Attachment 32 Additional Questions and answers.docx

DOCX document 18 KB Posted

Attached to
Fiber Optic Cable Install - Qty 6 Federal contract opportunity
Solicitation number
FA671223Q0014
Issued by
Department of the Air Force Reserve Command

About this file

This document contains answers to additional questions on a solicitation for fiber optic cable installation projects at various locations on an Air Force base. The scope of work involves the engineering, furnishing, installation, and testing of new fiber optic cable runs between six locations on base, including between manholes and buildings. The Air Force will provide a secure area for equipment staging and the contractor is responsible for obtaining any permits required for the work. Spoils from excavation can be pumped into storm drains unless contaminated and must be tested before off-base disposal. The contractor will install new innerduct, conduit, and splice boxes as detailed and terminate cables on adapter panels or splice cassettes as specified. Handhole locations and sizing will be at the contractor's discretion with input from the civil engineer.

View the file

Other files for this federal contract opportunity

Other files attached to Fiber Optic Cable Install - Qty 6, newest first.
File Type Posted
Attachment 31 Davis Bacon Act WD PA20230001 Rev 7 Building 07 28 2023.pdf PDF
Attachment 30 Wage Determination 2015-4235 Rev 24 6 30 2023.pdf PDF
Attachment 29 Site Visit Questions and answers.docx DOCX document
Attachment 6 Offer Pricing Template r1.pdf PDF
Attachment 26 SOW FOC from B202 to Marquee.docx DOCX document
Attachment 27 GD11014od01CG (107 HH).pdf PDF
Attachment 25 List of Attachments r1.xlsx XLSX spreadsheet
Attachment 28 EB 00202.pdf PDF
Attachment 3 SOW FOC from ITB 221 to B419 V2.docx DOCX document
Attachment 6 Offer Pricing Template.pdf PDF
Attachment 11 ITB 00221.pdf PDF
Attachment 25 List of Attachments.xlsx XLSX spreadsheet
Attachment 15 GD13013od01(MH1A 2 4 5 6 HH20).pdf PDF
Attachment 2 SOW FOC from ITB 221 to B317 V5.docx DOCX document
Attachment 4 SOW FOC from ITB 405 to ITB 221 v3.docx DOCX document
Attachment 7 AF1024 Confined Space Entry Permit.pdf PDF
Attachment 17 GD13014od01 (MH14 208 208A 210 HH21 220).pdf PDF
Attachment 20 ITB 00405.pdf PDF
Attachment 22 GD12014od02CG (MH 125).pdf PDF
Attachment 5 SOW FOC from ITB 405 to B120 V5.docx DOCX document
Attachment 8 Silica Control Plan.pdf PDF
Attachment 12 GD13013od02CG (HH304A 306 306A 306B 403 MH301).pdf PDF
Attachment 21 GD12014od01CG (HH2-6 MH 121).pdf PDF
Attachment 1 SOW FOC from ITB 221 to B209 V6.docx DOCX document
Attachment 9 GD13014od01 (MH14 208 208A 210 HH21 220).pdf PDF
Attachment 10 GD13014od02CG (MH213 218 221 221A HH300).pdf PDF
Attachment 14 GD13013dd01 (419 411 306 316 316a 333).pdf PDF
Attachment 16 GD13013od03CG (MH316 316A 411 418 419A419B).pdf PDF
Attachment 18 GD13014od02CG (MH213 218 221 221A HH300).pdf PDF
Attachment 19 GD14014od01CG (MH4A 221 B324).pdf PDF
Attachment 24 AF FORM 103 Work Clearance.pdf PDF
Show all 31

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No.

RFP Ref Section No. & Title
RFP Ref

Page No.

