This document contains a submittal register and related federal contract opportunity notice for roof repair services. The submittal register outlines requirements for experience documentation, drawings, specifications, inspection reports, warranties, and closeout documents for repair of thermoplastic polyolefin roofing membranes and installation of permanent fall protection systems on Hangar 1 and Hangar 3 at Westover Air Reserve Base. The federal contract opportunity is a pre-solicitation notice for project numbers YTPMs 18-0006 and 18-0007 to accomplish the roof repairs with an estimated period of performance of 300 calendar days from notice to proceed. The contract is set aside for small businesses under NAICS code 238160 for roofing contractors with a size standard of $16.5 million. The solicitation is expected to be issued in July 2020 as a request for proposal with a 30-day response period and mandatory site visit.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SUBMITTAL REGISTER | CONTRACT NO | ||||||||||||||||
| YTPM 18-0007 | |||||||||||||||||
| TITLE AND LOCATION | CONTRACTOR | ||||||||||||||||
| REPAIR BARELL ROOF H3 | CONTRACTOR SCHEDULES DATES | CONTRATOR ACTION | APPROVING AUTHORITY | ||||||||||||||
| ACTIVITY NO | TRANSMITTAL NO | Refence section | DESCRIPTION ITEM SUBMITTED | P A R A G R A P H # | CLASSIFICATION GOVT OR A/E REVIER | SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | ACTION CODE | DATE OF ACTION | DATE FWD AUTH/ DATE RCD FROM CNTR | DATE FWD TO OTHER REVIEWER | DATE FWD FROM OTHER REVIEWER | ACTION CODE | DATE OF ACTION | MAILED TO CONTR/ DATE RCD FRM APR AUTH | REMARKS |
| (a) | (b) | c | (d) | "(e)" | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | |
| SOW | |||||||||||||||||
| Prime Contractor Experience Information, Key Players | 2.7.1.1 | G | |||||||||||||||
| Installer Qualifications | 2.7.1.2 | G | |||||||||||||||
| RRC Information | 2.7.1.3 | G | |||||||||||||||
| RRO Qualifications | 2.7.1.4 | G | |||||||||||||||
| Licensed Structural Engineer Info | 2.7.1.5 | G | |||||||||||||||
| Field Investigation Report | 3.30 | G | |||||||||||||||
| Drawings (TPO Repair) | 3.4.2 | G | |||||||||||||||
| As-built Drawings (TPO) | 3.4.3 | G | |||||||||||||||
| Specifications (TPO) | 3.5.1 | G | |||||||||||||||
| Plan analysis (FP) | 3.6.1.1 | G | |||||||||||||||
| Drawings (FP) | 3.6.1.2 | G | |||||||||||||||
| Specifications (FP) | 3.6.1.4 | G | |||||||||||||||
| Catalog Cuts (FP) | 3.6.1.5 | G | |||||||||||||||
| Contractor Review and Approval by PE | 3.6.1.6 | G | |||||||||||||||
| Project Disks | 3.6.1.7 | G | |||||||||||||||
| Register Roof Observer (RRO) Daily Reports | 4.2.4.1 | G | |||||||||||||||
| Register Roof Observer (RRO) Photographs | 4.2.4.2 | G | |||||||||||||||
| Roof Signs | 4.3.1 | G | |||||||||||||||
| Pre-final Inspection | G | ||||||||||||||||
| TPO Membrane Pre-Final Inspection Report | 6.3.1 | G | |||||||||||||||
| Final Inspection | 7.10 | G | |||||||||||||||
| Certificate of inspection by Permanent Fall Protection Manufacturer | 7.2.1 | G | |||||||||||||||
| Close-Out Submittals | 7.3.1 | G | |||||||||||||||
| Warranty (FP) | 12.30 | G | |||||||||||||||
| General Conditions | |||||||||||||||||
| Badge Requests (439 AW Form 1) | 1.2.B | G | |||||||||||||||
| Dig Safe (if required) | 1.30 | G | |||||||||||||||
| Notification Prior to Construction or Demolition (BWP AQ 06) | 1.80 | G | |||||||||||||||
| Scheduling | 1.10 | G | |||||||||||||||
| Hazardous Material Reporting (439 AW Form 20) | 1.15 | G | |||||||||||||||
| Construction/Demolition Waste Management Plan and Reporting | 1.19 | G | |||||||||||||||
| C/D/W Report | 1.19 | G | |||||||||||||||
| Daily Report | 1.21 | G | |||||||||||||||
| Specifications Attachment B | |||||||||||||||||
| SD-02 Shop Drawings | 1.5.2 | G | |||||||||||||||
| SD-03 Product Data | 1.5.2 | G | |||||||||||||||
| SD-04 Samples | 1.5.2 | G | |||||||||||||||
| SD-06 Test Reports | 1.5.2 | G | |||||||||||||||
| SD-07 Certificates | 1.5.2 | G | |||||||||||||||
| SD-08 MFR's Instructions | 1.5.2 | G | |||||||||||||||
| SD-09 MFR's Field Report | 1.5.2 | G | |||||||||||||||
| SD-10 O&M Data | 1.5.2 | G | |||||||||||||||
| SD-11 Closeout Documents | 1.5.2 | G |