm that the establishment of Control Accounts is desired and budget reconciliation at the work package and control accounts are required.
Request the Government elaborate on what the expectations are for work package to control account budget reconciliations will be. DI-MGMT-81861A Format 6 (IMS) para 3.7.1.3.4.1 is applicable to the T-1A AMP.
Government expectations are as stated in DI-MGMT-81861A para 3.7.1.3.4.1: "Every discrete task/activity, work package, and planning package shall be clearly identified and directly related to a control account. Work packages and planning packages shall be individually represented and summarized to and reconciled with the total budget for that control account.
The requirement is clearly stated.
Additional reference is the IPMR Implementation Guide dated January 24, 2013 available at www.acqnotes.com/acqnote/tasks/integrated-program-management-report-ipmr 391 SOW 4. DI-MGMT-81861A, Para 3.7.3 – Task / Activity Codes and Data Dictionary This is a list of all contractor defined fields, definitions, and code Structures in the IMS.
Request the Government confirm that task / activity codes and a data dictionary are requirements. DI-MGMT-81861A Format 6 (IMS) para 3.7.3 is applicable to the T-1A AMP.
Additional reference is the IPMR Implementation Guide dated January 24, 2013 available at www.acqnotes.com/acqnote/tasks/integrated-program-management-report-ipmr
| 392 | SOW | 5. Request the Government confirm that an Organizational Breakdown structure be developed and imbedded in the IMS is a requirement. | |
| a. DI-MGMT-81861A, Para 3.7.1.3.7.2 - The Statement of Work and OBS must be traceable for all discrete work in the IMS. Traceability may be met with a field in the IMS or via other means as long as discrete work reconciles. | DI-MGMT-81861A Format 6 (IMS) para 3.7.1.3.7.2 is applicable to the T-1A AMP. |
Additional reference is the IPMR Implementation Guide dated January 24, 2013 available at www.acqnotes.com/acqnote/tasks/integrated-program-management-report-ipmr 393 SOW 6. Request the Government confirm that the following schedule analysis methods are required.
a. Total Float / Slack - DI-MGMT-81861A, Para 3.7.1.3.5.7
b. Driving Path - DI-MGMT-81861A, Para 3.7.1.3.5.8
c. Critical Path - DI-MGMT-81861A, Para 3.7.1.3.5.9
d. Free Float / Slack - DI-MGMT-81861A, Para 3.7.1.3.5.14
e. Critical Path / Driving Path - DI-MGMT-81861A, Para 3.7.1.3.7.3, Item 6 All DI-MGMT-81861A paragraphs listed in section 3.7 are applicable to the T-1A AMP unless it references any Formats 1 through 5 or 7, then they are ommitted.
All of the referenced DI-MGMT-81861A paragraphs in this question #393 a) through e) are applicable to the T-1A AMP.
Additional reference is the IPMR Implementation Guide dated January 24, 2013 available at www.acqnotes.com/acqnote/tasks/integrated-program-management-report-ipmr
| 394 | SOW | 7. DI-MGMT-81861A, Para 3.7.1.3.6, requires a 3 point schedule risk assessment be performed for the purpose of a probability analysis of key contract completion dates. This involves calculations of minimum, maximum, and most likely remaining durations for all remaining task durations. | |
| Request the Government confirm that a 3 point schedule risk assessment is required. | A Schedule Risk Assessment is required as per DI-MGMT-81861A Para 3.7.1.3.6. |
Additional reference is the IPMR Implementation Guide dated January 24, 2013 available at www.acqnotes.com/acqnote/tasks/integrated-program-management-report-ipmr
| 395 | SOW | 8. DI-MGMT-81861A, Para 3.7.1.3.6.3, SRA Submission Format - The SRA shall be submitted in Format 5 and is required prior to the Initial Baseline Review. An SRA is required before processing an OTB/ OTS or a single point adjustment. | |
| Request the Government confirm that the SRA submission format and requirements are required. | DI-MGMT-81861A Para 3.7.1.3.6.3 SRA submission format is not applicable as it references Format 5 of the DID. CDRL A008 Remarks directs schedule to be provided in Microsoft Project, additionally it states Contractor format is acceptable. |
Additional reference is the IPMR Implementation Guide dated January 24, 2013 available at www.acqnotes.com/acqnote/tasks/integrated-program-management-report-ipmr.
396 SOW 9. Request the Government confirm that the following earned value metrics are required as specified in DI-MGMT-81861A?
a. Schedule Percent Complete – DI-MGMT-81861A, Para 3.7.1.3.5.3
b. Identify the EV BCWP technique if the schedule is used to directly status the EVM tool – DI-MGMT-81861A, Para 3.7.1.3.7.3, Item 4 DI-MGMT-81861A para 3.7.1.3.5.3 and para 3.7.1.3.7.3 are applicable to the T-1A AMP.
Note: Earend Value Management is not the requirement for the T-1A AMP.
Additional reference is the IPMR Implementation Guide dated January 24, 2013 available at www.acqnotes.com/acqnote/tasks/integrated-program-management-report-ipmr
| 397 | SOW | SOW 8 “The Contractor shall provide a list of affected simulator installation areas.” | |||
| Request the government clarify their expectation as to “affected installation areas” and when does the government require the information? | SOW 8 para 7 "The Contractor shall provide a list of affected simulator installation areas” has been deleted. SOW 8 Paragraph 6 captures the requirement. SOW will be updated through RFP amendment. | KCL Verified | |||
| 398 | SOW | SOW 8 “A draft of the OFT and PTT documentation, identified above [technical and commercial], shall be delivered prior to the start of the OFT and PTT modification. | |||
| It is not realistic to prepare a draft of these documents prior to starting the prototype modification process. Any “ draft” at this point would have to be very basic. | The Government does not intend to change the wording in the SOW. |