Answers to Questions
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions.docx | DOCX document | |
| FA7000-14-R-0020-0001.pdf | ||
| Site_Visit_Attendance.pdf | ||
| Price_List-2d_Option_Year.xls | XLS spreadsheet | |
| Price_List-1st_Option_Year.xls | XLS spreadsheet | |
| SOW_Protective_Coating_Maintenance_-_01-14-2015.docx | DOCX document | |
| PAST_PERFORMANCE_QUESTIONNAIRE.doc | DOC document | |
| Price_List_-3d_Option_Year.xls | XLS spreadsheet | |
| Price_List-4th_Option_Year.xls | XLS spreadsheet | |
| Davis_Bacon_Wage_Determination_Highway.doc | DOC document | |
| Price_List_-Basic_Year.xls | XLS spreadsheet | |
| Solicitation.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1) With the new amendment stating this contract will support DoD installations within 75 miles, will there be a requirement to have an on-site Project Manager at each base?
No
2) Is there an estimate on the amount of work at the other bases?
No
3) Will claim for mileage be allowed for each task order outside of
USAFA?
No
4) Reference Bid Schedule, Basic Year, CLIN 001, Item A003.
Question: What is meant by "Gypsum wallboard treatment"? Please clarify what work is to be included in this line item. : A: Refer to PWS para.
6.17.1 and also Tech exhibit 2-2.1.5
5) Reference Bid Schedule, Basic Year, CLIN 001, Item A008.
Question: What is meant by "Wood refinishing, wood doors, frames and trim"?
Please clarify what work is to be included in this line item.
Refer to PWS para. 6.17.3 Tech Exhibit 2-2.21.8.5
6) Reference Bid Schedule, Basic Year, CLIN 001, Item A009AC.
Question: What is meant by "Two part 70 plus solids (Vehicle traffic areas)"? Please clarify what work is to be included in this line item.
This is under EPOXY COATINGS and refer to the parts of epoxy per requirement
7) Reference Bid Schedule, Basic Year, CLIN 001, Item A009AF.
Question: What is meant by "Air Gardens (Chlorinated rubber)? Please clarify what work is to be included in this line item.: They are the pools at the terrazzo and need to be painted with the same substance that the swimming pools are painted with
8) Reference Bid Schedule, Basic Year, CLIN 001, Item A012.
Question: What is meant by "Log oil maintenance (obstacle Course)? Please clarify what work is to be included in this line item.: Log oil means the wood weather protective coating for outdoors woods.
9) Reference Bid Schedule, Basic Year, CLIN 001, Items A017AB & A017AC.
Question: Please clarify what is to be included with the Aerial Lift Rental. i.e is mobilization to and from the worksite necessary?; is an operator required? will there be multiple locations?:
This is as need it per job requirements and all that requirements for the operation of the lifts