SOW POL Pickle System dated 12 July 2010.pdf

PDF 151 KB Posted

Attached to
Pickle POL Lines
Solicitation number
FA6670-10-Q-0039
Issued by

About this file

SOW POL 13 July 2010

View the file

Other files

File Type Posted
QUESTIONS 4 Pickle POL Lines.doc.docx DOCX document
QUESTIONS 3 Pickle POL Lines.pdf PDF
QUESTIONS 2 15 July 2010 POL.pdf PDF
POL Wage Determination 2005-2371 rev 11 6-15-2010.pdf PDF
POL Price Sheet.pdf PDF
POL Questions - 1 13 July 2010.pdf PDF
POL SOW.pdf PDF
POL Transfer-Hyddrant Lines.pdf PDF
POL Price Sheet.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

RVKQ 10-0485

Pickle POL Lines

03 June 2010

1.1 GENERAL

The contractor shall provide all plant, labor, material, and equipment necessary to complete the work described below and in the contract drawings and specifications at the 914th Airlift Wing, Niagara Falls, New York, 14304.

1.2 DESCRIPTION OF WORK

1.2.1 The work to be accomplished by the contractor shall include, but not be limited to, the following items:

1.2.1.1 The emptying/removing of JP-8 from a hydrant system loop and a transfer line.

1.2.1.1.1 Empty and gas free entire pipe lines. The Contractor is responsible for reclaiming all fuel contained within the pipe lines. All residual/waste product/sludge and wash water shall be properly disposed of by the Contractors qualified personnel or sub-contractors in accordance with all current state and federal requirements for proper manifesting, handling, transporting, and disposal of hazardous waste.

1.2.1.2 Contractor shall:

1.2.1.2.1 Drain, clean (pig) and vapor free the fuel system piping. All fuel will be reclaimed by pushing fuel into the 107 th aboveground tanks directly from the piping or by offloading directly into the

Government’s fuel tanker trucks with the use of the Contractor’s own pumping equipment.

1.2.1.2.2 Drain the 6” transfer line (approximately 1 mile in length) by pigging the line. Using pig launchers from the 914th end of the system, push fuel into one of the 107th aboveground fuel tanks.

1.2.1.2.3 Drain the hydrant loop (approximately 0.5 miles in length) at a low point drain or remove a hydrant control valve at the lowest part of the system and install a 4” flange with 2” kamlock to remove all fuel using a contractor provided pump into a tanker truck. All fuel from the tanker shall be delivered to the 914 th POL and offloaded by the POL operator(s). At the 107 th end, disconnect transfer line in the pump-house; cap/blind flange each open end. The blind flanges shall be painted to match the existing piping color, within the 107 th POL pump house.

1.2.1.2.4 AS AN OPTION AS FUNDING PERMITS - Fill the entire transfer and hydrant fuel pipe lines with nitrogen gas once the fuel is evacuated from the fuel pipelines.

1.2.1.3 At the 914

th end, the contractor shall disconnect the transfer line from the tee connection prior to the filter separator (located in the pump house) and place a blind flange at that tee connection point. Paint the blind flange to match the existing pipe color, within the 914

POL pump house.

1.3 REFERENCES (Not Applicable)

1.4 SUBMITTALS - Furnished by Contractor prior to startup

1.4.1 Environmental Protection Plan

1.4.2 The Contractor’s waste disposal process; accumulating, storing/packaging, manifesting, transporting, method of disposal, etc.

1.5 CONTRACT DOCUMENTS

1.5.1 The following sketch accompanies this specification and are a part thereof:

- Plan of Base indicating route of Transfer and Hydrant Pipelines.

1.6 WORK RESTRICTIONS

1.6.1 The contractor shall not be allowed to work on Federal Holidays.

1.7 NORMAL DUTY HOURS

1.7.1Normal duty hours for work shall be from 7:15 a.m. to 4:00 p.m., Monday through Friday. Requests for additional working hours, beyond the normal duty hours, shall be submitted by the Contractor to the

Contracting Officer 7 days in advance of the proposed work period. This request for additional time shall require written approval from the Contracting Officer.

1.8 NOTICE TO COMMENCE WORK

1.8.1 The contractor shall give the Contracting Officer or his representative a 48 hour notice of the contractor's intent to commence work.

1.9 DAILY SIGN-IN

1.9.1 Prior to starting work each day, the Contractor and/or Subcontractor must fill out the Sign-In

Sheet located at the 914th AW, Base Civil Engineer's Office, and Building 403.

1.10 NOT USED

1.11 ON-SITE PERMITS

1.11.1 Utility Outages and Connections

1.11.1.2 Work shall be scheduled to hold outages to a minimum. The Contracting Officer may permit outages at his discretion.

1.11.1.3 Requests for utility outages and connections shall be made in writing to the Contracting Officer at least 7 working days in advance of the time required. Each request shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.

