RFP Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q As_-_12_Dec_2014.pdf | ||
| Exhibit_B_-_MERC-G_QASP.docx | DOCX document | |
| Atch_3_-_MERC-G_PPQ.docx | DOCX document | |
| Atch_2_-_MERC-G_DD_254.pdf | ||
| Exhibit_A_-_MERC-G_CDRLs.pdf | ||
| Atch_1_-_MERC-G_PWS.docx | DOCX document | |
| FA7022-14-R-0012_MERC-G_Rev_1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question
Number
RFP
Section &
Paragraph
Number
RFP Page
Number(s) Question Answer
11 Section-B CLIN
Series 0003-
3, 8, 13,18, 23, For O&M Training/Travel CLINs:
Does the Government intend to provide a
“plug” number for these Training/Travel
CLINS as was the case with the DRFP? If not, will the government provide planned training/travel details as they apply to PWS
1.3.1 through 1.3.7 and 1.3.9 through
1.3.12 to support costs preparation?
The PWS provides some information, but does not itemize all ODC, materials and travel needed. Since much of this effort is
FFP, the lack of detail does not lend itself to a firm offer.
Amendment to the
Solicitation will be issued with “plug numbers.”
12 Section-B CLIN
Series 0004-
3, 8, 13, 18, 23, 28 For R&D Training/Travel CLINs:
“plug” number for these Training/Travel
CLINS as was the case with the DRFP? If not, will the government provide planned training/travel details as they apply to PWS
1.2.1 through 1.2.3 and 1.2.5 through 1.2.7
Amendment to the
Solicitation will be issued with “plug numbers.”
13 Section-B CLIN
Series 0005
-5005
4, 9, 14,19, 24, For O&M Mission Materials CLINs:
“plug” number for these Materials CLINS as was the case with the DRFP? If not, will the government provide planned material requirements supporting PWS 1.3.1 through 1.3.7 and 1.3.9 through 1.3.12?
Amendment to the
Solicitation will be issued with “plug numbers.”
14 Section-B CLIN
Series 0006-
4, 9, 14, 19, 24, 29 For R&D Mission Materials CLINs:
“plug” number for these Materials CLINS as was the case with the DRFP? If not, will the government provide planned material requirements supporting PWS 1.2.1 through 1.2.3 and 1.2.5 through1.2.7?
An Amendment to the
Solicitation will be issued with “plug numbers.”
15 Section-B CLIN
Series 0008
- 5008
4, 10, 15, 20, 25, 30 For High Interest Panel Support CLINs:
“plug” number for these CLINS as was the case with the DRFP? If not, will the government provide planned requirements supporting PWS 1.3.8?
An Amendment to the
Solicitation will be issued with “plug numbers.”
16 CLIN
Series 0010
- 5010
21, 26, 31 Does the Government intend to provide a
“plug” number for these Travel CLINS as was the case with the DRFP? If not, will the government provide planned travel details as they apply to PWS 1.2.4?
An Amendment to the
Solicitation will be issued with “plug numbers.”
17 Section-B CLIN
Series x005 x006 x008
While Travel COST CLINs clearly identify that there is “no fee allowed”, Material and
HIGH INTEREST PANEL SUPPORT
CLINs simply indicate “COST” without defining whether or not fee is allowable. Is fee allowable on these CLINS? If so, are these CLINs fixed fee?
No, fee is not allowable on
CLINs X005, X006, and
X008. An amendment will be issued to clearly identify that there is “no fee allowed.”
18 Section-L L-II 72 252.215-7009 Proposal Adequacy
Checklist, it states “offerors may elect to have their prospective Subcontractors use the same or similar checklist as appropriate”.
Is there a requirements for our major subcontractors (subcontracts performing over a certain % of work share), to submit sanitized cost or pricing information directly to the Government? If so, what is required?
252.215-7009 Proposal
Adequacy Checklist will be deleted with the issuance of an amendment to the solicitation.