Question

1
Attachment 1 – PWS for ITB 221 to B209
2 of 19
The scope is the engineering, furnishing, installation, and testing of fiber optic cable. Are the applicable USAF / 911 CS/SCXP engineering and construction standards available for review? Page 12 2.2.8.2.1 has testing requirements.
2
Attachment 1 – PWS for ITB 221 to B209
2 of 19
Will existing cable maps, manhole diagrams, and floorplans be furnished to the awardee in electronic format to serve as the basis of the engineering? NO
3
Attachment 1 – PWS for ITB 221 to B209
Section 2.1.2.3
Will the base provide a secure area for the staging of construction equipment and materials? YES
4
Attachment 1 – PWS for ITB 221 to B209
Section 2.1.4
Will a NPDES permit, or an environmental assessment be required? NO
5
Attachment 1 – PWS for ITB 221 to B210
Section 2.2.1.1
If water is discovered in existing manholes can it be pumped into the stormwater sewers? YES

Unless there is oil etc in the water then Bio will need to be notified. This has not been an issue to date

6
Attachment 1 – PWS for ITB 221 to B209
Section 2.1.4
Are there any known areas of environmental concern in the planned excavation pathways? NO none of the projects reside in a area of environmental concern
7
Attachment 1 – PWS for ITB 221 to B209
Section 2.2.3
Is there a dump site on base for the disposal of excavation spoils? NO
8
Attachment 1 – PWS for ITB 221 to B209
Section 2.2.3
Must excavation spoils be tested for contaminants before dumping? If there is any off site dumping it will be at the discretion of that location
9
Attachment 1 – PWS for ITB 221 to B209
Section 2.2.2.1.2
The table in the section lists (1) 4" duct between MH-210 and B209. The drawing included in this attachment includes a note requiring (2) 4" ducts. Please clarify. ONLY 1 DUCT
10
Attachment 1 – PWS for ITB 221 to B209
Section 2.2.2.1.3
Is the Geotextile Innerduct requirement for (1) 3" 3-pack, (2) 3" 3-packs, or (3) 3" 3-packs?

(1) 3” 3-PACK

11
Attachment 1 – PWS for ITB 221 to B209
Section 2.2.2.1.3
This section calls for Corning CCH-CP-12-3C adapter panels. These are 12-port simple SC UPC panels for OS2 cable. These would require pigtails spliced to the OSP cable in a splice tray and then routed to the rear of the adapter panel. Is this the intent? Can splice cassettes with the same ports be utilized? Follow device requests as listed
12
Attachment 1 – PWS for ITB 221 to B209
Section 2.2.2.2.1
The table in this section mentions new 1" corrugated innerduct, but this is not described in the writing. Is the contractor to provide & install this innerduct? YES provide and install
13
Attachment 2 – PWS for ITB 221 to B317
Section 2.2.2.2.1
This section states that an existing cable in HH 306 is already terminated in ITB 221. Is there an existing splice case in HH 306 that will be opened by the contractor? Is the contractor to splice the new 12-strand SM FOC to an existing cable in HH 306? Yes there is a splice box. Contractor will have to tone back to 221 to verify which cable to use. Per 38th.
14
Attachment 4 – PWS for ITB 405 to ITB 221
Section 2.2.2.2.1
The table in this section mentions new 1" corrugated innerduct, but this is not described in the writing. Is the contractor to provide & install this innerduct? YES provide and install
15
Attachment 5 – PWS for ITB 405 to B120
Section 2.2.2.2.1
The table in this section lists conduit in B120 from the Mechanical Room to the termination point, but this is not described in the writing. Is this existing, or is the contractor to provide & install this conduit? What type & size? YES provide and Install 1” metal conduit throughout.

16. Is there a specific size hand hole the 911th wants installed? (405 to B120)

The placement of a handhold would be at the discretion of the contractor. They have the option to go straight into the bldg. If they chose to install a HH then per CE they would like to have them make it a small one. ( lawn tractors could break a large ones lid) The only other requirement is that it be flush to the ground.

17. Need clarification on 2.2.2.1.4 Duct Bank Infrastructure No mention of new HH206. (405 to B120)

The placement of a handhold would be at the discretion of the contractor. They have the option to go straight into the bldg. If they chose to install a HH then per CE they would like to have them make it a small one. ( lawn tractors could break a large ones lid) The only other requirement is that it be flush to the ground.

18. What is the proposed location for new HH206A? (405 to B120)

The placement of a handhold would be at the discretion of the contractor. They have the option to go straight into the bldg. If they chose to install a HH then per CE they would like to have them make it a small one. ( lawn tractors could break a large ones lid) The only other requirement is that it be flush to the ground.