This is a Statement of Work (SOW) for premise wiring installation within Building 419 at Pittsburgh IAP ARS, Pennsylvania (Version 4, dated 18 February 2026). The work encompasses engineering, furnishing, installation, and testing of Category 6 cabling infrastructure to support 24 Wireless Access Points throughout the building. The contractor must provide all materials, labor, transportation, management, and tools necessary for completion, with all materials required to be new and not refurbished. The project scope includes installing blue-colored Cat 6 cables as home runs from user drop locations to patch panels in the existing communications closet, with cable runs not exceeding 300 feet in length and terminating in female keystones on both ends. Termination hardware must comply with Leviton EXTREME Cat 6 QUICKPORT specifications (Part #: 61110-BL6). The contractor is responsible for coordinating base support requirements with 911 OG, restoring all disturbed grounds to original condition, and managing all project waste removal in compliance with federal, state, local, and base environmental regulations.
The project performance period shall not exceed three months from start, with work conducted during normal operating hours of 0700-1500, Monday through Friday, excluding federal holidays. The contractor must provide a full-time on-site Project Manager, develop a detailed milestone schedule, conduct weekly IPT meetings with government representatives, and submit deliverables including as-built drawings, work schedules, status reports, meeting minutes, test reports, and test plans. All Cat 6 cabling must be tested and certified to Category 6 specifications with results documented. The contractor shall provide a one-year warranty (manufacturer's standard or longer) plus one-year workmanship warranty commencing from project acceptance. Installation must comply with specified industry standards including BICSI, NFPA 70, ANSI/TIA standards, IEEE 802 standards, and other referenced telecommunications and building codes. The contractor must complete Installation Access Applications for personnel requiring base access and obtain DoD Secret Security Clearance if access to classified areas is required.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK - SOW
FOR
PREMISE WIRING
WITHIN B419
AT
Pittsburgh IAP ARS, PA
Version 4 - 18 February 2026
Attachment #2
1396551515V Highlight
1.0 INTRODUCTION. This Statement of Work (SOW) defines the requirements for the Contractor to engineer, furnish, install and test (EFI&T) premise wiring within building 419 at Pittsburgh IAP ARS.
Newly installed premise wiring will support Wireless Access Points (W AP).
2.0 REQUIREMENTS.
2.1 General Requirements. The Contractor shall provide all materials, transportation, labor, management, tools, and other incidentals necessary to meet the requirements as stated in this SOW. All materials provided shall be new and not refurbished.
2.2 Base Support Requirements. The Contractor must identify any base support requirements (for example, laydown and storage areas) necessary to complete this project. The Contractor shall coordinate with 911 OG for storage space and staging area requirements.
2.3 Restoration. The Contractor shall restore all disturbed grounds/base property to the "as found" condition or better after installation. Base grounds/property restoration requirements shall be complied with.
2.4 Project Residue. All residues from this project shall be disposed off base and IA W Federal, State, local, and base environmental laws and regulations. The Contractor is wholly responsible for project waste removal. Removed premise wiring shall be transported to DRMO on base; premise wiring will be processed for disposition. Contractor may use base Recycling Center to dispose of other project waste materials. Contractor shall verify which waste materials the Recycling Center will accept. Contractor will not use base, facility, or building waste dumpster(s) to dispose of project waste material(s). If Contractor chooses to lease dumpsters for project waste, Contractor shall coordinate with 91OG for dumpster placement.
3.0 COMMODITY REQUIREMENTS. The Contractor shall engineer, furnish, and install the infrastructure as defined herein.
3.1 Converged Communications Requirements: "RESERVED"
3.2 Networking Requirements: The Contractor shall complete the following requirements:
3.2.1 In existing Comm closet, Contractor shall install
3.2.1.1 All Cat 6 cables shall be home run to the locations i,hown on the sketch provided in Attachment 3.
3.2.1.2 All Cat 6 cables shall be blue in color.
3.2.1.3 911 OG will configure and install all network switches and complete the installation of jumper cables from the Cat 6 patch panel to the new switch. The government already has the required equipment.
3.2.1.4 Preferred termination hardware. We have Brand Name Justification letter with
Contracting for Leviton Opti-X and Quickport Fiber and Copper solutions that fits in with existing architecture. Contractor shall verify with 911 OG for latest part numbers.
