Price_List-4th_Option_Year.xls

XLS spreadsheet 54 KB Posted

Attached to
Protective Coatings and Pavement Markings Federal contract opportunity
Solicitation number
FA7000-14-R-0020
Issued by
Department of the Air Force Headquarters Air Force Academy

View the file

Other files for this federal contract opportunity

Other files attached to Protective Coatings and Pavement Markings, newest first.
File Type Posted
Questions_1.docx DOCX document
Questions.docx DOCX document
FA7000-14-R-0020-0001.pdf PDF
Site_Visit_Attendance.pdf PDF
Price_List-2d_Option_Year.xls XLS spreadsheet
Price_List-1st_Option_Year.xls XLS spreadsheet
SOW_Protective_Coating_Maintenance_-_01-14-2015.docx DOCX document
PAST_PERFORMANCE_QUESTIONNAIRE.doc DOC document
Price_List_-3d_Option_Year.xls XLS spreadsheet
Solicitation.pdf PDF
Davis_Bacon_Wage_Determination_Highway.doc DOC document
Price_List_-Basic_Year.xls XLS spreadsheet
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

BID SCHEDULE
OPTION YEAR 4 CLIN 4001
The contractor shall furnish all labor, equipment, supplies, supervision and materials, and perform all work in strict accordance with the Statement of Work and technical exhibits for the Protective Coatings Maintenance Contract.
ITEMDESCRIPTIONEST QTYUNITUNIT PRICEAMOUNT
I001Exterior Protective Coatings
I001AAPreparation and prime (or first) coat below 15-ft height250,000SF______________________
I001ABSubsequent coatings below 15 ft height150,000SF______________________
I001ACPreparation and prime (or first) coat above15 ft height67,500SF______________________
I001ADSubsequent coatings above 15 ft height50,000SF______________________
I002Interior Protective Coatings
I002AAPreparation and prime (or first) coat below 15 ft height250,000SF______________________
I002ABSubsequent coats below 15 ft height250,000SF______________________
I002ACPreparation and prime (or first) coat above 15 ft height150,000SF______________________
I002ADSubsequent coats above 15 ft height10,000SF______________________
I003Gypsum wallboard treatment10,000SF______________________
I004Texturing5,000SF______________________
I005Fire hydrants100EA______________________
I006Stencils and Stencil Markings
I006AALettering, (1”- 6”)1000EA______________________
(Each = letter, number, symbol)
I006ABLettering (7"-12")200EA______________________
(Each = letter, number, symbol)
I006ACLettering (13”-24")50EA______________________
(Each = letter, number, symbol)
I006ADLettering (96”-105")20EA______________________
(Each = letter, number, symbol)
I007Graphics1000SF______________________
I008Wood refinishing, wood doors, frames and trim15,000EA______________________
I009Epoxy Coatings
I009AAEpoxy coatings for shower rooms5,000SF______________________
(Waterborne epoxy)
I009ABOne part urethane3000SF______________________
(Pedestrian traffic, shop areas)
I009ACTwo part 70 plus solids5000SF______________________
(Vehicle traffic areas)
I009ADNonslip grit5000SF______________________
I009AEDecorative flakes5000SF______________________
I009AFAir Gardens30,000SF______________________
(Chlorinated rubber)
I010Water blasting1000SF______________________
I011Sand Blasting5000SF______________________
I012Log oil maintenance7500SF______________________
(Obstacle Courses)
I013Painting flag poles
I013AAFlag Poles – 35-50 ft6EA______________________
(Includes rental of lift)
I013ABFlag Poles - 100 ft1EA______________________
(Includes rental of lift)
I014Round trip travel to Farish Memorial
Park and Ellicott Auxiliary Airfield.
I014AAFarish Memorial Park2RT______________________
I014ABEllicott Auxiliary Airfield1RT______________________
I017Aerial Lift Rental
I017A30 - 60 ft. lift5DY______________________
I017AB80 - 125 ft. lift1DY______________________
I017AC19 - 25 ft. scissors lift2DY______________________
Estimated Total Option Year 1:___________

Sheet2

BID SCHEDULE
OPTION YEAR 4 CLIN 4002
The contractor shall furnish all labor, equipment, supplies, supervision and materials, and perform all work in strict accordance with the Statement of Work and technical exhibits for the Protective Coatings Maintenance Contract.
J018Pavements Markings
J019Reflective pavement markings425,303LF______________________
(White roads)
J020Reflective pavement markings482,945LF______________________
(Yellow roads)
J021Reflective pavement markings5000SF______________________
(white stop bars)
J022Reflective pavement markings4224SF______________________
(white crosswalks)
J023Reflective pavement markings500SF______________________
(White traffic arrows)
J024Non-reflective pavement markings335,000LF______________________
(White parking lots)
J025Non-reflective pavement markings200EA______________________
(White handicap LOGOS)
J026Layout40HRS______________________
J027Pavements Markings Removal
Scarifying (hand machine)500LF______________________
Scarifying (industrial truck)1500LF______________________
Estimated Total Option Year 1:___________

Sheet3