Sheet CI101 calls for a new bollard (if needed) at the existing transformer. Please clarify whether or not a new bollard is required.
A new bollard will be needed based on the electrical connection work accomplished by the contractor.
Detail B1 on Sheet C501 states sidewalks shall be 4” thick (unreinforced), however Detail B4/C- 501 of the comm relocation set call for 6x6 WWF. Please clarify which will be required.
Use 6x6 WWF.
Sheet L-101, keynote L4 call to replace all disturbed turf with new matching sod, however the civil drawings on both renovation/addition and comm relocation call for hydromulching these areas (CI101 general note 5, and CS101 general note 5). Please clarify if sod or hydromulch will be required.
Sod or hydro-mulching is acceptable as long as an even grass surface is maintained with the finish grass.
General note 1, on sheet A-101 states the contractor is to coordinate with the KO and building user and remove, store and protect existing furniture, cabinetry, and equipment and return to designated location upon project completion.
Existing room 114/113 contains multiple file cabinets, and existing room 107 is a locker room. If the Government is requesting the contractor to store, protect and reinstall these units, then please clarify the extent of this scope and provide approximate quantities of furniture, cabinetry, and equipment to remain.
Government will move and store furniture.
Please advise us if a full conduit system will be required for the fire alarm and mass notification system.
Full conduit is required for the alarm and mass notifications system.
Keynote M3 on M-101 calls to obtain EH-1 from base personnel and install. Would it be possible to obtain a cutsheet or make/model of the EH in advance?
CONTRACTOR WILL PROVIDE and install EH-1.
PT-B1 is labeled a porcelain base tile 6 x 12. PT-B2 is labeled ceramic tile cove base 4” height.
Dal Tile does have a 6 x 12 cove base in Plaza Nova, but not a 4” high cove base. Would it be better to just use the 6 x 12 cove base where it calls for PT-B1?
Use the 6 x 12 cove base where it calls for PT-B1.