FA568218R0002 57th RQS/HMU TEMPORARY FACILITIES LEASE AT MIKE
LOOP, AREA F, AVIANO AIR BASE, ITALY
ANSWERS TO QUESTIONS 08 NOVEMBER 2017
1Q) Are the water coolers supposed to be contractor supplied? If yes, do you have any specifications?
1A) Yes, these should be wall mounted or floor mounted water coolers connected to the domestic water supply line.
2Q) In Appendix C, page 4, we are having difficulties identifying the “No. 5 – Enclosed Office (9 square meters). We have identified 3 of the 5 which are the OPS/SUPT, DO and ADO rooms. Where are the other two?
2A) The list reads for the second floor:
No. 1 Communications – 15 sm No. 1 DOX/MSN Plan - 215 sm No. 1 OPS/Supt – 9 sm No. 1 DO – 9 sm No. 1 ADO – 9 sm No. 1 CCV – 15 sm No. 1 OPS – 108 sm No. 1 DOT – 50 sm No. 1 Men – 30 sm No. 1 Custodial – 3 sm No. 1 Storage – 3 sm No. 1 Women – 15 sm No. 3 Team Room with Open Office (46 sm), Enclosed Office (9 sm), and Conference Room (15 sm) – 70 sm No. 1 Breakroom – 55 sm No. 1 CSS/Reception – 70 sm No. 1 Conference Room- 180 sm No. 2 Enclosed Offices (1 SGT, CEM) – 15 sm No. 1 Enclosed Office (CC) – 20 sm No. 1 Corridor – 250 sm
3Q) Is the room Marked CCV the 3rd 15m² room?
3A) Yes, See list above.
4Q) Is there a floor drain required in the ventilation room on Level 1 of the 57th Admin
Office?
4A) Yes, a floor drain is required.