Leviton EXTREME™ Cat 6 QUICKPORTfM Jack QuickPack, 25-pack, Blue. Part#: 61110-BL6.
DELETED - No wallplates required
1396551515V Highlight
1249666129C Highlight
1249666129C
3.2.2
3.2.3
3.2.4
3.2.5
3.2.6
3.2.7
3.2.8
3.2.9
3.2.10
3.2.11
3.2.12 3.2.13
3.2.14
3.2.15
3.2.17
4.0 MANAGEMENT
4.1 Schedule. The Contractor shall provide a complete milestone schedule that denotes major activities to include time-phased start and completion dates for this project and sub-projects associated with the installation of the components and systems.
4.2 Project Manager on Site. The Contractor shall provide a full time, on-site Project Manager (PM) to oversee all facets of the project.
4.3 Quality Assurance. The Contractor shall provide quality assurance support for the entire life of the project. This support shall assist the government representative in performing random spot checks and in performing the system acceptance tests. Contractor QA and Government Representative shall be responsible for identifying system and outside plant deficiencies and/or discrepancies throughout the life of the project. A weekly report (soft copy) will be submitted indicating project progress/statuses and listings any deficiencies/discrepancies found and actions to correct them.
3.2.16
User drop locations indicated on sketch are approximate. The Contractor shall verify all locations.
Areas indicated in the sketches are composed of various types of workspaces, the Contractor shall verify appropriate hardware required for cable routing, installation, and termination.
Existing cable routes within walls may be reused if within general location of User drop indicated on sketches.
Cable support hardware is already installed in hallways and should be utilized. Rooms may require some cable runs installed per Industry and Installation standards. Table of standards located in section 8.1.
All cables shall be routed in a structured and orderly manner. Secure cable(s) within support hardware i.e. J-hooks or Cable tray.
The Contractor shall fire stop all cable entrances cut, drilled, or cored drilled into walls, per Industry and Safety codes. Table of standards located in section 8.1.
Install plenum rated cables where required by Industry and applicable standards. Table of standards located in section 8.1.
Install CAT 6 cables at the locations indicated in sketches.
All CAT 6 cables shall be "Home Runs" from user drop to patch panel(s). Cable runs shall not exceed 300 feet in length and should end in female keystones on both ends.
As Identified in Attachment one:
3 .2. 11.1 Contractor shall install 24 single drops for Wireless Access Points. Both ends of the CAT 6 wire will terminate in female keystone.
All new CAT 6 cabling shall have a "Blue" colored (T-568B) sheath for identification.
All termination hardware, cable components, and cables shall be CAT 6 compliant.
Termination hardware to include but not limited to termination modules, patch panels, etc.
All cabling and terminations hardware shall be new and not refurbished.
Label all new premise wiring installations with Pittsburgh IAP ARS label scheme. Patch panels, shall all be labeled. Labeling will be completed via permanent method.
Handwritten labeling is not authorized. Labeling scheme provided in Attachment #2 of this SOW.
Test and certify all new cable installations to the Category 6 specifications. Document test results for review and reference.
All working areas shall be restored to original condition IA W Pittsburgh IAP ARS policy.
Mount the rack within the mechanical room required for the patch panel and install the patch panel. Ops will provide the rack that needs mounted and the patch panel that needs installed.
1249666129C Highlight
1249666129C Highlight
1396551515V Highlight
1249666129C Highlight
1249666129C Highlight
1249666129C Highlight
1249666129C Highlight
1249666129C Highlight
1249666129C Highlight
1249666129C Highlight
1249666129C Highlight
4.4 Compliance. The Contractor shall remain in compliance with all Federal, State, county, and base security and safety laws, regulations, policies, and requirements.
4.5 Clean up. At day's end, the Contractor shall remove all debris and surplus materials from the workplace. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard.
4.6 Environmental Management. The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations, and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The installer shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Pittsburgh IAP ARS. The Prime Contractor shall ensure their sub-contractors (if any) comply with these specifications. Asbestos may be present at all buildings within the scope of this project. But the presence of asbestos along, adjacent, or within existing cable runs is not anticipated. If asbestos is discovered during the installation phase of this project, the Contractor shall stop work and contact 911 OG for disposition.
