Hangar3 SUBMITTAL REGISTER.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Repair Roofs, Hangar 1 & 3 WARB Federal contract opportunity
Solicitation number
FA660620R0003
Issued by
Department of the Air Force Reserve Command

About this file

This document contains a submittal register and related federal contract opportunity notice for roof repair services. The submittal register outlines requirements for experience documentation, drawings, specifications, inspection reports, warranties, and closeout documents for repair of thermoplastic polyolefin roofing membranes and installation of permanent fall protection systems on Hangar 1 and Hangar 3 at Westover Air Reserve Base. The federal contract opportunity is a pre-solicitation notice for project numbers YTPMs 18-0006 and 18-0007 to accomplish the roof repairs with an estimated period of performance of 300 calendar days from notice to proceed. The contract is set aside for small businesses under NAICS code 238160 for roofing contractors with a size standard of $16.5 million. The solicitation is expected to be issued in July 2020 as a request for proposal with a 30-day response period and mandatory site visit.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SUBMITTAL REGISTERCONTRACT NO
YTPM 18-0007
TITLE AND LOCATIONCONTRACTOR
REPAIR BARELL ROOF H3CONTRACTOR SCHEDULES DATESCONTRATOR ACTIONAPPROVING AUTHORITY
ACTIVITY NOTRANSMITTAL NORefence sectionDESCRIPTION ITEM SUBMITTEDP A R A G R A P H #CLASSIFICATION GOVT OR A/E REVIERSUBMITAPPROVAL NEEDED BYMATERIAL NEEDED BYACTION CODEDATE OF ACTIONDATE FWD AUTH/ DATE RCD FROM CNTRDATE FWD TO OTHER REVIEWERDATE FWD FROM OTHER REVIEWERACTION CODEDATE OF ACTIONMAILED TO CONTR/ DATE RCD FRM APR AUTHREMARKS
(a)(b)c(d)"(e)"(f)(g)(h)(i)(j)(k)(l)(m)(n)(o)(p)(q)
SOW
Prime Contractor Experience Information, Key Players2.7.1.1G
Installer Qualifications2.7.1.2G
RRC Information2.7.1.3G
RRO Qualifications2.7.1.4G
Licensed Structural Engineer Info2.7.1.5G
Field Investigation Report3.30G
Drawings (TPO Repair)3.4.2G
As-built Drawings (TPO)3.4.3G
Specifications (TPO)3.5.1G
Plan analysis (FP)3.6.1.1G
Drawings (FP)3.6.1.2G
Specifications (FP)3.6.1.4G
Catalog Cuts (FP)3.6.1.5G
Contractor Review and Approval by PE3.6.1.6G
Project Disks3.6.1.7G
Register Roof Observer (RRO) Daily Reports4.2.4.1G
Register Roof Observer (RRO) Photographs4.2.4.2G
Roof Signs4.3.1G
Pre-final InspectionG
TPO Membrane Pre-Final Inspection Report6.3.1G
Final Inspection7.10G
Certificate of inspection by Permanent Fall Protection Manufacturer7.2.1G
Close-Out Submittals7.3.1G
Warranty (FP)12.30G
General Conditions
Badge Requests (439 AW Form 1)1.2.BG
Dig Safe (if required)1.30G
Notification Prior to Construction or Demolition (BWP AQ 06)1.80G
Scheduling1.10G
Hazardous Material Reporting (439 AW Form 20)1.15G
Construction/Demolition Waste Management Plan and Reporting1.19G
C/D/W Report1.19G
Daily Report1.21G
Specifications Attachment B
SD-02 Shop Drawings1.5.2G
SD-03 Product Data1.5.2G
SD-04 Samples1.5.2G
SD-06 Test Reports1.5.2G
SD-07 Certificates1.5.2G
SD-08 MFR's Instructions1.5.2G
SD-09 MFR's Field Report1.5.2G
SD-10 O&M Data1.5.2G
SD-11 Closeout Documents1.5.2G