19 Section-L L-II 72 252.215-7009 Proposal Adequacy
Checklist, it states “offerors may elect to have their prospective Subcontractors use the same or similar checklist as appropriate”.
Which volume would you like the Proposal
Adequacy Checklist to be inserted, Volume
I: Administrator, or Volume III Cost/Price.
If in Volume III, does it count towards the page limit?
252.215-7009 Proposal
Adequacy Checklist will be deleted with the issuance of an amendment to the solicitation.
20 H.3 47 How are proposing companies able to enter into an ACA on a contract that has not yet been awarded and until an award, determine which portions of the contract require joint participation in the accomplishment of the Government’s requirement? Is it the Government’s intent that these ACAs are completed and submitted with proposal, or are these completed after contract award?
ACAs are completed after award.
21 Section-L L-III
2F (3)
L-III 4C(2)b
The solicitation (page 82) states “cost or pricing data shall be addressed ONLY in
Cost/Price Proposal and Contracts
Documentation volumes. Part of the
Technical Volume (page 86) states instructions for Sample Problem Scenarios, including cost estimate for work performed. Are we correct in assuming the cost estimate portions of the Sample
Problem Scenarios should be included in
Volume III Cost/Price?
No. The estimates requested as part of the sample problems in the technical volume (page 86) should be submitted with the technical volume. The pricing provided is used to assess technical capability only;
selecting the right materials, quantities and generally relevant costs.
22 Section
L-III 2G & 2H -
L
82 & 83 Section L, Items G & H contains instructions
Do those instructions apply to the offeror’s subcontractors or just to the offeror for the cost volume.
The instructions apply to both the offeror’s subcontractors and the offeror.
23 Section I, 52.219-9, 52.219-16, 52.230-2, 52.230-3, 52.203-6, 252.219-7003, and 252.227-
49, 50, and 51 52.219-9 Small Business Subcontracting
Plan JUL 2013
52.219-9 Alt II Small Business
Subcontracting Plan (JULY 2013)
Alternate II OCT 2001
52.219-16 Liquidated Damages-
Subcontracting Plan JAN 1999
52.230-2 Cost Accounting Standards MAY
52.230-3 Disclosure And Consistency Of
Cost Accounting Practices MAY 2014
52.230-6 Administration of Cost
Accounting Standards JUN 2010
252.219-7003 Small Business
Subcontracting Plan (DOD Contracts)
AUG 2012
252.227-7038 Patent Rights--Ownership by the Contractor (Large Business) JUN 2012
(note: solicitation contains both this clause and FAR 52.227-11) These clauses do not apply to small businesses. Does the Government intend to delete these clauses from the contract at the time of award?
These clauses will be deleted with the issuance of an amendment to the solicitation.
24 PWS 1.3.12 16 Will travel be required for Hydroacoustic
Engineering Management support? If so, will the government include CDRL A003 to 1.3.12?
Yes, travel will be required.
The PWS will be amended to include A003 in paragraph
1.3.12.
25 RFP L-III 4 M-1 87, 93 Is the expectation to define or re-define a software change process? Please confirm that the Section L paragraph should be
“defining” and not “re-defining” the software change process.
(Section L – Software Process) (pg. 87).
Defines, in detail, the methods used in re-defining the software change process
(Section M-Software Process) (pg. 93). To pass the offeror must define, in detail, the methods to be used in the software change process
Section L is amended to include details about the
Sample Problems. The sample problem shows a
Software Change Process issue, and the Software
Change Process requires “re-defining” by the bidder.
26 L-III Table 1.2 81 Note “** Includes up to 10 pages for
Sample Problem Scenarios.”
Please confirm the page limit for Volume
II, Technical Proposal.
We read that the total page limit for this volume is 50 pages and of that, up to 10 pages of this limit may be used for the sample problem scenarios. Confirm that the
10 pages are for “all of the scenarios combined” and “not” 10 pages per scenario
(30 pages).
The requirement is for 10 pages for all of the scenarios combined.