FA568218R0002 57th RQS/HMU TEMPORARY FACILITIES LEASE AT MIKE LOOP, AREA F, AVIANO AIR BASE, ITALY

ANSWERS TO QUESTIONS 31 OCTOBER 2017

1Q) FACTOR 2 TECHNICAL shows 4 items as necessary requirements for Technical Acceptability of the submitted proposals:

1. Initial Installation Proposed Duration and Summary Schedule;

2. Initial Installation Management Approach;

3. Experience;

4. Lease Management Approach Can you confirm the above are the only items to be submitted and subject to the Government award criteria?

1A)The above mentioned documents are the ones that will be evaluated as Technical Factor.

In addition there are all the other documents required by the istant solicitation.

2Q)At page 6 of 21 of PWS para 2.1 QC Plan the following statement: “…A copy of the QCP shall be submitted with the contractor’s proposal.” is in conflict with FACTOR 2 instructions. No page counts, instructions or evaluation criteria for award are being provided to bidder in reference to this item.

Please clarify whether a QC plan is to be submitted or not with proposal.

2A) In accordance to Addendum to FAR 52.212-1, the Quality Control Plan (QCP) is one of the document that the offeror must submit with the proposal in order to be determined responsive (see Amendment#1 to Solicitation#FA568218R0002).

3Q) What is the width of the Mezzanine with will be in the fabric structure?

3A) The mezzanine structure that will be installed by the Government at a later date is 14m x 11m x 7m.

4Q) Is it possible to distribute the .dwg files for the drawings?

4A) No .DWG files will not be provided. Contractor is requested to input the layout using their systems modular dimensions.

5Q) We respectfully request an extension for the closing date until 8 Nov 2017.

5A) We are considering to extend the closing date of Solicitation#FA568218R0002.

6Q) In the subject solicitation at page 53 of 56 Section L and M are mentioned but they cannot be found. Can the Gov. please provide them or indicate where they are located in the solicitation.

6A) In accordance with Amendment#2 to Solicitation#FA568218R0002 Section M and Section L have been substituted with the proper verbiage.