Questions/Answers for Tab A (should have been attached to Amendment 0007)

View the file

Other files

File Type Posted
SCA_Wage_Determination_2015-4235.pdf PDF
FA6712-16-R-0001-0009.pdf PDF
FA6712-16-R-0001-0008.docx DOCX document
WD_PA170001.pdf PDF
WD_PA170004.pdf PDF
Q&A_Pittsburgh_Tab_C_response_28_Dec.docx DOCX document
Summary_of_changes_29_Dec_2016.docx DOCX document
NEW_CBA_-_Pittsburgh_-_01_Feb_2017_to_31_Jan_2018_-_Final_-_Signed_-_recd_20_Dec_2016.pdf PDF
Q&A_Pittsburgh_Tab_B_Response_Dec_28_2016.docx DOCX document
FA6712-16-R-0001-0007.pdf PDF
Pittsburgh_BOS_PWS_Rev_2,_Jan_3_2017.docx DOCX document
Q&A_Pittsburgh_Tab_F_28_Dec_2016.docx DOCX document
Pittsburgh_BOS_PWS_Sep__2016.docx DOCX document
Atch_16_Revised_GFP_data_7_Sep_2016.xls XLS spreadsheet
FA6712-16-R-0001-0006.docx DOCX document
Conformed_FA6712-16-R-0001.docx DOCX document
Pittsburgh_Attachment_11_Pricing_Matrix_Rev_3,_5_Dec_2016.xlsx XLSX spreadsheet
Pittsburgh_BOS_PWS_Sep__2016.docx DOCX document
Pittsburgh_BOS__WD_PA4.txt TXT text file
Pittsburge_BOS_WD_PA1.txt TXT text file
Amend_0005.pdf PDF
FA6712-16-R-0001-0004.pdf PDF
FA6712-16-R-0001-0003.pdf PDF
FA6712-16-R-0001-0002_Conformed_Copy.pdf PDF
Attach_11_-_Pricing_Matrix_Rev_1_7_Jan_16_.xlsx XLSX spreadsheet
FA6712-16-R-0001-0002.pdf PDF
FA6712-16-R-0001_0001.pdf PDF
Site_Visit_Memo_Rev_1_-_Pittsburgh.pdf PDF
Atch_2_-_PPC_Brief_18_Nov_2015.pptx PPTX presentation
F-TE-7-D-1_ELECTRIC_DISTRIBUTION_PLAN_2015.pdf PDF
F-TE-7-C-5_AIRFIELD_MARKING_2015.pdf PDF
F-TE-7-C-8_BASE_STREETS_SNOW_REMOVAL_PRIORITY_MAP_2015.pdf PDF
F-TE-7-C-7_AIRFIELD_SNOW_REMOVAL_PRIORITY_MAP_2015.pdf PDF
F-TE-7-A-2_SNOW_PLOW_STAKES_2015.pdf PDF
Atch_3_-_Pittsburgh_ARS_Site_Visit_Agenda_-_18Nov2015.pdf PDF
C-F-TE-7-C-1_C-2_GROUNDS_MAINTENANCE.pdf PDF
F-TE-7-E-3_STORM_DRAINAGE_SYSTEM_2015.pdf PDF
F-TE-7-A-1_LANDSCAPING_PLAN_2015.pdf PDF
Atch_1_-_Pittsburgh_BOS_site_visit_Sign-in_Roster_from_18Nov2015.pdf PDF
Snow_Removal_Plan_2015.pdf PDF
F-TE-7-L_BASE_WATER_OUTFALL_INFALL_MAP_2015.pdf PDF
F-TE-7-E-2_SANITARY_SEWER_SYSTEM_2015.pdf PDF
F-TE-7-D-2_AIRFIELD_LIGHTING_2015.pdf PDF
2015_Integrated_Pest_Management_Plan2.pdf PDF
F-TE-7-E-1_WATER_SUPPLY_SYSTEM_2015.pdf PDF
F-TE-7_BASE_PLOT_PLAN_2015.pdf PDF
F-TE-7-G_LIQUID_FUEL_SYSTEMS.pdf PDF
F-TE-7-H_GAS_DISTRIBUTION_SYSTEM_2015.pdf PDF
F-TE-7-C-3_C-4_PAVEMENT_SWEEPING_PLAN_2015.pdf PDF
911ARS_BaseMap_WasteWaterUtilityNode_2015.pdf PDF
Show 40 more

Latest 50 of 74 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PITTSBURGH BOS

TAB A QUESTIONS

1. Reference PWS paragraph A.3.2.4; the paragraph ends with the statement, “(See A-TE-3, A?).”

Question: Where, exactly, is this reference meant to be taking us? PWS revision resolves this

2. Reference PWS paragraph A.3.2.6; as one of the four new paragraphs added to the PWS (A.3.2.3 – A.3.2.6), the paragraph references the use of Management Internal Control Toolset (MICT) or current annual self-inspection program.

Question: Is either of these programs Government furnished? Yes, programs are web based and access will be given to awardee

3. Reference PWS paragraph A12.3; the last sentence reads: “The KTR shall provide secure storage area for reserve member owned tools and equipment within or adjacent to the training facility.”

Question: What is meant by “secure storage area” and who will be financially liable if AF Reserve member-owned tools and equipment are missing from these areas? There are secure areas for storage. Reservists are accountable on UTA weekends; contractor is accountable other times

4. Reference PWS paragraph A12.6; which reads: “The KTR shall take appropriate precautions to safeguard any materials made available to Government personnel during these training periods.”

Questions: What is meant by “appropriate precautions?” Will the Government personnel be liable for the materials used during their training? Please explain. Same as 3 above

5. Reference PWS paragraph A18.10; Publications and Forms; as the KTR is responsible question 3 for managing the TODO and TODA:

a. Question: please provide the number of books that the KTR will be responsible for. Total TOs is 160, spread throughout functional areas

b. Question: Is the library centrally located or is it just an area found within the different TAB admin areas? Each functional area has a TO library, with majority managed in Tab C & G

6. Reference PWS paragraph A-TE-4b.1 Parts Cost:

Question: Are the snow plow blade related parts included in the TAB A provided parts costs? yes, blades are parts