4.7 Integrated Product Team (IPT). The Contractor shall chair a weekly IPT meeting consisting of Contractor representatives, the Contracting Officer, Program Manager, Engineer, and representatives of the 911 Operations Group. The purpose of this meeting is to discuss project progress, problems being encountered, and other discussions necessary/beneficial to ensure success and timely completion of the SOW.
4.8 Walk-Through. The Contractor shall schedule a final project walk-through of all work completed prior to close out with the government Project Manager. This should be scheduled at least 72 hours prior to the event.
5.0 DELIVERABLES.
5.1 List of Deliverables. All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth in this Task Order. All deliverables shall be produced using recommended software tools/versions as accepted by the Government. The Contractor shall submit the following deliverables:
Data Item Title
As Built
Work Schedule
Status Report
Meeting Minutes
Test Report
Test Plan
5.2 Cutover Plan: Reserved.
5.3 Acceptance Test Plan: The Contractor shall provide a detailed acceptance test plan of the installation covering all aspects of the installation and demonstrate the acceptability of the work on meeting the government requirement. The Contractor shall perform all tests and document results of tests with government witnesses overseeing the Acceptance testing.
5.4 As-Built Drawings: The Contractor shall provide as-built drawings for the installed equipment to include where and how they connect/interface with each other and existing base.
5.5 Training: Reserved.
5.6 Testing Requirements: The Contractor shall perform testing and inspections of all CAT 6 cable ran to ensure there are no breaks/kinks/severs. The Contractor shall conduct on-site testing in accordance with the Original Equipment Manufacturer's installation manuals, practices and the appropriate vendor's test procedures. The Contractor shall provide test results. The 911 OG will ensure the system is working and verify with AFRC (approx 72 hours). After verification of system operation with AFRC, the OG will contact the vendor to schedule removal of old wiring.
6.0 WARRANTY
The vendor shall provide a one-year warranty or manufacturer's standard commercial warranty, whichever is longer. The vendor shall also provide a one-year workmanship warranty. The warranty period shall start from the date of system and or project acceptance.
7.0 PERFORMANCE.
7.1 Period of Performance. The period of performance for the project shall not exceed three months after the start of the project.
7.2 Place of Performance. The place of performance is Pittsburgh IAP ARS.
7.3 Hours of Work. The Contractor shall routinely work during normal operating hours 0700- 1500.
Monday through Friday, excluding federal holidays. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated with the 91 lOG, Contracting, and B419 building users at least two working days in advance. The Contracting Officer must be notified in advance if there is any cost impact for this work
1396551515V Highlight
1249666129C Highlight
9.0 SECURITY
9.1 Stated work and associated products shall be perfonned at the UNCLASSIFIED level. However, when access to classified areas may be required, selected personnel who install network equipment, test network equipment and cutover network equipment may be required to obtain a minimum of DoD Secret Security Clearance. Escorts may be required, as some work will be perfonned in secure facilities. It is the Government's responsibility to provide escorts.
9.2 The Contractor shall process a Site Visit Request Letter before access to the 911th AW. This letter shall identify the names, social security numbers, driver's license numbers and state of issue, and birth date of the personnel who will be perfonning on this SOW. This infonnation is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations.
Complete Installation Access Application fonn (Refer above 9.2). Access requests should be made through 911 OG. Access requests shall be submitted at least one (1) week prior to scheduled arrival.
10.0 ENVIRONMENTAL PROTECTION & OCCUPATIONAL HEALTH SAFETY STATEMENT
10.1 See ESOH statement attached to this solicitation which the contractor is required to sign and acknowledge.
Attachment #3
See B419 (Ops) Juniper Both Floors (18 February 2026)
Pittsburgh IAP ARS LAN CAT 6 cable Labeling Standard
1.1 Cable labeling
1.1.1 All Cables will be labeled with the patch panel letter and port number matching the position on the patch panel. The 911 OG will assist in labeling standard. EXAMPLE: J-01, J-02, ect.
Patch panels will be Labeled as the following: A, B, C, etc.
Attachment #4
See ENVIRONMENTAL PROTECTION & OCCUPATIONAL
HEALTH SAFETY STATEMENT (ESOH)