This document contains questions and answers related to Solicitation Number FA568224R0003, a federal contract opportunity for the demolition of a military working dog kennel at Aviano Air Base in Italy.
The key details are:
- The solicitation is for the demolition of Facilities 620 and 625, the military working dog kennel, in Area F of Aviano Air Base, Italy.
- There is a site visit scheduled for April 10, 2024 at 9:00 AM at the LVIS Gate.
- The contractor must have a current SOA certification in category OS23 to be eligible.
- The original period of performance was 120 calendar days, but this has been changed to 180 calendar days due to the potential presence of asbestos that will need to be abated before demolition can proceed in those areas.
- Subcontractor personnel will be granted escort privileges or regular pass requests to access the site as needed.
- Trucks transporting materials to the landfill will need to go through the LVIS Gate for security inspection, which cannot be avoided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA568224R00030003 SF 30.pdf | ||
| QUESTIONS AND ANSWERS 18 APRIL 2024.pdf | ||
| Solicitation Amendment FA568224R00030002 SF 30.pdf | ||
| ASHE22 1012 ADD1 Tech Specs.pdf | ||
| ASHE-22-1012-CCEB-REV1.xlsx | XLSX spreadsheet | |
| Solicitation Amendment FA568224R00030001 SF 30.pdf | ||
| ASHE22 1012 Tech Specs Rev1.pdf | ||
| ASHE-22-1012-CCEB.xlsx | XLSX spreadsheet | |
| AVIANO MASTERSPECS 2020.pdf | ||
| Solicitation - FA568224R0003.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
17 April 2024
REQUESTS FOR INFORMATION FOR PROJECT ASHE 22-1012 DEMO MILITARY WORKING DOG
KENNEL, Fac#620&625, Area E, AVIANO AB, ITALY
Q1. Reference is made to Page 43 2. QUALIFICATION CERTIFICATION Submit current SOA certification for category OS23 classification adequate to cover offeror's amount for projects performance.
May OFFERORS rely on Nominated Key - Subcontractors SOA Certification?
A1. The SOA cer�fica�on OS23 must be possessed by the Offeror as indicated in solicita�on sec�on M.
Q2. Concerning the PACM and ACM, if it is confirmed the presence of asbestos after appropriated chemical analysis, it is, as requested by the solicitation, its disposal before starting the demolition works. With asbestos disposal then, it will be quite sure the necessity of more days than the 120 required by the solicitation to complete the demo works.
A2. In the area where the asbestos presence is found, Contractor shall fence the area, and ini�ate the procedure as required by Italian Law. Contractor can proceed with the demoli�on works where the asbestos is not present. Period of performance is changed to 180 calendar days as per Amendment 2 to the Solicita�on.
Q3. Concerning the reclamation of the septic tank or any other particular work, it will be probably necessary to allowed qualified personnel enter the site, so than an escort pass will be required so as to simplify the entering of subcontractors.
A3. Sep�c tank is old, empty and abandoned. In accordance with Technical Specifica�ons Rev1 paragraph 4, contractor will have to demolish the underground tank and fill the hole with gravel and compact it. In the case during the performance of this project personnel of a sub-contractor needs access, the contractor will be granted escort privileges or regular pass requests will be processed.
Q4. Value the possibility to not enter at Lvis Gate any time with trucks during the transportation to landfills.
A4. It is impossible to avoid inspec�on on LVIS gate as required by US GOV Security Police.