Table 1

CONTRACTOR COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
REPAIR FAC#940A FOR 57RQS, REVISION 1
PURCHASE REQUEST NUMBERPROJECT NUMBER ASHE 18-1058WORK LOCATION Area F, Aviano AB.
LINE NO.MATERIAL PLUS LABOR COST
ITEMUNIT OF
MEASUREQUANTITYUNITTOTAL(6)(7)(8)OTHER DIRECT
COSTSLINE TOTAL
(1)(2)(3)(4)(5)(9)(10)
3. ARCHITECTURAL/STRUCTURAL/CIVIL WORKS
1DOORS REMOVALSIT. No.
Art. n.3.1EA4
2ASBESTOS REMOVALIT. No.
Art. n.3.2L.S.1
3METAL PLATES REPLACEMENTIT. No.
Art. n.3.3L.S.2
4SUSP.CEILING REMOVALIT. No.
Art. n.3.4L.S.1
5INTERNAL REMOVALSIT. No.
Art. n.3.5L.S.1
6VINYL FLOOR REMOVALIT. No.
Art. n.3.6SM80
7BASEBOARD REMOVALIT. No.
Art. n.3.7LM500
8NEW VINYL FLOORIT. No.
Art. n.3.8SM80
9FLOOR WASHINGIT. No.
Art. n.3.9SM360
10NEW BASEBOARDIT. No.
Art. n.3.10LM400
11NEW SUSPENDED CEILINGIT. No.
Art. n.3.11SM360
12INTERIOR PAINTIT. No.
Art. n.3.12SM1200
13NEW DOORSIT. No.
Art. n.3.13L.S.1
14RESTORATION OF ELECTR.ROOM 65IT. No.
Art. n.3.14LS1
15CORE DRILLING 200mm DIAIT. No.
Art. n.3.15EA7
16CORE DRILLING 100mm DIAIT. No.
Art. n.3.16EA3
17CORE DRILLING 50mm DIAIT. No.
Art. n.3.17EA4
18RESTORATION EXTERNAL WALLSIT. No.
Art. n.3.18SM400
CONTRACTOR COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
REPAIR FAC#940A FOR 57RQS, REVISION 1
PURCHASE REQUEST NUMBERPROJECT NUMBER ASHE 18-1058WORK LOCATION Area F, Aviano AB.
LINE NO.MATERIAL PLUS LABOR COST
ITEMUNIT OF
MEASUREQUANTITYUNITTOTAL(6)(7)(8)OTHER DIRECT
COSTSLINE TOTAL
(1)(2)(3)(4)(5)(9)(10)
19NEW CONCRETE PADIT. No.
Art. n.3.19SM190
20CONCRETE PIT & CAST IRON COVERIT. No.
Art. n.3.20LS1
21BLOCK OPENING RMS 58/57IT. No.
Art. n.3.21L.S.1
22TRAFFIC METAL BUMPERSIT. No.
Art. n.3.22EA8
23CONCRETE RAMPIT. No.
Art. n.3.23LS1
24REPAIR OF MAIN ENTRANCE & FLASHINGIT. No.
Art. n.3.24LS1
25ANTENNA POLE RESTORATIONIT. No.
Art. n.3.25LS1
26CYPHER LOCKS INSTALLATIONIT. No.
Art. n.3.26EA10
27RELOCATE 2EA TRAILERSIT. No.
Art. n.3.27LS1
28SCAFFOLDINGIT. No.
Art. n.3.28LS1
29ENAMEL METAL PAINTIT. No.
Art. n.3.29SM40
30DEMOLITION OF CONCRETE SLABIT. No.
Art. n.3.30LS1
31REMOVAL & DISPOSAL OF MINERAL WOOLIT. No.
Art. n.3.31KG200
32INTERIOR COUNTER WALL, RM. 47IT. No.
Art. n.3.32SM10
33GENERAL REPAIR WORK, RM 54IT. No.
Art. n.3.33LS1
34BLOCK WALL OPENING, RM 63IT. No.
Art. n.3.34LS1
35NEW UNDERGROUND ELECTRICAL DUCT LINEIT. No.
Art. n.3.35LM115
TOTAL 3. ARCHITECTURAL/STRUCTURAL/CIVIL WORKS
CONTRACTOR COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
REPAIR FAC#940A FOR 57RQS, REVISION 1
