This document contains Questions and Answers related to a federal contract opportunity for the purchase and installation of dormitory furniture for Building 1423 at Aviano Air Base.
The key details are:
- The original technical specifications document has the correct furniture measurements, despite differences observed during the site survey. The bookcase will need to fit safely on top of the desk.
- The desk will require an enclosed central drawer, not just a pull-out tray. The headboard is not a required item.
- The facility has a public use elevator with weight limitations, so the contractor must provide their own means for installation and removal able to reach the 2nd floor. Contractor will be provided space for two mobile dumpers during the work.
- The furniture dimensions remain the same as originally specified. The Air Force cannot provide information on a previous furniture contract.
- The 90-120 day delivery and 6 week installation requirements are based on working days, not calendar days. Delivery and installation are to be performed in the building, which is 2 floors.
- The procurement is for dark oak colored wood, but the Air Force is open to High Pressure Laminate (HPL) wood options.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
1. Are the measurements in the original technical specifications document the same as the measurements of the furniture from the site survey?
a. The measurements stated on the original document are correct. The furniture in the room during the site survey was the old furniture that is being replaced.
2. Are the measurements for the width of three drawer chest and two shelf bookcase may be incorrect if the book case is to be sitting on top of the drawer chest (which per table is smaller)?
a. The bookshelf will be placed on top of the desk and will need to ensure that the desk is wide enough to allow the bookcase to safely sit on top.
3. Are the bed and underbed storage measurements correct?
a. The measurements stated on the original document are correct. The furniture in the room during the site survey was the old furniture that is being replaced.
4. Desk has no drawer but a pull-out shelf for the keyboard. Can you clarify if a drawer is needed or a pull-out tray, and the dimensions?
a. The desk will require an enclosed central drawer directly under the desktop. Pictures attached.
5. Is the headboard a required furniture item?
a. Headboard is NOT a required furniture item.
6. Will there be elevating equipment to transport supplies?
a. The Facility does have a public use elevator for personnel but is limited by weight and potential service outages. Other lifting means for installation/removal must be provided by contractor with the ability to reach European 2nd floor.
7. What storage areas will be available for use during the installation?
a. Dorm Management will provide space for TWO mobile dumpers for the removal/disposal of old items. The space provided will be 2 parking spaces by 5 parking spaces (35.5 feet by 36 feet).
8. Are there restrooms for use by the workers, and if elevators can be used for installation or they must use their own?
a. Removal and Installation crew members will have constant access to public restrooms during the extent of their work hours. Locations will be provided upon their arrival.
b. The Facility does have a public use elevator for personnel but is limited by weight and potential service outages. Other lifting means for installation/removal must be provided by contractor with the ability to reach European 2nd floor.
9. Can the USG confirm the composition of the existing furniture shown during the site visit? Is it also solid wood?
10. During the site visit, a USG representative suggested that the dimensions of the required furniture may have changed. Can the USG confirm when these new dimensions will be published?
a. The dimensions remain the same. Please refer to the answer in question 1.
11. Can the USG confirm that the furniture delivered under solicitation FA568223Q0033 for Building 1422 was also solid wood?
a. 31 CONS Answer: We cannot provide any information with reference to another contract.
12. Should bidders be prepared to offer NDT solutions for each piece of furniture? If not, how will the USG confirm the composition of the delivered furniture?
13. From page 1 of the Technical Specifications document, “Work to be performed on regular working hours Mo-Fri 7:30 through 17:00.” Additionally, page 2 of the Technical Specifications document states, “Total delivery and installation completed between 90-120 days from receipt of order. Installation to be completed in 6 weeks.”
a. Can the USG confirm the “90-120 days” requirement is workdays (Monday through Friday)?
b. Without specific clarification how will the USG evaluate different schedules that may use workdays versus calendar days from different bidders?
c. Can the USG confirm that the “Installation to be completed in 6 weeks” statement means that if all furniture is delivered in 2 weeks, the installation should be completed by the end of 8 weeks?
14. Will the delivery and installation be done in a warehouse or in a building? If it is a building, how many floors are in the building?
15. Do you have photos of the furniture that you would like to procure?
16. When you refer to the dark oak wood, are you referring to the dark oak color?
17. Can you offer HPL wood?