1.11.2 Borrow, Digging, Welding, and Burning Permits

ACTIVITY SUBMISSION DATE SUBMISSION FORM

Borrow 10 days prior to work from Base Civil Eng. Bldg. 403 AF 103

Digging 10 days prior to work from Base Civil Eng. Bldg. 403 AF 103

Welding Each day prior to work from Base Fire Chief, Bldg. 821

Burning Each day prior to work from Base Fire Chief, Bldg. 821

1.11.2.1 Permits shall be posted at a conspicuous location in the working area.

1.11.2.2 Permits are the property of the Government and shall be returned to the Contracting Officer upon completion of permitted work.

1.11.2.3 The contractor is responsible for hand excavation within three (3) feet from either side of all known underground utilities that have been either staked or marked from the scaled drawings.

1.11.2.4 Burning of trash or rubbish is not permitted.

1.12 REMOVAL OF WASTE MATERIAL, Hazardous and Non-hazardous

1.12.1 The Contractor shall be held liable financially for any penalties or fines imposed on the Base due to the negligence or improper storage, manifesting, transporting, or disposal of hazardous waste materials by the contractor’s or sub-contractor’s personnel.

1.12.2 During the progress and at the completion of work, all refuse and waste material shall be removed from Government property and disposed of in accordance to and adherence to Federal, State, and Local environmental regulations. If waste material is not removed daily, the contractor shall provide a covered waste container at his expense.

1.13 UTILITIES

1.13.1 Electricity and water shall be provided by the Government. Any extension of, or connections to, the existing lines and their removal will be at the expense of the Contractor. All connections to existing utilities, if necessary, shall be coordinated with the Government. The Contractor is responsible for supplying his own restroom facilities.

1.14 ENVIRONMENTAL REQUIREMENTS

1.14.1 Any questions concerning environmental conditions or problems can be referred to 914th

AW/CEV at 236-3126.

1.14.2 Spills and Spill Reporting: The contractor is responsible for cleaning-up any spills caused by the contractor or its agents to the satisfaction of the 914th AFRC Environmental Office and at no cost to the government. Niagara Falls Air Reserve Station (NFARS) shall be responsible for the disposal of any spill waste generated during the project and the contractor shall reimburse NFARS for the disposal costs of such wastes. NFARS will be considered to be the generator of such wastes for purposes of disposal. The contractor shall maintain spill equipment and materials sufficient to handle the containment and clean-up of spills in the capacity of the project. The contractor must immediately report any and all spills or leaks to the 914th AW Fire Department at 911 from a base phone or 716-236-2117 by cell phone. In the event of a spill, the following information shall be reported:

- Description and amount of material spilled.

- Location of the spill (i.e. bldg. number, street name, room number, etc. )

- Name of the person reporting the spill (with location and telephone number where they can be reached.)

- How the spill occurred.

- The estimated time of the spill and the time the spill was discovered.

- What has been done to stop the spill and has any personnel been evacuated. What natural resources were affected. Did the spill effect any water resources or enter any storm or sanitary sewers?

1.14.3 The contractor shall be required to restore, repair or otherwise replace any and all damage that occurs as a result of the Contractor’s work at no additional cost to the government.

1.14.4 After work has been completed, but before the contract is considered final, the contractor shall submit a report to the Base Contracting Officer specifying the hazardous materials used and quantities.

1.14.5 All work shall stop immediately if contractor discovers unspecified asbestos or other regulated wastes during the course of the project, and contractor shall notify the Base Contracting Officer. All certifications, including transportation and disposal paperwork, needs to be authorized by CEV prior to removal.

1.14.6 All work shall stop immediately if contractor discovers hazardous wastes during the course of the project, and contractor shall notify the Base Contracting Officer.

1.14.7 If there is an unanticipated discovery of cultural resources (such as arrowheads, pottery pieces, building foundations, etc.) during the project or if the unanticipated discovery involve human remains, then activities shall stop and the Base Contracting Officer should be notified immediately.

1.14.8 Hazardous or regulated wastes shall be disposed of in the following manner:

On-Base: - Contractor calls 914th AW/CEV at 236-3124.

- CEV will provide proper HW container(s) to contractor.

- Contractor places labels/markings on containers and fills them as needed.

- Contractor contacts CEV to deliver waste containers into Building 830 (HW storage facility).

- CEV disposes of waste through DRMO contract.

1.14.8.1 JP-8 Jet Fuel in either its liquid form or absorbed into absorbent pads, booms or speedy-dry to create a waste solid are the only waste-streams expected to be generated from the work described herein.

The flashpoint of JP-8 is 100-degrees Fahrenheit, below the EPA minimum limit of 140-degrees for hazardous waste (HW). Therefore it has the EPA Waste Code or Number D001 due to its ignitibility characteristic. The reportable quantity for ignitable waste is 100 lbs. If disposed of, the DOT shipping name for JP-8 waste (in either liquid or absorbed form) is: Fuel, Aviation, Turbine Engine (JP-8 Jet

Fuel); Hazard Class 3, UN1863, Packing Group III. Emergency Response Guide (ERG) page number is

128. 55-gallon metal drums are the most common storage/shipping containers for this type of waste.