PURCHASE REQUEST NUMBERPROJECT NUMBER ASHE 18-1058WORK LOCATION Area F, Aviano AB.
LINE NO.MATERIAL PLUS LABOR COST
ITEMUNIT OF
MEASUREQUANTITYUNITTOTAL(6)(7)(8)OTHER DIRECT
COSTSLINE TOTAL
(1)(2)(3)(4)(5)(9)(10)
4. ELECTRICAL WORKS
36REMOVAL OBSOLETE ELECTRICAL SYSTEMIT. No.
Art. n.4.1L.S.1- €
37SAVE AND RE-INSTALL LIGHTING AND FIRE ALARMIT. No.
Art. n.4.2L.S.1- €
38REMOVAL ELECTRICAL PANEL rm65IT. No.
Art. n.4.3L.S.1- €
39THERMAL-MAGNETIC BREAKER SUBSTATION 947IT. No.
Art. n.4.4L.S.1- €
40NEW MAIN ELECTRICAL PANEL RM65IT. No.
Art. n.4.5L.S.1- €
41RESTORATION ELECTRICAL SYSTEM RM65IT. No.
Art. n.4.6L.S.1- €
42NEW SECONDARY ELECT.PANEL EXTERNAL WALLIT. No.
Art. n.4.7L.S.1- €
43ALUMINUM BOX MM 410X315X150IT. No.
Art. n.4.8EA4- €
44EXTERIOR LIGHT FIXTURESIT. No.
Art. n.4.9EA5- €
45ELECTRICAL METAL TUBING (EMT)IT. No.
Art. n.4.10L.S.1- €
46ELECTRICAL FEEDING LINESIT. No.
Art. n.4.11L.S.1- €
47COPPER GROUNDING SYSTEMIT. No.
Art. n.4.12L.S.1- €
TOTAL 4. ELECTRICAL WORKS- €
5. MECHANICAL WORKS
48REMOVALSIT. No.
Art. n.5.1L.S1- €
49CHILLER RELOCATIONIT. No.
Art. n.5.2L.S1- €
50ELECTRICAL FEEDING LINESIT. No.
Art. n.5.3L.S1- €
51STAINLESS STEEL PIPINGIT. No.
Art. n.5.4L.S1- €
52NEW WATER STORAGE TANK 800LTIT. No.
Art. n.5.5L.S1- €
53NEW TWIN PUMPSIT. No.
Art. n.5.6L.S1- €
CONTRACTOR COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
REPAIR FAC#940A FOR 57RQS, REVISION 1
PURCHASE REQUEST NUMBERPROJECT NUMBER ASHE 18-1058WORK LOCATION Area F, Aviano AB.
LINE NO.MATERIAL PLUS LABOR COST
ITEMUNIT OF
MEASUREQUANTITYUNITTOTAL(6)(7)(8)OTHER DIRECT
COSTSLINE TOTAL
(1)(2)(3)(4)(5)(9)(10)
54BUTTERFLY AND BALL VALVESIT. No.
Art. n.5.7L.S1- €
55AHU RESTORATIONIT. No.
Art. n.5.8L.S1- €
56ANTI FREEZING COMPOUNDIT. No.
Art. n.5.9L.S1- €
57GENERAL CHECK-UP OF 2 CHILLERSIT. No.
Art. n.5.10L.S1- €
57NEW DRINKING FOUNTAINIT. No.
Art. n.5.11EA1- €
TOTAL 5. MECHANICAL WORKS- €
6. COMM WORKS
58OSP RM55 OPTIC FIBER WORKSIT. No.
Art. n.6.1L.S1- €
59ISP RM54 OPTIC FIBER WORKSIT. No.
Art. n.6.2L.S1- €
60ARMAG OPTIC FIBER WORKSIT. No.
Art. n.6.3L.S1- €
61OLD DATA OUTLETS REMOVALIT. No.
Art. n.6.4L.S1- €
62NEW PATCH PANELSIT. No.
Art. n.6.5L.S1- €
63WIRE MESH CABLE TRAYIT. No.
Art. n.6.6L.S1- €
64CAT 6 DUAL OUTLET BOXIT. No.
Art. n.6.7EA51- €
65ALUMINUM BOX IP66 MM410X315X150IT. No.
Art. n.6.8EA3- €
TOTAL 6. COMM WORKS- €

TOTAL WORKS - €

image1.png image10.png image2.png image3.png image4.png image5.png image6.png image7.png image8.png image9.png

File details come from the government source that posted it.