YTPM 24-0012 RFI 001_Repair HVAC Chiller B7087-signed.pdf
PDF 385 KB Posted
- Attached to
- Repair HVAC Chiller B7087
- Solicitation number
- FA660626B0003
About this file
This is a Request for Information (RFI) report documenting a contractor's query regarding equipment specifications for a federal HVAC repair project.
The RFI (No. 001) was submitted on 22 July 2026 by 439 CONF/PKB for KTR(s) in response to Solicitation No. FA6606-26-B-0003, titled "Repair HVAC Chiller B7087 YTPM 24-0012" for Project Name 439 CONF/PKB for KTR(s). The contractor questioned whether the chiller specification should be updated from Carrier Model 30RAP030 (listed in Statement of Work Section 3.1) to Carrier Model 30RC030 with R-32 refrigerant, noting that the original model is no longer manufactured. The WARB (likely the government contracting office) affirmed this change, confirming the specification update from Model 30RAP030 to Model 30RC030 due to new environmental refrigerant regulations. The response confirmed no negative impacts to project budget, schedule, or site layout, as the new unit matches required tonnage, is physically smaller, and carries negligible pricing differences. The contractor's request was marked with no potential cost impact and no potential schedule impact. One attachment from the contractor accompanied this RFI.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION REPORT (RFI)
RFI (Preaward) NO. PAGE NO.
Contractor's Request for Information
REQUESTED BY: Potential Cost Impact
[No] Potential Schedule
Impact [No]SUBCONTRACTOR
: RFI
SUBJECT:DRAWINGS
INFORMATION REQUESTED:
ATTACHMENTS FROM CONTRACTOR: (1 attachment)
NOTE: THE RFI SYSTEM IS INTENDED TO PROVIDE AN EFFICIENT MECHANISM FOR RESPONDING TO CONTRACTOR'S REQUESTS FOR
INFORMATION. IT DOES NOT PROVIDE AUTHORITY TO PROCEED WITH ADDITIONAL WORK. IF THE CONTRACTOR CONSIDERS
THE RFI RESPONSE A CHANGED CONDITION, PROVIDE WRITTEN NOTICE TO THE CONTRACTING OFFICER'S REPRESENTATIVE
IN ACCORDANCE WITH CONTRACT PROVISIONS.
QA REVIEWER'S SIGNATURE DATE
RFI FORM
SOLICITATION NO:
FA6606-26-B-0003
SOLICITATION TITLE:
Repair HVAC Chiller B7087 YTPM 24-0012
DATE REQUESTED:
22 JULY 2026
QUESTION 01: Should the current new Carrier model for this project be 30RC 030 with R-32 refrigerant? (The SOW section 3.1 lists the new chiller as a Carrier model 30RAP 030... this style of chiller is no longer produced)
WARB RESPONSE 01: Yes, we will be updating the chiller specification from Carrier Model 30RAP030 to Model 30RC030 due to new environmental refrigerant regulations. There are no negative ramifications to the project budget, schedule, or site layout, as the new unit matches the required tonnage, is physically smaller, and has a negligible pricing difference.
In short, nothing changes about the installation plan or project scope except the physical unit model itself
PROJECT NAME:
439 CONF/PKB for KTR(s)
1533453186C Inserted Text ff
| RFI_HGC_0001_10.Aug.2020 |
| RFI_HGC_0001_10.Aug.2020_2 |
| 2026-07-23T08:35:49-0400 | |
| NYAMWEYA.JOSHUA.OKARI.1533453186 |
File details come from the government source that posted it. Updated .