Reconditioned drums may be used for storage, but any containers used for shipping hazardous waste off-base to a disposal facility must meet DOT performance oriented packaging specifications outlined in 49

CFR. Should any HW be generated and stored in containers, the containers must be immediately labeled with a red HW adhesive label stating the contents and the date the waste was placed in the container. A diamond-shaped flammable liquid/solid HW class label should also be placed on the container. HW containers must be kept securely closed (so nothing would escape if container was tipped on its side) unless adding or taking waste from the container. The contractor must contact 914 CEV immediately when HW containers become full and turn-in such container(s) to CEV at B-830 (HW storage facility) within three (3) working days of becoming full. CEV will arrange for the HW container to be transported and delivered to an EPA-permitted Treatment, Storage or Disposal Facility (TSDF) within 90-days from the date HW was first placed in the container.

1.14.8.2 914 MSG/CEV is considered the generator of any hazardous waste liquid, sludge, or solids resulting from this scope of work. Accumulation, disposal, transport and handling of said waste materials shall be in accordance with all applicable local, state and federal and Air Force regulations.

1.14.8.3 All site personnel shall be required to submit a copy of their 40 HR. HAZARDOUS WASTE

SITE WORKER CERTIFICATE for review and approval by 914 AW/CEV personnel prior to beginning any work.

1.14.9 The contractor shall perform all work in a fire-safe manner in accordance with Niagara Falls ARS fire prevention standards available from Base Fire Department.

1.14.10 Portable fuel dispensing equipment and the dispensing of fuel, which includes diesel, unleaded gasoline, and propane, are not allowed on base unless prior written approval is obtained from the Base

Contracting Officer or his designated representative.

1.14.11 No Ozone Depleting Chemical (ODC) containing materials are allowed.

1.14.12 Contractor shall submit a Stormwater Pollution Prevention Plan (SWPPP) for approval by the

Contracting Officer and 914th AW/CEV prior to start of the project. For project activities with soil disturbance less than one acre, a SWPPP shall be developed in accordance with the “Niagara Falls ARS

Guidance for Stormwater Pollution Prevention/Erosion & Sediment Control Plan for Disturbances that are Less than One Acre”, most recent version. The Contractor shall be responsible for compliance with the SWPPP and all reports and documentation described within the SWPPP. The aforementioned guidance is available from the 914th AW/CEV (Environmental Office).

For project activities with soil disturbance equal to or greater than one acre, a NYSDEC SPDES General

Permit for Stormwater Discharges from Activity, GP-0-10-001 (or most recent version), shall be obtained.

The Contractor shall be responsible for compliance with this permit. The Contractor shall be responsible for all reports and documentation needed to comply with this permit including, but not limited to: the

Notice of Intent, SWPPP, inspection reports, NOT. The Contractor shall prepare all permit related documentation for approval by 914th AW/CEV or 914th AW/CEV designated entity prior to start of project activities. 914th AW/CEV or 914th AW/CEV designated entity shall submit all permits and permit applications, etc. to the appropriate regulatory authorities unless otherwise agreed upon between the Contracting Officer, 914th AW/CEV, and Contractor.

1.14.13 Contractor shall use recovered materials to the maximum extent possible. The Contractor shall divert a minimum of 50% by weight of total project solid waste from landfill disposal. The Contractor shall submit Solid Waste Diversion Reports to the Contracting Officer and 914

AW/CEV on the first working day after each quarter that non-hazardous solid waste has been disposed and/or diverted and shall be for the previous quarter (e.g. the first working day of January, April, July, and October). The report shall state the project name, project number, project duration, contractor name, name of contact, and phone number. Additionally, the report shall include the date the waste was disposed, waste type (i.e.

scrap metal, concrete, construction debris, etc.), disposal method (landfill, recycle, incineration, etc.), disposal location (facility name, city, state), total amount (in tons), and cost of disposal for waste generated. The contractor shall not use on base solid waste or recyclable containers unless prior written permission from the base 914th AW/CEV has been received.

1.14.14 Contractors shall certify that they have reviewed the HAZMAT Plan prior to commencing work and received a copy of the Quick Reference section of the plan. Contractors shall receive a briefing about spill response and reporting requirements as presented in the HAZMAT Plan.

PART 2 PRODUCTS

2.1 MATERIALS

2.1.1 Unless otherwise specified, all materials used for this contract shall be new and unused.

PART 3 EXECUTION (Not Applicable)

PART 4 SPECIAL CONDITIONS

4.1 The Contractor shall repair any structures, pavement, etc. that are moved, disturbed or damaged, by the Contractor’s operations, at no additional cost to the Government.

-- End of Section –